2.4-ZXSDR BS8800 Installation Criterion V1.0 - Deepak
2.4-ZXSDR BS8800 Installation Criterion V1.0 - Deepak
Prepared by-
Rajesh K Gaurav
秘密▲
Installation of cards
Precaution -Wear
ESD Wrist strip
while installation
of cards
Fig 1- Insert the RSU cards Fig 2- Insert the Dummy cards
1st Sec
2nd
Reserved for Sec
expansion Sec
UBP
G
秘密▲
Prepare lugs
Lug
Core cable
Crimping tool
秘密▲
The cross sectional areas of the power cables and the ground cables shall
comply with the product installation requirements. The cross sectional area of
the ground cables shall be at least 35 mm2 and they shall be connected reliably
to the indoor ground copper bar. Those of the -48V GND power cable and the
-48V power cable shall be at least 25mm2 and they shall be laid straight and
connected reliably.
秘密▲
5
Assemble the antenna clamps. 秘密▲
Pulley block
Feeder head
bandage
Label
T ie the pull-up rope
0.4m and 3.4m away
from the feeder
Pull the feeder away from
the iron tower with this
rope to avoid damage to
the feeder or feeder head
Pull-up rope
秘密▲
Feeder installation
1. Distance between two clamps should be 1~1.5 meter.
Fig-1 Grounding near feeder Fig-2 Feeder grounding at Fig-2 Grounding at EGB
connector & antenna jumper tower ladder
秘密▲
Standard Grounding
秘密▲
Labeling
All equipments & cables must be labeled for identification and easy maintenance.
The labels of cable are filled in and stuck correctly and reliably.
They must be tidy position and same direction. They must be stuck
on a position 2 cm away from their connectors. They can be made
in a uniform way according to customer requirement.
Feeder & Jumper cable labels must have minimum 200mm distance from their
connector.
200mm 200mm