GOLDEN CLUSTERS PROJECT IMPLEMENTATION

STRATEGY, PROJECT STRUCTURE & JOINT PROCESS

Regional Joint Kick Off Meeting


30th March 2011
Version 1.0

STRICTLY CONFIDENTIAL

Golden Clusters Project Governance Structure

JSC

Joint Execution
Management
(JEM)

Project Rainbow PMO

Business stream

Technical stream

Celcom PM-Shahrizal

DiGi PM-Yeerudy

Property-Azahar

Property - Vaani

RAN - Ikhsan

JSC (HOD or CXO level)

Regular
interactions
and weekly
meetings

Weekly
reports and
fortnightly
meetings

RAN - Laavenia

Tx Sulaiman

Tx - Amirullah

CME - Roshidi

CME - Suresh

I&C - Hafez

I&C - Suresh

Ops Mohd Yusof

Ops - Gunalan

Finance

Finance

Project Support

Project Support

PMC

JET

SUPPORT FROM REGIONAL RAINBOW TEAM


CELCOM
DiGi representatives
for Rainbow (GC)

representatives
for Rainbow (GC)
Head : Rosli Mansor
HP No :0194814333

Supervisors : Chan HG (Ipoh) /


Teh KG (Prai)

Emial ID :rosliman@celcom.com.my

HP No :
0165500413/0164227788

Cme

Emial ID :
hgchan@png.digi.com.my /
kgteh@png.digi.com.my

Email ID :
shamsuddin_nazardin@celcom.com.my

: Shamsudidn Nazardin

HP NO :0194481900

Property: Ahmad Zaini Yakop

REP 1 : Yong Teck Wei (Ipoh)

HP No :0194771900

HP No : 0165232394

Emial ID :zaini_yakop@celcom.com.my

Emial ID :
twyong@png.digi.com.my

I & C: Mizazuddin

REP 2 : Chung Kok Fu (Ipoh)

Emial ID :mizazuddin@celcom.com.my

HP No : 0165508693
Emial ID :
kfchung@png.digi.com.my
REP 3 : Jasmizal (Prai)
HP No : 0164164419
Emial ID :
jasmizal@png.digi.com.my

HP No :0195713060

Operation : Mohd Shapia


HP No

: 019574900

Email ID

: shapia@ celcom.com.my

Tx: Al Helmi
HP No :0195702444

Emial ID :alhelmia@celcom.com.my

Overview of Golden Cluster Project Execution

224 SITES

Implementation
for bucket 770,
1212 & 2206 to
be done by PMC

PERAK

GOLDEN
CLUSTER
Survey for
bucket 2206 to
be done by PMC

50/50 split
between
Celcom & Digi
Survey for
bucket 770 &
1212 to be done
by Celcos
Contractors

Golden Cluster Implementation Strategy

Peninsular Malaysia

Perak cluster has been selected for GC since consist


of various clutter types (urban, sub-urban and rural)
hence able to reflect all probable rationalization scenarios

Penang

GC implementation divided into 5 phases


to start from rural area towards urban area. [1 (A6Kuala Kangsar & A5-Matang), 2 (A4-Kerian & A9Teluk Intan), 3 (A10-Setiawan & A11-Kampar), 4
(A8-Ipoh Selatan), 5 (A7-Ipoh Utara)]
to start from low risk to high risk (quality, coverage &
capacity- Network & customer impact

Site survey to start based on :


Implementation cluster according to proposed phase,
Prioritize the infill pair sites [14 Infill sites A5(2),
A4(1), A9(3),A10(2), A11(3), A8(1), A7(2)]

Perak

KL

JB

IMPLEMENTATION PHASE
Pha
se

Cluster

Cumulat
ive

A6, A5

25%

25%

A4, A9

22%

47%

A10, A11

18%

65%

A8

15%

80%

A7

20%

100%

Criteria

Follow as per RAN


implementation
criteria

Golden Cluster (Detail & Analysis)


Sites
Bucket

Scope of work

770
1212

Negotiate rental
Negotiate rental

2206

+ Terminate /Rationalize sites


Total

DiGi move to
Celcom
(# of sites)

Celcom move to
DiGi
(# of sites)

Total
68
48

65
65

43
43

108
224

Access Transmission
Bucket
770
1212

Scope of work
1. Redesign the network
2. Upgrade existing IP
3. Swap/refresh E1 to IP

2206
Total

Celcom as
provider
(# of links)

DiGi as provider
(# of links)

Total

23
25

45
23

68
48

65
113

43
111

108
224

TRANSMISSION
Criteria
1

Cost

Cold Swap vs Hot Swap - to avoid revenue loss by


minimizing downtime

Fiber - existing infra or 3rd party leasing with


sufficient capacity is the highest priority to remain.
Reduce AA cost.

Sufficient capacity ( m/w + aggregation) highest priority is given to the sites with sufficient
E2E capacity

route thru microwave only to BSC/RNC will take the


highest priority & follow by mw + fiber/ 3rd party
leased line.

Smaller nos of hops to single Hub - To reduce


unnecessary multiple hops to hub/collector point.
Will reduce AA cost, implementation time and
reduce element .

Bucket 770 is the highest priority. 1212 & 2206

Shortest route / path to BSC/RNC - Shortest

Quality

will follow accordingly. Able to meet target within


timeline.

Time

AGREED JOINT PROCESS

The Agreed Joint Process is a consolidated process between both DiGi and Celcom based on
our internal practices.

