Praneev Atram (PGP30161) Sakshi Jain (PGP30167) Sneha Vinherkar (PGP30173) Sonika Angilin (PGP30174) Vishnu Chauhan (PGP30178) Vivekanandan KK (PGP30179) Vivek Kumar Gupta (PGP30180) IMPORTANCE OF POWER Human
Roti
Bijli Makaan Kapda 12% 17% 9% 2% 1% 59% Renewable Energy Hydroelectrici ty Natural Gas Nuclear Oil Coal DEMAND AND SUPPLY OF POWER IN INDIA
HIERARCHY FOLLOWED IN POWER INDUSTRY IN INDIA
Public Sector enterprises: NTPC -Generating Company, PTC-Trading Company, POWERGRID-Transmission Company Undertakings owned by Central government: DVC Regulators: Appellate tribunal for electricity, Central Electricity Regulatory Commission
PUBLIC AND PRIVATE INDUSTRIES IN POWER SECTOR NTPC - 43,128 MW Reliance Power Limited-33,480 MW Tata Power Co. Ltd -8613 MW Adani Power Limited- 7920 MW Suzlon Energy-584 MW
POWER TARIFF REGULATORY BODIES IN INDIA The Central Electricity Regulatory Commission (CERC) State Electricity Regulatory Commission (SERCs) THE MAIN FUNCTIONS OF THE CERC
To regulate tariffs in the power generating companies CERC regulates the inter-state transmission of energy which includes tariff of the transmission utilities. Indian Electricity Grid Code (IEGC), Availability Based Tariff (ABT) Facilitate inter-state trading
ECONOMIC IMPACT OF NEW CERC RULES ON NTPC Incentives based on plant load factor (PLF) rather than plant availability factor (PAF). The CERC has also lowered the heat rate standard for coal-based plants to 2,375kCal/kWh from 2,400kCal/kWh. It is forcing the power plant to be more efficient ANALYSIS OF ECONOMIC IMPACT OF NEW CERC DEVIATION SETTLEMENT MECHANISM ON SSTPS POWER PLANT NTPC LTD. SCOPE OF ANALYSIS The change in economic impact due to unplanned shutdown of thermal power units
The change in breakeven frequency for unscheduled interchange of power by equating marginal cost to marginal revenue.
ABOUT SINGRAULI SUPERTHERMAL POWER STATION- NTPC LIMITED It consists of 2 x 500 MW units and 5 x 200 MW units
Uses Coal as fuel DEVIATION SETTLEMENT MECHANISM Every power producer declares its generation capacity one day in advance to load dispatch centers, its called Declared Capacity (DC)
Load Dispatch Centers tell in advance how much each power plant should produce according to time , its called Scheduled Generation (SG)
The actual power generated by the power producer is called Actual Generation (AG)
The target of load dispatch centers is to maintain grid frequency with in a narrow band for grid stability , currently its revised to 49.95 to 50.05 Hz
Power generating stations are rewarded or penalized monetarily for under/over injection i.e Deviation (SG AG) of power based on the Grid Frequency ECONOMIC IMPACT OF THERMAL POWER UNIT TRIPPING In this table we have analysed changes economic losses due to tripping of one unit at a time i.e. either 500MW unit or 200 MW unit with varying frequency 2014 2010 2014 2010 2014 2010 At Frequency(Hz) 50 50 49.94 49.94 50.05 50.05 Charges of deviation(Paisa/kWh) 178 155 303.04 201.5 0 124 Scheduled Generation(MW) 1945 1945 1945 1945 1945 1945 If one 200 MW unit trips Scheduled Generation for next 45 minutes(MW) 1945 1945 1945 1945 1945 1945 Actual Generation for next 45 minutes(MW) 1755 1755 1755 1755 1755 1755 Total deviation(MW) 190 190 190 190 190 190 Deviation charges(Lacs) 2.54 2.21 4.32 2.87 0.00 1.77 Additional Deviation charges(Lacs) 0.11 0.09 0.18 0.12 0.00 0.07 Total loss (Lacs) 2.64 2.30 4.50 2.99 0.00 1.84 If one 500 MW unit trips Scheduled Generation for next 45 minutes(MW) 1945 1945 1945 1945 1945 1945 Actual Generation for next 45 minutes(MW) 1465 1465 1465 1465 1465 1465 Total deviation(MW) 480 480 480 480 480 480 Deviation charges(Lacs) 6.41 5.58 10.91 7.25 0.00 4.46 Additional Deviation charges(Lacs) 3.47 3.02 5.91 3.93 0.00 2.42 Total loss (Lacs) 9.88 8.60 16.82 11.18 0.00 6.88 KEY OBSERVATIONS If presently unit trips at frequencies above 50.05 Hz there is no loss due to deviation charges ,but previously there were charges/penalties corresponding to the same event.
