Professional Documents
Culture Documents
PBC Lessons Learned BM
PBC Lessons Learned BM
PBC Lessons Learned BM
BASED CONTRACT:
Lessons Learned in Indonesia National Roads
Management
Road
length
Sumater
a & Java
15,708
15,336
41
Bali,
NTT,
NTB
2,376
2,172
189
Sulawesi
7,089
5,641
878
488
72
560
Kalimant
an
5,707
4,006
308
625
807
1,432
Maluku
& Papua
3,747
1,063
958
1,014
712
1,726
TOTAL
34,627
Hotmix/
Rigid
Nonhotmix
Unpaved
Gravel
Earth
218
-
Total
113
331
Source: Ministry of Public Works (2008) MOHON DIUPDATE DENGAN DATA TERBARU
28,278
2,364
2,286
1,079
3,995
Good
km
Moderate
Lightly
Damaged
Heavily
Damaged
Dead End
km
km
km
km
Total
km
Sumatera
& Java
8,094
51,5
6,611
42,1
809
5,1
82
0,5
113
0,7
15,70
8
Bali, NTT,
NTB
1,234
51,9
960
40,4
158
6,6
25
1,1
0,0
2,377
Sulawesi
4,609
65,0
1,662
23,4
606
9,8
95
1,3
30
0,4
7,092
Kalimanta
n
2,087
36,6
2,261
39,6
1,287
22,6
70
1,2
0,0
5,706
Maluku &
Papua
672
17,9
1,599
42,7
1,065
28,4
48
1,3
364
9,7
3,747
16,695
48,2
13,093
37,8
4,015
11,6
320
0,9
506
1,5
34,62
9
TOTAL
Source: Ministry of Public Works (2009) MOHON DIUPDATE DENGAN DATA TERBARU
Finding
a) Reduction cost of management and maintenance:....... (DATA)
b) Contract for .... Years, including road maintainance to achieve
certain performance;
c) The current contract may give to much freedom for the
contractor to apply pavement designs that are not consistent
with good practice.
d) The current contract provides no physical measure to verify
that the required design life will be reached.
e) The current contract did not define the required design
reliability.
f) Social, landscaping, safety, pedestrian facilities, flood
drainage, adjoining property interface and other design
features are not driven by design life consideration. Therefore
the employer must retain control of design and supervisionof
the design elements.
Finding
g) The supervision team appears to have no power to
enforce the Hold Point requirements of the contract as
this authority also has not been delegated;
h) Most of contractors do not have an efective Quality
Assurance Plan and not operate comprehensive quality
control system;
i) There is no mechanism in the contract documents to
identify the residual life at the end of waranty periodas
an means to reward or penalise the contractor.
Lessons Learned
1. Quality and compliance inspection remain necessary for PBC
contract to ensure that the design life is reached. Therefore
supervision consultants should be engaged and authorized to
carry out quality inspection.
2. The PBC contract documents should allow contractor to
choose the specifications to be used.
3. The PBC contract document should clarify the minimum design
standard that must be provided and the right of the employer to
insist on good practice design solutions;
4. The PBC model does not ensure the best outcomes for design
issues such as property access, pedestrian facilities, storm
drainage, safety standards, etc. The matters need to be
comprehensively defined by the contract documents.
5. Procedures and sanctions, including termination, applicable in
the event of the contractors failure to deliver specified quality
to respond to engineers instructions should be clearly defined.