Professional Documents
Culture Documents
Operational Research Ie G3F3: Industrial Engineering Industrial Engineering Faculty Telkom University
Operational Research Ie G3F3: Industrial Engineering Industrial Engineering Faculty Telkom University
RESEARCH 2
IE G3F3
Industrial Engineering
Industrial Engineering Faculty
Telkom University
PROJECT MANAGEMENT
Amelia Kurniawati, ST., MT.
Goal
Understanding the
process of planning,
implementation and
evaluation of projects
Outline
4
Introduction
INTRODUCTION
KINDS OF PLANNING
regional
sectoral
planning of tools
financial planning
production planning
PRINCIPLES OF PLANNING
10
PLANNING
TECHNIQUES
CPM (Critical Path Method)
PERT (Project Evaluation and
Review Technique)
Useful for planning, scheduling and
monitoring / controlling project
11
PERT
12
PROJECT SCHEDULING
TECHNIQUE
13
14
PLANNING PHASES
15
PLANNING PHASES
16
PLANNING PHASES
17
PLANNING PHASES
PHASES OF PROJECT
18
19
2.
3.
20
FORMATION OF DIAGRAM
ARROWS
21
22
or
23
Contoh lain :
24
FORMATION OF DIAGRAM
ARROWS
25
26
27
28
29
30
Provide an overview of the correct order logic. Example: The waste water
will be discharged from sewer 1 (Outlet 1) to the river flowed into the
WWTP I (3), channel 2 before to the river outlet will also pass through the
WWTP I (3), because the processing load on the WWTP first limited, then
the capacity untreated sewage is channeled to the WWTP II (4), while the
already processed can be discharged directly into the river (5)
Activity A: Outlet channel 1 to the WWTP I (3)
Activity B: Outlet Channel 2 to the WWTP I (3)
Activity C: WWTP channel I (3) to WWTP II (4)
Activity D: WWTP channel I (3) to the river (5)
In the picture above shows that activity C can not start before activity
B, which means that the activities of C can operate when activity B is
already running, while D can run after the events A or B if the run is not
the same.
31
32
ANSWER:
33
34
ANSWER:
35
Examples
of
charting
arrows
3
Draw arrows diagram that includes activities A,
B, C, ....., and J so that relations such that the
following is true.
A project started from the activity,
Activities B and C can only be started if A is
complete.
Activities D and E can only be started when C is
complete.
Activities of F and G can only be started when B
is complete.
H activities can only begin if E is complete.
I could start a new activity when D is complete.
A new activity can start if G and H are finished.
36
ANSWER:
37
38
39
Determination of Time
40
Notation used
41
Sample Case
42
Activiti
es
A
B
C
D
E
F
G
H
I
J
K
Predecessor
A
B
B
C
F,G
D,E
F
H
Time
(Day)
4
8
7
15
6
12
9
11
3
10
5
Forward calculation
43
event
occurrence (TE) which is also a
forward result
c = space to indicate when the latest
occurrence of event (TL) which is also a result
of the countdown
44
45
46
47
48
Total Float:
amount of time in which the completion time of an
activity can be delayed without affecting the fastest
time of the completion of the overall project. TF =
LF-ES-duration
Free Float:
amount of time in which the completion of an
activity can be delayed without affecting the fastest
time of the commencement of the activity of others
or the fastest time on the occurrence of another
event network, FF=EF-ES-duration
49
Activiti Duration
es
(t)
(0,1)
(0,2)
(0,3)
(1,4)
(2,4)
(2,5)
(3,6)
(4,8)
(5,6)
(5,8)
(6,7)
(7,8)
4
8
7
15
6
12
9
3
0
10
11
5
Fastest
Start Finish
ES
0
0
0
4
8
8
7
19
20
20
20
31
EF
4
8
7
19
19
20
20
36
20
36
31
36
Slowest
Start Finish
LS
0
0
0
18
8
8
11
33
20
20
20
31
LF
18
8
11
33
33
20
20
36
20
36
31
36
Total
Free
Float
Float FF
TF
14
0*
4
14
19
0*
4
14
0*
6
0*
0*
0
0
0
0
5
0
4
14
0
6
0
0
FF(0,1) =4 0 4 = 0
Aktivitas B: TF (0,2) = 8 0 - 8= 0,
FF(0,2) = 8- 0 8 = 0
Aktivitas C: TF(0,3) = 11 0 - 7= 4,
FF(0,3) = 7- 0 7 = 0
FF(1,4) = 19- 4
FF(2,4) = 19- 8 6 = 5
F: TF (2,5) = 20 - 8- 12= 0,
FF(2,5) = 20- 8 12 =
G: TF (3,6) = 20 - 7- 9= 4,
H: TF (6,7) = 31 - 20- 11= 0,
FF(3,6) = 20- 7 9 = 4
FF(6,7) = 31- 20 11 =
FF(4,8) = 36- 19 3 =
FF(0,2) = 8- 0 8 = 0
51
Labors
4
5
3
7
3
2
Activiti
es
(3,6)
(4,8)
(5,8)
(6,7)
(7,8)
Labors
1
2
5
6
4
Making Time
Chart and
Resource
Time chart for the
project are as follows:
Allocation
52
53
If the non-critical
activities
scheduled as
soon as
possible, it
needs to be seen
in the following
figure:
54
55
Making Time
Chart and
Resource
Allocation
56
PERT
PERT
PERT
57
F(D)
P(D<A) = .01
P(D>B) = .01
A
optimistic
M
most
likely
B
pessimistic
TIME
58
PERT
PERT
Estimating activity duration distributions :
A = optimistic time
M = most likely time
B = pessimistic time
t = expected duration = (A + 4M + B) / 6
= standard deviation = (B A) / 6
59
PERT
Immediate
Predecess Optimis Most
Activity
or
tic
Likely
A
3
4
B
2
9
C
5
6
D
A
12
15
E
B
4
5
F
B
6
13
G
C
7
8
H
F,G
5
12
I
D,E
2
3
J
F
4
11
K
H
4
5
Pessimis
tic
5
10
13
18
7
14
15
13
4
12
6
60
Immediate
Predecess Optimis Most
Activity
or
tic
Likely
A
3
4
B
2
9
C
5
6
D
A
12
15
E
B
4
5
F
B
6
13
G
C
7
8
H
F,G
5
12
I
D,E
2
3
J
F
4
11
K
H
4
5
PERT
Expect
ed
Pessimis Durati Varian
tic
on
ce
5
4
1/9
10
8
16/9
13
7
16/9
18
15
1
7
6
1/4
14
12
16/9
15
9
16/9
13
11
16/9
4
3
1/9
12
10
16/9
6
5
1/9
61
PERT
Example Problem
62
63
EXERCISES PROBLEM
1
Activiti
es
Activities describtion
A
Digging
B
Making Foundation
C
Making Walls
D
Making Roof
E
External water pipe installation
F
Internal water pipe installation
G
Exterior board making
H
Exterior painting
I
Electricity Installation
J
Wall board making
K
Floor Installation
L
Interior Painting
Exterior equipments
M
installation
N
Interior equipments installation
Predecessor
A
B
C
C
E
D
E,G
C
F,I
J
J
Time
2
4
10
6
4
5
7
9
7
8
4
5
H
K,L
2
6
64
EXERCISES PROBLEM
2
Activitie
s
Activities describtion
Predecessor
Time
Artwork preparation
A, B
G, H
Book production
C, I
65
EXERCISES PROBLEM 3
B.