Cooling Water System Schedule
Cooling Water System Schedule
Cooling Water
System
Construction
Date
Start
Finish
12 February 2015
9 December 2015
Initial drive
(100m)
27 July 2015
24 September
2015
Main drive
17 October 2015
23 April 2016
Dredging work
7 January 2016
29 February 2016
Installation of
Steel Caisson
3 March 2016
4 March 2016
Installation of
light beacon
17 June 2016
27 June 2016
Flooding of tunnel
15 July 2016
18 July 2016
Installation of
Velocity Cap
21 July 2016
22 July 2016
Deep Cement
Mixing