POLANDS A2 MOTORWAY
Group no. 08
Kumar Prashant (17/023) | Pritam Karmakar (17/031) | Sanjeet Kumar (17/042)
2
Project Risk Mitigation Current Structure
Major Risk
Extremely conservative approach by the WSA, lowering the value of driver time, perceived
operating costs, and higher speeds on alternative routes compared to the previous estimates which
resulted in 16% decline in revenue in 2002 and a 50% decline in 2022. All these was done to check
the project viability under extreme conditions
Use of interest rate swaps to convert the floating rate to a fixed rate
Innovative cash sweep mechanism to ensure that extra cash flow was used to pay down senior
debt or to create a sinking fund account for repayment of the zero coupon bonds
5. Default in payment of
Mezzanine debt and zero
coupon bonds
The bonds were backed by guarantee from the Polish government for up to 800 million Euros in
maximum future value for the entire life of the concession. Thus AWSA would be able to refinance
the bonds
3
Project Risk Mitigation
Major Risks
Risk bearers
Factors
AWSA, Development
Company (DC), Operating
Company
AWSA, Development
Company (DC), Operating
Company
This too as the above risk, would lead to deviations in the revenue
forecasts, which might lead to the same risks of shortfall in
meeting the operational expenses and service debt
This would generate less than expected cash flow and hence
reduce the debt service coverage ratio or even make the SPV go
bankrupt
5. Default in payment of
Mezzanine debt and zero
coupon bonds
4
Project Risk Mitigation
Major Risk
It is proposed to provide stimulants to the countrys economic growth through government business plans and
foreign direct investment (from other EU countries specially).Tie the tariff plan with the rates of inflation or the
GDP growth rate to promote the countrys industrial development.
Engage advisory firm with prior relevant experience. Enter into agreements with banks to obtain mezzanine
debt and short term debt to meet the difficulties of the start-up phase of the project. Involve other international
firms to get a more accurate estimate for future traffics, incorporating the predictions on human development
and industrial advancements.
To diversify the interest rate risk it is recommended to issue fixed-rate bond nominal pegged to inflation, so as
to ensure stability in the project. In addition, it would be useful to ask for help to the European Community and
the European Central Bank for an accurate rating of the project and the opportunity to be well received in the
market of public savings.
Monitor annually the performance of the cash flow and adjust the estimates in terms of new variables that come
into play.
5. Default in payment of
Mezzanine debt and zero
coupon bonds
Identify a possible exit strategy in case the project does not go through. hypothesize the entry of a private
investor determines that the units of the Government of Poland in order not to damage his reputation.
5