Also we see that if unit trips at frequencies below 50.05 Hz the penalties or deviation charges are higher now as compared to before.
The new tariff rules have led to a better frequency management of electricity grid. Comparative analysis of new Deviation Settlement Mechanism (2014 vs 2010) In this analysis we are comparing the CERC (Unscheduled Interchange charges and related matters) (Amendment) Regulations, 2010 with the new CERC (Deviation Settlement Mechanism and related matters) Regulations, 2014 -400 -200 0 200 400 600 800 1000 49.4 49.5 49.6 49.7 49.8 49.9 50 50.1 50.2 50.3 D E V I A T I O N
C H A R G E S
( P A I S E / K W H )
GRID FREQUENCY (HZ) Comparative Analysis of Deviation rates wrt Frequency Charges for Deviation (Paise/kWh) Charges for Deviation (Paise/kWh) ANALYSIS OF BREAKEVEN FREQUENCY AT NEW TARIFF RATES(2014) VS OLD TARIFF RATES(2010) The selling price for power produced at Singrauli Super Thermal Power Station (SSTPS), Shaktinagar, Uttar Pradesh is 165 Paisa per Unit (kWH) and the marginal cost of power production is 111 Paisa per Unit (kWH) -50 0 50 100 150 200 250 300 49.9 49.95 50 50.05 50.1 50.15 50.2 D E V I A T I O N
C H A R G E S - M A R G I N A L
R E V E E N U E
( P A I S E / K W H )
GRID FREQUENCY (HZ) Breakeven frequency for New(2014) vs Old(2010) Tariff Rules Charges for Deviation (Paise/kWh) Charges for Deviation (Paise/kWh) Marginal Cost of Power production (Paise/kWh) KEY OBSERVATIONS At breakeven frequency the marginal revenue (MR) realized is equal to the marginal cost (MC) of power generation.
For a power producer its profitable to generate extra power only till its MR is greater than MC else it should stop generating extra power above the scheduled generation.
From this graph we see that under New tariff rules (2014) the breakeven frequency (New) is 50.02 Hz while under that of Old tariff rules (2010) the breakeven frequency (Old) was 50.06 Hz.
Thus ideally now Singrauli Super Thermal Power Station (SSTPS) should not generate any extra power if frequency is above 50.02 Hz
Short term forecasting of Power demand in DELHI based on daily average temperature Data Source Average temperature/day of Delhi in August 2014 (IMD website) Anticipated demand for power has been obtained State Load Despatch Centre, DELHI website for the past one month (August 1, 2014 to August 29, 2014). Details of the Regression analysis are as following: Regression Statistics Multiple R 0.528239562 R Square 0.279037035 Adjusted R Square 0.248996911 Standard Error 244.4990908 Observations 26 Power Demand = f(Daily Average Temperature) Power Demand Function=> CONCLUSIO N Final results Power Demand (MW)=94.72*Daily Average Temperature(Temp) +977.98 is the best fit line with the 95% confidence level with standard error of 31.08.
This model is able to explain 28% of variation in the data available.
As the temperature increases, power demand increases. Thank you