Project Schedule

Cooling Water
System
Construction

Date
Start

Finish

12 February 2015

9 December 2015

Initial drive
(100m)

27 July 2015

24 September
2015

Main drive

17 October 2015

23 April 2016

Dredging work

7 January 2016

29 February 2016

Installation of
Steel Caisson

3 March 2016

4 March 2016

Installation of
light beacon

17 June 2016

27 June 2016

Flooding of tunnel

15 July 2016

18 July 2016

Installation of
Velocity Cap

21 July 2016

22 July 2016

Deep Cement
Mixing

You might also like