Professional Documents
Culture Documents
Wellheads and Casing
Wellheads and Casing
DRILLING RISER
CHOKE LINE
SEA WATER
HYDROSTATIC
MUD HYDROSTATIC
DEPTH
BOP
SEAFLOOR
PRESSURE
DRILLPIPE
~200
30
DRILLING RISER
CHOKE LINE
30
~1,050
20
Drill 26-in hole to 1,050 ft below mudline
Riser optional - Mud returns to surface or
seafloor
Run 20-in Conductor to ~ 1,000 ft below mudline
Cement to mudline
DRILLING RISER
CHOKE LINE
BOP
Run Riser and BOP Stack
Drill 17 1/2-in hole to 4,050 ft BML
Drill with Mud returns to surface
Run 13 3/8-in Surface Casing
to ~ 4,000 ft below mudline
Cement to mudline
13 3/8
10
Fig.4-10.
Typical
sealing
arrangement
for subsea
wells.
11
12
Depth BML
240 ft
1,100 ft
4,100 ft
8,600 ft
10,100 ft
13
14
Permanent
Guide
Structure.
Temporary
Guide Base
15
16
Utility
Guide Frame
Hole Opener
Temporary
Guide Base
17
Fracture gradient at
Shallow
Gas
Blowout
Gas
reduces
buoyancy!
24
Gas in the
Water Column
26
Gas in the
Water Column
g f (g ob g p )F g p
28
g f (g ob g p )F g p
Where:
1
d KB
Where:
d KB depth measured from the kelly bushing, ft
d
water depth, ft
g ob
1
d KB
Get f from
density log.
Get F from
this plot.
Get gp
Calculate gf
Formation bulk density vs. horizontal to vertical
stress ratios for the Santa Barbara Channel.
32
= 5.3 * (TVDBML)0.1356
e.g. = 5.3 * (3,000)0.1356 = 15.70 lb/gal
34
= 5.3 * (TVDBML)0.1356
gob = 5.3 * (1,000)0.1356 = 13.52 lb/gal
gf = 0.9 * ob= 12.17 lb/gal= 0.663 psi/ft
gp = 0.8 * ob = 10.82 lb/gal= 0.563 psi/ft
NOTE: These are gradients relative to
the mudline!
35
1 D
=
Poissons
Ratio
g f (g ob g p )F g p
from Text
F S p
D D D
37
Leak-Off Test
BOPs
Casing
Drillpipe
40
Fig. 4-9.
Sub-sea
cementing
system.
41
Fig.4-10.
Typical
sealing
arrangement
for subsea
wells.
42
Liquid Compressibility
The volume required to compress a liquid
is defined by the equation:
V = Vi * Cp * P
Where:
Vi = volume of system, bbl
Cp = compressibility = 3 * 10-6 per psi for water
= 6 * 10-6 per psi for mud
P = test pressure, psi
47
V = 11 bbl
500 KB
996
1,500
Mud Line
20
13 3/8
4,000 ft 49
-6
51
53
Plug for
testing
casing seal
to full
working
pressure.
54
Test Procedure
1. Set seal
2. Land test plug in wellhead,
sealing off below the seal
3. Displace mud with water for test
4. Close pipe rams
5. Pump slowly down the choke line,
preferably in stages, to protect the
casing in case of leaks
55
Test Evaluation
During the test, if the wellhead system
being tested will not sustain test
pressure, several possible causes
should be considered:
1. Leak in the surface manifold
2. Leak in the test plug (detected by
returns through the drillpipe)
56
57
Drilling Procedures
from a floater
Install 30 Structural Csg.
Install 20 Conductor
Install 13 3/8 Surface Casing
etc.
59
Drilling Procedures
Tentative Hole and Casing Sizes
8 1/2 Pilot Hole to 180 BML
26x36 Hole Opener to 180 BML
Install 30 Structural Csg.
8 1/2 Pilot Hole to 1040 BML
17 1/2 Pilot Hole to 1040 BML
17 1/2x26 Under reamer to 1040
Install 20 Conductor
60
Drilling Procedures
Tentative Hole and Casing Sizes
General Rules
1. Do not change the tension on the
anchor lines until the 30 casing
has been run and cemented.
