Professional Documents
Culture Documents
LK-XRF XRD Presentation
LK-XRF XRD Presentation
LK-XRF XRD Presentation
Participants name :
Dinesh Purohit
(Manager QA)
Lakheri Cement Works
Venue Maddukarrai Cement Works
Date -
Range
Existing
Parameter
XRF KV
30
XRF MA
0-40(+/- 0.1)
40
MDP Speed
10000-28000
27000
MDP Temp
15-60 deg C
20-30 deg C
0-8 Pa
2-6.5 Pa
400-4500
1900-2150
Spectrometer
Pressure (Vacuum)
Sec Water Resistively
10-03-08
Preparation XRD
Internal- When soft maintenance like cartridge change and other smaller
job
External When Major s break down due to hardware & software
problem .
We control and monitor XRF KV, XRF MA, MDP Speed , Spectrometer
pressure ,Sec Water receptivity, P10 Gas cylinder pressure and flow
No Environment problems related to laboratory conditions
Room Temp maintained 20-22 deg C
Analysis control
10-03-08
Preparation XRD
Supplier support
Service contract
service contract include only AMC twice in year and guarantee spares replacement(if required )
01 year service contract
Cost - 2,65,000 INR.
Supplier should trained at least Two instrument engg so that they can be able to follow the
service engg on phone and able to resolve cassette stucked in transmission problem & can
able to change FPC window and minimize XRF break down time.
The serious and/or frequent problems are Hardware related problem generated XRF shut down
min. 1 month per year.
We faced many Hardware failures Related To Power supply system , and vacuum system,
Gonio Amplifier break down no any problem related to source, crystals & detectors.
Two times Software related problem Stopped XRF functions for 07 days .
Water pump failure , more noise and no new warrantee pump receive.
Instrument remain stopped for 07 week
10-03-08
Preparation XRD
clinker phase with minimum and regular variation with bouge calculation.
XRD give absolute Free lime because some time wide variation observed
XRD and wet analysis.
between
10-03-08
Preparation XRD
To (Date)
No. Of
days
Reason
25.04.2008
28.07.08
30.07.2008
18.08.2008
21.08.2008
Continuous
25.09.2008
02.10.2008
Continuous
23.10.2008
25.10.2008
26.07.2009
28.07.2009
03
General Maintenance
23.08.2009
29.08.2009
07
03
10-03-08
Preparation XRD
02.09.2009
04.09.2009
09.09.2009
15.09.2009
10
21.09.2009
23.09.2009
12
1.12.2009
03.12.2010
13
09.07.2010
12.07.2010
14
31.07.2010
11.08.2010
12
15
08.10.2010
15.10.2010
10-03-08
Preparation XRD
5 time break down of hardware like- Genex, mono 2 failure, MDP Pump,
water Pump replaced after one and half year of reporting.
Some time service engg. reach at site after 7-10 day of information.
Software for calibration is not user friendly because during task same entry
were fill in three time .
10-03-08
Preparation XRD
Thank You
10-03-08
Preparation XRD