Trimble CEC - TilosDemo
Trimble CEC - TilosDemo
Novapoint / Network
Quadri
Quantm
VisionLink
Business Center - HCE
Novapoint / Tekla
TiLOS
Connected Community
GCS900
CCS900
PCS900
DPS900
SCS900
Scheduling software
When
Traditional GANTT
book
What
Line Pattern
Type of work
Rectangles
Bridges
Blocked zones
+ Production monitoring
Location based progress tracking
Road
General overview on 50 km new highway project
Railway
General schedule in 5 sections (5 years)
Track repair 60 h
Tunnel
Brenner base tunnel
- 220 km Drilling
- 17 Mio m3 Material
Metro
Cityringen Copenhavn
- 17.4 km tunnels
- 17 Stations
TILOS was used in early planning stage to
coordinate TBM and work in stations
Pipeline
Weather impact to schedule
Progress monitoring
Usage of TILOS
Stand alone planning system
Overall planning
Detailed production planning (repetitive work planning based on task templates)
Prepare layout > Import tasks > Inspect schedule : Determine interaction
between disciplines
Combination: Linear tasks in TILOS (e.g. TMB) and stations in P6 or MS Project
and exchange
Get all location based information imported into TILOS: Station points, Sections,
Elevation profiles
Quantity profiles, Mass haulage plan.
Schedule in TILOS
Data Preparation
Data Import
Data Import
Clipboard
Profiles
Edit in TILOS
Import by ASC
Import from XML File
Import through TCPIP
Scheduling activities
Scheduling activities
Linking activities
Basic CPM link types
Distance links
Keep distance in m
Start when predecessor is @
Calculate meeting point
Set lag on distance
Other options
Synchronize speed
Set distance coordinates
Resource Calculation
Quantity based
Time based
Fixed assignment
Resource Monitoring
rs
Fu
e
C
ut
or
ho
u
s
hi
ne
La
b
Resource planning
M
ac
Resource Planning
Cost monitoring
Cost controlling
co
ic
To
D
at
e
io
d
Pe
r
Cost planning
st
s
Cost Planning
Project Simulation
Connecting Schedule and Map
Weekly production
Production to date
Logistic Plan
Grouped by Company
Progress Monitoring
Baseline
Snapshot of the project at beginning
Actual progress
Report time and location
Update schedule
Cut off completed work
Reschedule project
Integration
Data Prep, Plan
Business Center HCE
Tekla Civil, Vianova
Project Management
TILOS
Generic
ASC, XML, XLS
BusinessCenter (BC)
The constructible model = Design model + Constructability
model
Mass Haulage
plan
Compaction plan
Driling plan
Machine control
data
.
Corridor
Landhight
profile
Cross sections
Soil conditions
Construction
layers
Dozer
100
Scraper
800
Off Road Truck 2500
On Road Truck 10000
Integration with BC
TILOS Import
Scheduling
Progress Analysis
Baseline
Store a snapshot of current state
Actual progress
Enter quantities for each
task
Planned / Actual
Compare productivity in
each period or to date
Engineering:
HDR, SNC Lavalin, Fluor, Worley Parsons, DB Consult, Drees & Sommer
Rail Equipment:
Siemens, Alstom, Bombardier, Balfour Beatty
Construction Companies
When TILOS is
Used
Feasibilty Studies
Overall Plan
Production plan
Special studies
Maintenance plan
Pre-design
Planning
Procurement
Execution
Claims
Operation
Schedule and Geometry on 1 output makes it easy to read: It tells whole story
Scheduling becomes interesting for engineers.
High quality outputs: Good marketing for engineering of the company
Helps to win projects
Reduced risk
Planning mistakes leading to clashes can be easy identified and worked around
early
Working with high precision (Work, work rate and weather profiles)