2. Have all the 30 casing and all of the
wellhead equipment on board
prior to spudding.
3. There will be an SLM prior to any
logging or coring run.
62
General Rules
4. All casing strings will be strapped
and drifted prior to running.
5. Casing will not be run until the
hole is in the best possible
condition and a trouble free
wiper trip can be made.
6. Cement densities will be
monitored with a mud balance.
63
General Rules
7. The rig will be moved 50 off location
whenever the riser is being run or
pulled.
8. No smoking or open flames are
permitted on deck whenever the
riser is connected to the well.
9. Welding permits (authorized by the
drilling supervisor and tool pusher)
will be required at all times.
64
General Rules
10. Coring will be at the the discretion of the
well site geologist, but only after
approval from the task force Manager
and the Exploration Coordinator.
11. All information concerning the well will
be kept strictly confidential. Any
discussions will be held in a secure
area in the quarters or on the rig.
65
General Rules
11. Confidentiality - contd.
Only contractors with a need to
know
will be allowed access to well information.
12. All personnel on board and all visitors
will be instructed with the necessary
environmental and safety films and
instructions.
66
General Rules
13. No one will be allowed on the
helicopters, work boats, or drilling
vessel without the proper
authorization or identification.
14. The rotary table must be positioned
within a 200 foot radius of the
proposed location.
67
General Rules
Anchoring
General Rules
Anchoring
3. Pull in opposing lines to set anchors.
An indicated line tension of 125
kips is necessary for the anchor to
receive any load.
4. A tension level of 440-460 kips
should be reached before 600 of
line is taken in with the rig
remaining stationary.
69
General Rules
Anchoring
5. If a line tension of 440-460 kips has
not been reached before 8001000 of line has been retrieved,
then it may be necessary to use
piggy-back anchors.
6. The following Western KDC plan
outlines the mooring procedure.
70
71
72
36 Hole Plan
1. Premix 600 barrels of 11.5 ppg kill mud
prior to spudding the well.
2. PU and TIH with an 8 1/2 bit, 6 - 6 1/2
drill collars, 6 jts of 5 Hevi-Wate drill
pipe, and sufficient 5 drill pipe.
75
36 Hole Plan
3. Tag bottom with the pilot bit, and
note and report the following:
a. RKB to water level
b. RKB to mud line
c. Water depth
d. Time of day (tide allowance)
76
36 Hole Plan
4. Lower TV camera, and observe bit
entering guide base. Retrieve
universal guide frame back to surface.
5. Upon spudding, space out drill string with
pup joints so that it will not be
necessary to pull the bit above the
guide base to make the first
connection.
77
36 Hole Plan
6. Drill an 8 1/2 hole to +/- 30 below
the setting depth of the 30
casing (estimated at 180 BML).
Circulate returns to the sea floor,
and monitor returns with the
TV camera.
78
36 Hole Plan
7. If there are no problems with shallow
gas, pull out of hole, PU 26 bit and
36 hole opener, 6-9 1/2 DCs, 6 jts
5 Hevi-Wate DP, and sufficient 5 DP.
Drill 36 hole to set 150 (4 joints) of
30 OD structural casing.
79
36 Hole Plan
Drill with sea water as follows:
a. Circulate viscous sweeps as
required to clean the hole.
b. Survey hole at 30, 60, and
150 BML.
c. At TD of 36 hole, displace
hole to the mud line with
viscous mud.
80
36 Hole Plan
Drill with sea water cont.:
d. Make a wiper trip.
e. Circulate the hole to the
mud
line with viscous mud.
f. Penetration rate should not
exceed 100 ft/hr overall.
81
36 Hole Plan
8. Run 30 structural casing per procedure.
9. If there are problems with shallow gas,
displace the 8 1/2 hole with kill mud
until the gas stops or the hole is full of
kill mud.
Monitor returns with the TV camera for
evidence of gas or flow, and if after
one hour the hole is stable, proceed
as in steps 7 and 8.
82
36 Hole Plan
10. If the kill mud in step 9 does not
stabilize the well and it appears that
heavier mud will not stabilize the well
or will break down the formation, then
prepare to cement.
