KOM - Amal HRSG Final
KOM - Amal HRSG Final
PROJECT
C311/333
TOPIC
13.30 to
Assembly
13.40
13.41
Welcome Address
13.50
13.51- 14.10 Introduction of PDO & AHEC
delegates
14.11
Project Introduction
14.20
14.21
15.00
15.01
15.20
15.21
15.30
Kick-off Presentation
SPEAKER
PROJECT
MANAGER
AHEC
AHEC & PDO
Discussions
Close Out
AHEC
Project
Owner
EPC Contractor
Location
:
South of Oman and approximately 1 KM to the
Existing Amal Sub station
Scope
Contract Value
Duration
660 Days
Start Date
21-Mar-12
Completion
10-Jan-14
South west of
To meet the future steam demand in AMAL West field, the Company
plans to install a Heat Recovery Steam Generator unit at AMAL Power
Plant. The HRSG shall be installed at the back end of an existing GE
Frame 9E Gas Turbine with a target net average calendar day per year
steam production of 6,000 tonnes per day at a delivery pressure of
100 barg and 80% quality.
SCOPE OF WORK
HVAC System.
Project Manager : Shall be overall responsible for the complete project and
focal point for PDO for execution of the project. His responsibility includes
Engineering, Procurement, Project Management, Construction, Safety,
Contract
Management and Quality till successful completion of the
project. All other
personnel w.r.t. project execution will be under his guidance as per the project
organization chart.
*
10
Krishnaraj G B
Murali Krishna
M N Tamodharan
Karthikeyan
Girish
Arun Roshan DSouza
Kopula Sudakhar
Binil Mohan
Design Verification
FEED Documentation Review & Verification to ensure
*
*
*
*
Design Review
HAZOP Review
SAFOP Review
IPF Review
12
Engineering
* Mott Macdonald / TR Engineering to be finalised as a Design consultant
* All Engineering will carried out at Design consultant office at Muscat for the entire
project
Procurement
*
13
Planning will be monitored since start of the project to the end of the project. The
monitoring of the project is the continuous process.
14
Acceptance test will be carried out in accordance with the requirement of C6- 21
and ISO 2314. During this acceptance test the plant will be operated by
company staff.
15
Final Documentation
*
As Built Drawings.
Commissioning Reports.
16
17
Site Establishment
Office & Camp Facilities: Existing Facilities of Amal power project shall be used
for Amal HRSG project. All office and camp facilities to the company personnel
will be provided as specified in C6-29.
Site office: Existing office facility will be used for this project.
18
Material lay down area shall be used for storing of materials in identified areas
for different class of materials.
19
Living Accommodation:
20
21
22
23
2.
3.
24
Catering : Reputed catering contractor for this project has already been
identified.
25
All equipment & materials including spare parts at the project site shall be
received by AHECs authorised personnel. Upon receipt, materials will be
inspected for specification, quantity, quality, shipping damage, certification of
approval and conformity to purchase order. Reporting on damages, if any, for
possible insurance claim / corrective action.
Material shall be handled with great care and protected from the impact of
throwing, dropping, dragging, bumping and hitting which may damage the
material or coating.
Materials shall be lifted by suitable equipment with non-abrasive wide nylon pipe
slings or special lifting hooks.
26
Security:
Site security shall be arranged by AHEC. we shall appoint Security staff for the entire
duration of the project. The sources of Local Security will be done through Local
Wali / PDO authorities,
27
HSE
STOP Implementation
Journey Management System/Journey Transit Point at Haima & AHEC IZZ Yard
with rest room facilities including for PDO.
28
HSE
Addresses all issues including Legal and other requirements in HSE Plan.
Amal HRSG project addressed life saving rules for site implementation.
29
Subcontracting:
Identified subcontract areas are as follows:
NDT
Insulation.
Earth Works
HVAC Works
Catering Services
Road Works
30
Engineering Contract Quality Plan will be prepared in compliance with ISO 9001-2000
Document & Drawing control register.
Preparation of Engineering documents & drawings.
Single Discipline Checks (SDC) and Inter discipline check
Incorporation comments of SDC/ IDC.
Internal Quality Audits.
External Quality Audits.
SAP Coding.
31
Expediting
Kick off/Inspection meeting between company, suppliers & contractors prior to start
of manufacturing activities.
32
Contract Quality plan of SP 1171 will be prepared and approval from the client
shall be obtained.
ISO-9001:2008 Quality system shall be implemented.
AHEC is accredits certificate for U stamp (Pressure vessel), S Stamp
(Pressure boilers) and R Stamp (Repair works)
All the relevant QCPs (ITPs) shall be prepared initially with the project scope of
work and approval shall be obtained from client.
The approval for site key QA/QC Personnel shall be obtained from client and will
be mobilized to site on need basis.
The audit shall be conducted as per the audit plan. (In the CQP).
33
34
35