A&D High Tech - Team 2
A&D High Tech - Team 2
A&D High Tech - Team 2
Team 2:
Yusuf Akkoca
Tom Bloom
Karen Delton
Shweta Hire
Eric Johnson
David Mahzonni
Project Priority
Main priority is completion
time
May until Mid November to
complete;
about 6 months
Projected Completion
Time
322 Days to Complete
With Deployment at
11/14/2003 and 100%
resource usage.
Critical Path
Process / Product:
WHAT
WHEN
Technical Infrastructure
Sev
erit
y
WHY
Oc
cur
ren
ce Mitigation Controls
Testing
Deployment
Det
ecti
on
2
Detailed Design
42
60
84
96
98
105
120
Project Management
Software Requirements
Inadequate planning
144
Test Planning
192
Inefficient workflow
Peer Reviews
216
RPN
Project Management
Software Requirements
System Requirements
Gathering Inaccurate
Requirements
Ensure communication
between designer and key
7
stakeholders
Hold requirement walkthroughs
with all key stakeholders
7
(business & technical), gather
formal sign-off
315
567
Thank you!