Inventory Management: Reservation
Inventory Management: Reservation
Reservation
A reservation is a request for a goods issue at a later
date.
Reservation can be requested by various departments
for various account assignment objects (such as cost
center, order, asset, etc.).
The purpose is to ensure that a material will be available
when it is needed.
Also important is that reservations are taken into account
by Material Requirements Planning (MRP), (are
procured in time if they are out of stock).
Information in a Reservation
In a reservation, information is stored that is relevant
for the goods issue and for materials planning, for
example:
what? (which material?)
how much? (in which quantity?)
when? (for which requirement date?)
from where? (from which plant or warehouse?)
to where? (to which recipient or customer?)
Results of a Reservation?
When a reservation is entered, the following events
occur in the system:
A reservation document, which serves as proof
of the request, is created.
Total stock and unrestricted-use stock of the
material remain unchanged. Reserved stock is
increased by the reserved quantity.
In materials planning, available stock is reduced
by the reserved quantity. This is visible in the
current stock/requirements list.
Reservation
Displaying Reserved Stock
Stock Overview at Plant Level
System displays the total reserved stock at plant
level. From the stock overview. Environment to
display.
Current Stock/Requirements List
System lists all of the open reservations for the
material at plant level, along with the reserved
quantity for each.
Creating a Reservation
1. Reservation Create.
(The initial screen ).
Creating Reservation
3 Press ENTER to display the collective entry screen.
Enter an Account Assignment
Upper part screen - header data for the reservation.
Depending on the movement type, you must maintain
different account assignment fields (for example, cost
center, order, or asset).
Some of the account assignment fields (for example, G/L
account) need not be maintained manually. The relevant
information is automatically copied from the account
assignment object.
Enter Items
Lower part of the screen, you can enter item.
Changing a Reservation
Changing a Reservation
Changing a Reservation
Constraints
There are some restrictions on changing a
reservation, as follows:
You cannot change the account assignment data
(for example cost center, order, and so on). If the
account assignment is incorrect, you must delete
the reservation and enter a new reservation.
You cannot change the material number or the
plant for an item. If either of these entries is
incorrect, you must delete the item and enter a new
item.
Changing a Reservation
Changing: a Reservation
1 Choose Reservation Change.
(initial screen)- enter the reservation number.
Displaying a Reservation
Individual Reservation
Reservation Display (Enter the reservation. )