Network collaboration will leverage from common network


to maximize cost saving

DiGi
Celcom
Shared
Interconnect
Upgrade to support 3G

Effective Access Link Reduction at Hub site (Concept)

Aggregation

AS IS = 10 links at Hub

Hub

TO BE = 6 links at Hub

GS DC R

GS DC R

Maintained
Shared site

1.
2.

GS DC R

Maintained
Shared site

GS DC R

GS DC R

Shared Sites

GS DC R

Maintained
Shared site

GS DC R

GS DC R

Maintained
Shared site

All shared sites will have effective reduction of one access link towards Hubs.
Hub site will have more effective reduction of links towards the shared sites
when there are more shared sites linking to the Hub site.

QUESTIONS & ANSWER SESSION

Project Rainbow: CME


Regional Joint Kick Off Meeting
30th March 2011
Version 1.0

STRICTLY CONFIDENTIAL

Civil, Mechanical and Electrical Preparedness

Jet Project

Civil, Mechanical and Electrical


The objective is to share wherever possible on all infrastructures. The host shall prepare all the
necessary infrastructure for the visitor. These are as below but not limited to:
Cabin/Outdoor Plinth Space
AC and DC power system
DCPDB/ACPDB
Tower/Monopole
Indoor sites

Space inside cabin will be shared

DC power systems will have to be upgraded to cater the additional loads, if requires
cabin shall be strengthen

Shall indoor space be insufficient, the visitor will install outdoor equipments

The TNB incoming power supply will be split to cater the outdoor PDU for the visitor
Outdoor sites

Outdoor plinth will be extended if possible

The visitor shall install their equipment outdoor as well

Equipment shall be placed back to back to minimize the equipments footprint

The TNB incoming power supply will be split to cater the outdoor PDU for the visitor

If space is a constraint, the outdoor PDU shall be shared

Civil, Mechanical and Electrical Preparedness

Towers

Jet Project

Towers or monopoles will be shared


Tower analysis shall be performed if necessary
Tower strengthening shall be done if required or stated in the tower analysis report

New sites (infill)

All infrastructures will be built and shared

QUESTIONS & ANSWER SESSION

Project Rainbow: SA
Regional Joint Kick Off Meeting
30th March 2011
Version 1.0

STRICTLY CONFIDENTIAL

SITE ACQUISITION STRATEGY


Own Build Sites
Strategy to adopt to ensure no rental increment, possible rental reduction and
securing long term tenancy agreement

Jointly develop communication plan towards property owners


a.
b.

c.
d.

To develop communication/ negotiation strategy based on consolidation plan.


Up front engagement to inform of owner of multiple activities throughout the year with the
following objectives:
I.
Commitment towards maintaining the rented premises identify defects, fix and
beautify the site
II. Commitment towards Deep Green initiative by modernizing equipment towards smaller
footprint and less power consumption
Subsequent access arrangements to make reference to aforementioned initiative
Jointly develop a generic Technical Proposal to be used whenever requested by property
owners
Jointly develop standard communication line and FAQ materials to be shared with property
agents

SITE ACQUISITION STRATEGY


Own Build Sites
Continue
Jointly develop standardized commercial offers
a.
b.
c.

Develop rental capping rates based on the states/ area property value
Develop a standardized terms and conditions in the tenancy agreement
Develop other commercial offers to achieve further rental reduction eg. bulk payment for
better discount, long term agreements etc.

Jointly develop site securing boundary


a.

Avoid creating unnecessary competition in the same area

Jointly develop site acquisition strategy for difficult high profile areas
a.
b.

Jointly develop technical solutions to address the constraints at these areas


Leverage on each others strengths to secure the site eg. Celcom strong tie with
government, Celcom with TM etc

Joint sourcing for 3rd party property agents


a.
b.

Manage and control the site securing cost


Manage and control quality of work and performance of property agents

SITE ACQUISITION STRATEGY


Own Build Sites
Continue

Ensure to be seen as ONE maintenance team


a.

Explore the possibility of a consolidated field maintenance team or introduce


one field maintenance party

Jointly develop technical solutions


a.
b.

Jointly develop technical solutions to reduce equipment footprint and antenna


poles (can also leverage on modernization)
Evaluate different site provider solutions (Pylons, payphones, traffic lights etc)

QUESTIONS & ANSWER SESSION

Project Rainbow: RAN


Regional Joint Kick Off Meeting
30th March 2011
Version 1.0

STRICTLY CONFIDENTIAL

The Radio Planning process is as shown in the figure below:-

Detailed
Planning

Site Survey

TP Approval

Capacity and future expansion study to provide equipment information


for survey
Study of existing coverage and key market area
Survey to verify existing equipment and conditions at site
Technical proposal to indicate RAN equipment space availability for
Visitor Party at site
Detailed coverage study based on TP including coverage prediction
plots
Joint Discussion of both JET Radio counter parts with regards to
antenna height ,coverage and RAN equipment upon TP review.

The optimization process is as shown in the figure below:-

Single Site
Verification

Optimization

Performance
Monitoring

Verify the cell configuration in the network


Verify the site accessibility and quality

Single Site Optimization(up to 1st tier neighbors of a new


site)
Cluster Optimization ( may consist one or more new sites)

Monitor the statistical performance


Ensure it achieves the KPIs

The types of verification and drive test methodology are dependent on


the types of sites, GERAN and/or UTRAN.
Site verification work and drive test will be carried out in the non-busy
hours to retain excellence customer experience.
The Supplier shall propose and perform the necessary optimization
works such as antenna re-engineering, network tuning, parameter
changes, new feature implementation and new coverage enhancement
plans to achieve the KPIs.
The Single Site Verification forms , Single Site Optimization, Cluster
Optimization and statistical KPIs can be found from the attachment.