Professional Documents
Culture Documents
BDS PPT ch06
BDS PPT ch06
Investment
Decision Rules
Chapter Outline
6.1 NPV and Stand-Alone Projects
6.2 Internal Rate of Return Rule
6.3 Payback Rule
6.4 Choosing between Projects
6.5 Project Selection with Resource Constraints
6-2
Learning Objectives
1. Define net present value, internal rate of return, payback
period, incremental IRR, and profitability index.
2. Describe decision rules for each of the tools in objective
1, for both stand-alone and mutually exclusive projects.
3. Given cash flows, compute the NPV, internal rate of
return, payback period, incremental IRR, and profitability
index for a given project.
4. Compare each of the capital budgeting tools above, and
tell why NPV always gives the correct decision.
6-3
6-4
NPV Rule
The NPV of the project is calculated as:
35
NPV 250
r
The NPV is dependent on the discount rate.
6-5
Figure 6.1
6-6
6-7
6-8
6-9
6-10
6-11
6-12
6-13
500, 000
500, 000
500, 000
$243,426
2
3
1.1
1.1
1.1
6-14
Figure 6.2
When the benefits of an investment occur before the costs, the NPV is an
increasing function of the discount rate.
6-15
6-16
500, 000
500, 000
20, 000
20, 000
20, 000
L
1 r
(1 r ) 2
(1 r )3
(1 r ) 4
(1 r )5
500, 000
1
1
20, 000
1
r
(1 r )3
(1 r )3
r
6-17
6-18
6-19
Figure 6.3
6-20
6-21
2
1 r
(1 r )
(1 r )3
6-22
Figure 6.4
No IRR exists because the NPV is positive for all values of the discount rate.
Thus the IRR rule cannot be used.
6-23
Example 6.1
6-24
6-25
6-26
6-27
Example 6.2
6-28
6-29
Cost
$80
$120
$150
Cash Flow
$25
$30
$35
6-30
Project B
$120 $30 = 4.0 years
Project C
$150 $35 = 4.29 years
6-31
IRR Rule
Selecting the project with the highest IRR may lead
to mistakes.
When projects differ in their scale of investment, the timing
of their cash flows, or their riskiness, then their IRRs cannot
be meaningfully compared.
Copyright 2012 Pearson Canada Inc.
6-32
Example 6.3
6-33
6-34
Differences in Scale
If a projects size is doubled, its NPV will double.
This is not the case with IRR because IRR
measure average return of the investment. Thus,
the IRR rule cannot be used to compare projects
of different scales.
6-35
6-36
6-37
Differences in Timing
Even when projects have the same scale, the IRR
may lead you to rank them incorrectly due to
difference in the timing of the cash flows.
The IRR is expressed as a return, but not the
timing of the return.
In Example 6.3, although the music store has a
higher IRR than the coffee shop (26% vs 23%), it
has a lower NPV.
The coffee shop has a lower initial cash flows but
higher long-run cash flows than the music store.
Copyright 2012 Pearson Canada Inc.
6-38
Differences in Risk
The IRR that is attractive for a safe project need
not be attractive for a much riskier project.
In Example 6.3, the IRR of the electronics store is
28%, but it has the lowest NPV due to the high
risk.
6-39
6-40
Example 6.4
6-41
6-42
Figure 6.5
6-43
6-44
6-45
Profitability Index
The profitability index can be used to identify the
optimal combination of projects to undertake.
Profitability Index
Value Created
NPV
Resource Consumed
Resource Consumed
6-46
Example 6.5
6-47
6-48
6-49
6-50
6-51
Questions?
6-52