SAP Implementation
Technical Scope
Functional &
Technical Scope
Out of Scope
Hardware procurement
Changes to third party system: Modifications, additions, installation and
configuration of any third party system, interfaces
Development of Interfaces
SAP Licenses
Implementation
Methodology - ASAP
Project
Steps.
4.Final Preparation
End users are trained; this is the final check before the cutover to
the new system solution.
5.Go Live and Support
The solution receives confirmation, ongoing support is in
place,
and the project is closing.
ProjectSteps.
Preparation
Project
Purpose
Deliverables
Project Plan
Training Plan
System Landscape Strategy
Project Team training Level -1
End User Training and
Documentation Strategy
Project Steps.
Business Blue Print
Purpose
To create a body of work, know as
Business Blueprint that
Aligns business requirements to
the SAP business model
Documents the TO-BE process
models
Describes the solution design
Identifies additional functional
and technical requirements
Obtains business sign-off on
requirements and design
Blueprinting is dedicated to
support value delivery
Deliverables
Project Steps.
Realization
Purpose
Deliverables
Project Steps.
Final Preparation
Purpose
Deliverables
Data Converted
Cut-Over Plan
End-Users Trained
End-User System Ids Created
System Support Organization in
Place
Help Desk
Technical Support
Operational Production System
Environment
Organizational Changes
Implemented
Go/No-Go Decision
Project Steps.
Go Live and Support
Purpose
Deliverables
Go-Live
Project Close
Project Steps.
Types of
Testing
Tools
Roles
System Required
Unit testing
Baseline configuration
Final Configuration
Consultant
Development
system: QA
environment
Scenario
testing
Baseline Configuration
Final Scope
Configuration
Test Scenario
template
Core team
leader
Development
system: QA
environment
Development
testing
Develop Conversion
Programs / Develop
Interface Programs /
Develop Enhancements /
Create Reports /
Create Forms
Object
Testing
template.
Developer
Core team
leader
Development
system: QA
environment
Integration
testing
Baseline Confirmation
Final Scope Confirmation
Final Integration Test
Test Scenario
template
Core team
leader
Quality
assurance
system
Performance
testing
System Management
Stress/Volum
e test
template
Technical Team
Lead /
Core team
leader
QA system
Productive
system
Project Timelines
Month
Particulars /
Week
Project
Preparation
Month 1
Month 2
Month 3
Month 3.5 Month 4.5
W1 W1 W1 W1 W1 W1 W1 W1 W1
W1 W2 W3 W4 W5 W6 W7 W8 W9
0 1 2 3 4 5 6 7 8
Blueprint
Realization
Testing &
Training
Final
Preparation
Go Live &
Support