Mix and pump, sufficient 15.8 ppg
cement slurry to circulate cement to
the mud line, and monitor returns for
gas with the TV camera.
83
36 Hole Plan
84
26 Hole Plan
1. Have 600 barrels of 11.5 ppg kill mud
prior to drilling out below the 30
casing.
2. PU and TIH with an 8 1/2 bit, 9-6 1/2
DCs, 9 jts of 5 Hevi-Wate DP, and
sufficient 5 DP.
85
26 Hole Plan
3. Drill an 8 1/2 hole to +/- 40 below the
setting depth of the 20 casing
(estimated at 1040 BML).
Circulate returns to the rig shakers, and
monitor returns for indications of gas or
flow.
86
26 Hole Plan
87
26 Hole Plan
5. If there are no problems with shallow
gas, pull the riser, PU & TIH with a
17 1/2 bit, 26 hole opener, monel
DC, 6-9 1/2 DCs, 6-8 DCs, 9 jts 5
Hevi-Wate DP, 26 stabilizer at 60,
qand sufficient 5 DP.
Drill a 26 hole to set 1040 of 20 OD
conductor casing as follows:
88
26 Hole Plan
a. Circulate viscous pills as
required to clean the hole.
b. Circulate returns to the sea floor
with sea water.
c. Maintain inclination at less than
three degrees.
d. Spot viscous mud at TD of 26
hole.
89
26 Hole Plan
e. Make a wiper trip.
f. Spot viscous mud as required.
g. Drop multishot and POH.
6. Run 20 OD conductor casing and
cement per procedure.
90
26 Hole Plan
7. If there are problems with shallow gas in
Step 5, circulate the hole with viscous
spud mud and slowly increase the
weight until the flow has stopped or
until the active system is depleted.
If the flow continues, pump the kill
mud at the maximum rate until the
active system is depleted.
91
26 Hole Plan
7. (Cont.) Then pump sea water at the
maximum rate until the hole bridges.
8. If the flow rate is significant, and the hole
will not bridge, prepare to move the rig.
Cement the hole to just below the sea
floor with 15.8 ppg cement. POH with
the BHA. Cut or shoot the 30 casing,
and pull the TGB and PGB. Move rig
as required.
92
26 Hole Plan
9. If the gas in step 7 depletes or the
density is sufficient to control the
well, then casing can be run or the
well can be drilled ahead.
10. Drill 8 1/2 hole to +/- 40 below the
setting depth of the 20 casing
(estimated at 1040 BML).
93
26 Hole Plan
11. Circulate and condition for logs. Pull out
of hole, and log well per procedure.
12. PU & TIH with 17 1/2 bit, Monel DC, 6-9
1/2 DCs, stabilizers at 60 amd 90, 6-8
DCs, jars, 9 jts 5 Hevi-Wate DP.
94
26 Hole Plan
13. Drill a 17 1/2 hole to sufficient depth
to set 1040 of 20 conductor casing.
Drop multishot, and POH.
14. PU & TIH with 17 1/2 bit and 26
underreamer, 6-9 1/2 drill collars, 68 drill collars, 9 jts 5 Hevi-Wate DP,
and 26 stabilizer at 60.
95
26 Hole Plan
15. Underream to sufficient depth to set
1040 of 20 conductor casing.
16. Circulate and condition the hole for
casing. Care must be taken to have a
balanced mud weight all the way
around with no heavy slugs.
96
26 Hole Plan
17. Displace hole from TD to the sea floor
with sufficient weight mud to balance
the hydrostatic when the riser is
removed.
Again, care must be taken to have a
balanced mud weight while displacing,
and the riser may have to be voided
with sea water as the heavier mud is
circulated.
97
26 Hole Plan
18. POH, run the 20 casing and 18 3/4 10,000 psi wellhead housing, and
cement per procedure.
19. If there is evidence that the hole
cannot be drilled deeper safely in
step 9, the well will be underreamed
at the depth reached in step 9 and
20 casing will be set.
98
26 Hole Plan
20. It will then be determined whether
future casing settings need to be
changed.
100
101