Professional Documents
Culture Documents
EC532 - Environmental Economics, Institutions and Policy: Lecture 9 - Environmental Valuation in Practice
EC532 - Environmental Economics, Institutions and Policy: Lecture 9 - Environmental Valuation in Practice
EC532 - Environmental Economics, Institutions and Policy: Lecture 9 - Environmental Valuation in Practice
EC532 Environmental
Economics, Institutions
and Policy
Lecture 9 Environmental Valuation in
Practice
Introduction
Used to decide whether a project (such as
building a road or a dam) is worth undertaking
or not.
Can be used to select best project from a
range of alternatives
Improving transport links between A and B proposed road passes through different routes
with different environmental impacts or might
be better to improve other forms of transport
such as rail or buses
EC532 Lec 9
EC532 Lec 9
Economic Prices
EC532 Lec 9
EC532 Lec 9
METHODOLOGICAL STEPS IN
CBA
EC532 Lec 9
EC532 Lec 9
EC532 Lec 9
Include all direct costs and benefits plus all indirect costs
and benefits (the externalities) borne by third parties.
EC532 Lec 9
Step 4: Incorporating
environmental values
EC532 Lec 9
10
EC532 Lec 9
11
B benefits
C costs
r rate of interest
t time periods (t=1.....T)
Formula takes all costs and benefits incurred over time period
of project - aggregated and discounted.
This yields an estimate - Net Present Value (NPV).
EC532 Lec 9
12
EC532 Lec 9
13
A Hypothetical
Example
A road building scheme
EC532 Lec 9
14
EC532 Lec 9
15
EC532 Lec 9
16
EC532 Lec 9
17
EC532 Lec 9
18
EC532 Lec 9
Route B is preferred
19
EC532 Lec 9
20
CBA in Practice
Demand for CBA many different sources especially government
EC532 Lec 9
21
Data
Sample contains 74 CBAs
27 from the Reagan period of government, 24 for Bush and 23 for
Clinton. The data are from a period 1982-1999. All of the CBA were
undertaken by the Environmental Protection Agency (EPA).
1. Costs
Most CBAs identified, many quantified and a reasonable proportion
expressed in monetary terms.
More recent CBA provide point and a range of cost estimates. Also
costs identified are typically those incurred by producers but
administrative costs are often not included.
2. Benefits
Presentation of benefit estimates is less common than costs.
Benefits frequently quantified but far less frequently expressed in
monetary terms. So 100% of CBA examined expressed some costs
in monetary terms less than 50% express some benefits in
monetary terms. The implication is that benefits are more difficult
to quantify than costs in monetary terms.
EC532 Lec 9
Results
The use of economic information is examined across six categories:
22
4. Consideration of alternatives
Alternative is another policy option that could achieve the same
outcome as policy being examined. Consideration of alternatives is
at best poor and practice over time has seen a reduction in the
consideration of alternatives.
5. Clarity of presentation
Criteria describes how much overall information is included in CBA to
help the reader understand the problem more broadly. For example,
as CBA are frequently very large documents a minimum requirement
is that they contain an executive summary. Interestingly, 80% of
CBA provided an executive summary and this average is falling as
the more recent CBA in the sample are less likely to provide a
summary. It was also noted that most executive summary do not
provide details of key calculations underpinning findings.
EC532 Lec 9
23
Key Findings
Results do not indicate that EPA failed to meet regulatory
requirements.
Hahn and Dudley note government agencies are allowed
leeway if information that might be used does not exist or
cannot be collected.
Express some concern about the quality of practices they
have examined.
Analysis reveals no real change in practice over time and
that the practical application of CBA is to certain extent
constrained by political reality. Use of fundamental
economic information is limited. Many of the CBA are of
low quality.
EC532 Lec 9
24
EC532 Lec 9
Example
EC532 Lec 9
26
EC532 Lec 9
27
EC532 Lec 9
The risk premium relates to the risk default - proxy for risk
free rate is what is called the bond rate - normally gauged
by reference to government treasury bonds which we
assume will always be honoured
Why?
Intergenerational equity for individual do not make
decisions and/or consider the future much beyond their own
lifetime or that of their children.
28
In Practice
EC532 Lec 9
In practice r = 10 or 12%
Set based on opportunity costs of capital (real return on
additional investment)
29
Different Discounting
Models
There are alternative discount models:
EC532 Lec 9
30
EC532 Lec 9
31
EC532 Lec 9
Discount Factor
Proportional/Hyperbolic
Constant
0
Time Periods
23
32
Criticisms of
Discounting
Distributional Issues
EC532 Lec 9
33
Future Generations
Discounting places lower importance on future
generations - intergenerational equity.
Projects - large investments today benefits in future
EC532 Lec 9
34
EC532 Lec 9
35
EC532 Lec 9
Incommensurable values
Some environmental values and other non-marketed
values are incommensurable.
Cannot be compared with marketable goods.
In other cases, environmental effects may be measurable
in principle, but the state of science does not enable them
to be quantified at present.
Might argue in response in the real world, choices
between alternative states have to be made.
Better choices made in systematic way - involves
quantification
36
EC532 Lec 9
Equity Issues
Can employ distributional weights
This modification reliant on some value
judgement
This approach to CBA more consistent with
Rawlsian ethic that explicitly protects the
interests of the disadvantaged groups in society.
37
EC532 Lec 9
38
39