Professional Documents
Culture Documents
Lag and Slack
Lag and Slack
Lag and Slack
Steps
Define activities
Sequence
activities
Estimate time
Develop
schedule
Techniques
Gantt chart
CPM
PERT
DSM
Gantt Chart
Graph or bar chart with a bar for
each project activity that shows
passage of time
Provides visual display of project
schedule
Slack
amount of time an activity can be
delayed without delaying the project
Copyright 2006 John
Wiley & Sons, Inc.
Month
4
Activity
Design house
and obtain
financing
Lay foundation
Order and
receive
materials
Build house
Select paint
Select carpet
Finish work
5
Month
10
CPM/PERT
Critical Path Method (CPM)
DuPont & Remington-Rand (1956)
Deterministic task times
Activity-on-node network construction
Project Network
Activity-on-node (AON)
nodes represent
activities, and arrows
show precedence
relationships
Activity-on-arrow
(AOA)
arrows represent
activities and nodes are
events for points in
time
Event
completion or
beginning of an activity
in a project
Copyright 2006 John
Wiley & Sons, Inc.
Node
A
Branch
Lay
foundation
A
3
Design
house and
obtain
financing
C
2
Dummy
0
Build
house
3
Order
1 Select
and
Select 1
receive
paint
carpet
materials
E
Finish
work
1
Concurrent Activities
Lay foundation
Order material
Lay
foundation
C
Dummy
2
0
1
Order material
(b) Correct precedence
relationship
Build house
D
3
B
2
Start
G
1
A
3
Design house
and obtain
financing
C
1
E
1
Finish work
F
1
Select carpet
Critical Path
D
3
B
2
Start
A
3
C
1
1:
2:
3:
4:
A-B-D-G
3 + 2 + 3 + 1 = 9 months
A-B-E-F-G
3 + 2 + 1 + 1 + 1 = 8 months
A-C-D-G
3 + 1 + 3 + 1 = 8 months
A-C-E-F-G
3 + 1 + 1 + 1 + 1 = 7 months
G
1
F
1
E
1
Critical path
Longest path
through a network
Minimum project
completion time
D
3
B
2
Start
Finish at 9 months
G
1
A
3
C
1
Start at 3 months
E
1
F
1
Start at 6 months
Finish
Mode Configuration
Activity number
Earliest start
Slack
ES
ID
SL
LS
EF
SL
DUR
LF
Latest start
Activity duration
Earliest finish
Slack
Latest finish
Forward Pass
Start at the beginning of CPM/PERT network
to determine the earliest activity times
Earliest Start Time (ES)
earliest time an activity can start
ES = maximum EF of immediate predecessors
EF= ES + t
A
Start
3
C
Finish
F
E
1
1
8 G 9
0 A 3
Start
5 D 8
Finish
2
1
3
3 C 4
6 F 7
5 E 6
1
1
Backward Pass
Determines latest activity times by
starting at the end of CPM/PERT network
and working forward
Latest Start Time (LS)
Latest time an activity can start without
delaying critical path time
LS= LF - t
0 A 3
5 D 8
8 G 9
5 3 8
Finish
3 2 5
Start
8 1 9
0 3 3
3 C 4
4 1 5
6 F 7
5 E 6
7 1 8
6 1 7
Slack or float
3
Start
0 A 3
3 2 5
5 D 8
5 3 8
8 1 9
0 3 3
3 C 4
1
4 1 5
8 G 9
6 F 7
5 E 6
7 1 8
6 1 7
Finish
Example 1
4
Lag 2
10
10
Lag 2
4
9
Lag 2
5