Cost Control
Project cost control includes:
Monitoring cost performance.
Ensuring that only appropriate project changes are included in a
revised cost baseline.
Informing project stakeholders of authorized changes to the project
that will affect costs.
Pengendalian Biaya
Pengendalian Biaya pada Proyek mencakup:
Pemantauan kinerja biaya.
Memastikan bahwa hanya perubahan dalam proyek yang tepat
masuk kedalam biaya revisi awal.
Memberikan informasi kepada pemilik proyek atas perubahan
kewenangan pada proyek yang akan mempengaruhi biaya.
S-curves
S-curves
Rate of Performance
Rate of performance (RP) is the ratio of actual work completed
to the percentage of work planned to have been completed at
any given time during the life of the project or activity.
Brenda Taylor, Senior Project Manager in South Africa,
suggests using this approach for estimating earned value.
For example, suppose the server installation was halfway
completed by the end of week 1. The rate of performance would
be 50 percent (50/100) because by the end of week 1, the
planned schedule reflects that the task should be 100 percent
complete and only 50 percent of that work has been completed.
Tingkat Kinerja
Tingkat Kinerja (RP) adalah perbandingan antara pekerjaan
sesungguhnya yang diselesaikan dengan persentase pekerjaan
yang direncanakan telah selesai pada waktu tertentu selama
masa proyek atau kegiatan.
Brenda Taylor, Senior Project Manager in South Africa,
menyarankan penggunaan pendekatan ini dalam
memperkirakan nilai yang diperoleh.
Misalnya, instalasi sebuah server baru selesai setengahnya
pada akhir minggu 1. Berarti Tingkat kinerjanya adalah 50
persen (50/100) karena pada akhir minggu 1, jadwal yang
direncanakan mencerminkan bahwa tugas harus 100 persen
lengkap dan hanya 50 persen dari pekerjaan yang telah selesai.
Case Study
To complete our analysis of the status of a project, we must calculate the budget at
completion (BAC) and the estimate at completion (EAC). The parameters for this
analysis can be determined by asking the following questions for the Georgia Light
Rail project:
how much work should be done to get the preliminary designs
completed? - i.e., what is the PV?
how much work is completed at the present moment? - i.e., what is the
EV?
how much did the actual completed work done cost? - i.e., what is the AC?
what was the total job of completing the preliminary designs supposed to
cost? - i.e., what is the BAC?
The BAC is the sum of the total budgets allocated to the project and is equivalent
to the final point on the project baseline. For the Georgia Light Rail project, the
BAC to deliver the preliminary designs is approximately $50,000. It is what the
project effort should cost.
The estimate at completion identifies either the hours or the dollars that represent
a realistic appraisal of the work when performed. It is equal to the sum of all costs
PROJECT
MANAGEMENT
to date, plus the
estimate of
all remaining work.PROFESSIONAL
M.P.D.C
Studi Kasus
Untuk melengkapi analisis kita tentang status proyek, kita harus menghitung
anggaran di penyelesaian (BAC) dan estimasi pada penyelesaian (EAC). Parameter
untuk analisis ini dapat ditentukan dengan mengajukan pertanyaan-pertanyaan
berikut untuk proyek Georgia Light Rail:
Berapa banyak pekerjaan yang harus dilakukan untuk mendapatkan
desain awal selesai? - seperti, apa itu PV?
Berapa banyak pekerjaan selesai pada saat ini? - seperti, apa itu PV?
Berapa banyak biaya pekerjaan sesungguhnya yang telah diselesaikan? seperti, apa itu AC?
Apakah total pekerjaan dari penyelesaian desain awal merupakan suatu
biaya? - seperti, apa itu BAC?
BAC adalah jumlah total anggaran yang dialokasikan untuk proyek dan setara
dengan titik akhir pada awal proyek. Untuk proyek Georgia Light Rail, BAC untuk
memberikan desain awal adalah sekitar $ 50.000. Ini adalah apa upaya proyek
harus biaya.
Estimasi pada penyelesaian mengidentifikasi baik jam atau dolar (harga) yang
mewakili penilaian realistis pekerjaan bila dilakukan. Hal ini sama dengan jumlah
PROFESSIONAL
semua biaya PROJECT
sampai saat MANAGEMENT
ini, ditambah perkiraan
semua pekerjaan yang tersisa.
M.P.D.C
Studi Kasus(lanjutan)
Pada minggu ke 4, AC adalah $ 16.256 dan EV adalah $ 11.617 (mana CPI
adalah 0.71 atau 71%)
EAC adalah BAC / CPI
$ 50,000 / 0.71
$ 70,423
EAC menunjukan jumlah dolar (biaya) yang dibutuhkan untuk menyelesaikan
proyek. Perkiraan pada estimasi terbaik dari total biaya proyek
yang didasarkan pada kinerja proyek.
EAC