Inspections: CE 300 Floodplain Management Unit 7
Inspections: CE 300 Floodplain Management Unit 7
Objective
Able to describe when and what to inspect
1st Inspection
When before ground is broken
Check
Location of floodplain and floodway boundaries
Floodway encroachments if applicable
2nd Inspection
When just before installation of lowest floor
Slab on grade when forms are up and before concrete
poured
On foundation before 1st floor is installed
Why?
Easy to correct mistakes before concrete poured
Easy to add another course of concrete block before floor
construction begins
3rd Inspection
When near end of project
What?
Later Inspections
For VE zones make sure area below floor is not finished
out.
Look for non-permitted accessory structures, fences, or
walls in the SFHA or blocking swales
Summary
Be able to describe when and what to inspect for NFIP
compliance.
Be able to describe method of measuring elevations.