Professional Documents
Culture Documents
Monthly TCR Calculation Draft 3: Also Review ERCOT Protocols Section 7 For More Details and Additional Data
Monthly TCR Calculation Draft 3: Also Review ERCOT Protocols Section 7 For More Details and Additional Data
TCR Calculation
DRAFT 3
James J. Teixeira
05/11/02
Also review ERCOT Protocols Section 7
for more details and additional data
Process Overview
SSWG Case Selection
PSSE
Apply IDEVs
MS Access Filter
outages to be
considered
Apply Outages
Change Zone
Numbers to
Reflect CM Zone
MUST
Create PSSE
SAV Case
MUST Load
SAV Case
Create PSSE
RAWD
Multiple Transfers
AC Based FCITC
Calculation
PowerWorld
Simulator
Import RAWD into
PowerWorld
Simulator
Calculate Shift Factors
for each bus for each
CSC (1 line of DCKT)
Outage Scheduler
Query for Study
Month to CSV
MS Access
Tables and
Queries
Monitored
Elements Impact
Analysis
VB
Scripts
TCR.ERCOT.COM
Zonal
ATC
MS Excel
MON02_TTC
Ties
Flow
CSC
Flow
MS Excel
MON02_AWSF
Process Overview
Outage Scheduler
PSSE Version 26.2.3 (Moving to Version 28)
Apply Outages
Change Zone Numbers to CM Zone Number
Outage Grouping
Outage
Group 1
Outage
Group 2
Line
Outages
Beginning
of Month
End of
Month
The modified seasonal base case for a particular month will be based on the most
limiting situation within the corresponding month. This analysis takes into
account all transmission outages of significant duration and impact (Protocols
7.5.2.2)
PSSE
Determine PSSE Seasonal SSWG On Peak Base Case to
use
Apply Applicable IDEVs to Base Case to apply latest
transmission updates to case
Supplied by TDSPs
PowerWorld Simulator
Import RAWD into PowerWorld and Save
In PowerWorld, calculate a set of raw Shift Factors for
each bus for all four CSCs using TLR Sensitivities
Use Norwood (PSSE Bus #2406) as Transaction Buyer
Calculate raw SFs for one line of CSC double circuit and
multiply by 2 later
MS Access
Run VB scripts to calculate all data found in
MON02_AWSF.xls
Summation of Weighted Shift Factors
Average Weighted Shift Factors
Min, Max, Average, Std Deviation
Contingencies/Limits
Types Used
48 Phantom Single
Multiple modeled elements out for single outage/fault
512 Double
Only ones that result in cascade are considered as valid
Limits Used
Rate B
105 % if Graham Parker or Sandow Temple DCKT is the
contingency
Based upon TSDP determination
100 % Otherwise
MUST
Load previously created PSSE save case into MUST
Check/Modify MUST options to use 105% limit for
applicable contingencies, 100% otherwise
In MUST, run Multiple Transfers AC Based FCITC
Calculation
AC is more accurate than DC
MUST Contd
Calculate Study Transfers
Examine AC FCITC Multiple Transfers Report
to determine lowest AC FCITC where the
limiting element is a CRE or the Contingency is
a CRE (Protocol 7.5.2)
This number is the Zonal ATC found in
MON02_TTC.xls
MUST Contd
Run Monitored Elements Impact Analysis and set
Transfer level to Zonal ATC and Contingency number
to the corresponding contingency causing the Zonal
ATC from the AC FCITC Multiple Transfers Report.
Appropriate Ties and CSC Interfaces are defined in file
02cscinterface.mon
Post-Shift Base Case flow Impacts on Ties and CSC
interfaces are the Ties TTC and OC0 CSC TTC found
in MON02_TTC.xls
Settlement Adjustment
ERCOT will determine the total quantity of TCRs for the monthly
distribution by adjusting the corresponding modified seasonal base
case CSC Limits by the following amount: for each CSC, the sum over
all nodes of the product of the expected level of load at each node
from the modified seasonal base case multiplied by the difference
between the corresponding Shift Factor for that node and CSC and the
Zonal Shift Factor. (Protocol 7.5.2.2)
[L
i1
* (SFi AWSF)]
Where:
n = total number of load buses
L i = MW load at bus i
SF i = ind. shift factor at bus I
AWSF = corresponding zonal
shift factor for bus i
Limiting Element
Contingency
Zonal ATC
Ties TTC
OC0 - CSC TTC -double circuit
line flow - MW
delta CSC - adjustment for
Settlement Calculation
total TCR (following Protocols)
COMMERCIALLY
SIGNIFICANT
CONSTRAINT #1 GRAHAM TO PARKER
COMMERCIALLY
SIGNIFICANT
CONSTRAINT #2 SANDOW TO TEMPLE
COMMERCIALLY
SIGNIFICANT
CONSTRAINT #3 STP TO DOW
COMMERCIALLY
SIGNIFICANT
CONSTRAINT #4 PARKER TO GRAHAM
WEST TO NORTH
SOUTH TO NORTH
SOUTH TO HOUSTON
NORTH TO WEST
726
638
756
237
57
783
-46
592
-54
702
-57
180
Posted Information
TCR.ERCOT.COM
Questions?