Professional Documents
Culture Documents
Project Cost Management
Project Cost Management
Plan Cost
Management
Control
Costs
Estimate Costs
Determine
Budget
INPUT
TOOLS &
TECHNIQUES
OUTPUT
INPUTS
TOOLS &
TECHNIQUES
OUTPUTS
10
11
Cost estimate:
Costs are estimated for all resources that will be charged to the project
(ex: labor, materials, equipment, services, and facilities, inflation, cost of
financing, contingency costs, etc)
Include the identification and consideration of costing alternatives to
initiate and complete the project
A quantitative assessment of the likely costs for resources required to
complete the activity.
A prediction that is based on the information known at a given point in
time
Generally expressed in units of some currency
Should be reviewed and refined during the course of the project to reflect
additional detail as it becomes available and assumptions are tested
The accuracy of a project estimate will increase as the project progresses
through the project life cycle
12
13
14
15
16
17
18
19
20
BANGUNAN
GEDUNG
PERSIAPAN
Sub Project
FONDASI
SubNetwork
Activity
STRUKTUR
BAWAH
STRUKTUR
ATAS
STRUKTUR
BETON
PELAT
KOLOM
FINISHING
STRUKTUR
BAJA
BALOK
MACHANICAL
ELEKTRICAL
BALOK
Sub Activity
BEKISTING
Resources
Material
Breakdown
PEMBETONAN
TENAGA KERJA
PC
MATERIAL
PASIR
PEMBESIAN
PERALATAN
KERIKIL
23
Faktor
Indikator
Lokasi
Desain
Kualitas Bangunan
Konstruksi
Waktu
24
INPUT
TOOLS &
TECHNIQUES
OUTPUT
25
26
27
28
Jenis Pekerjaan
1.
2.
3.
4.
5.
6.
7.
8
9.
Galian
Timbunan
Pas. Batu kali
Pas. Batu bata
Beton bertulang
Lantai
Kuda-Kuda
Penutup Atap
Dst
Satuan
Pek.
M3
M3
M3
M2
M3
M2
M3
M2
Harga
Satuan
Pek
(Rp)
Kuantitas pekerjaan
Fondasi
Struktur
Finish-ing
Jumlah
Jumlah
Harga
( Rp )
Jenis Pekerjaan
1.
2.
3.
4.
5.
6.
7.
8
9.
Galian
Timbunan
Pas. Batu kali
Pas. Batu bata
Beton bertulang
Lantai
Kuda-Kuda
Penutup Atap
Dst
Satuan
Pek.
M3
M3
M3
M2
M3
M2
M3
M2
Jumlah
Harga
satuan
Jumlah Harga
Pasir
Bt.
kali
Bt
Bata
Besi
beton
Kayu
Tege
l
Ds
t
Jenis Material
1.
2.
3.
4.
5.
6.
7.
8
9.
Semen
Batu Kali
Pasir
Batu pecah
Batu Bata
Tegel
Kayu
Kosen
Dst
Harga
Satuan
(Rp)
Kuantitas material
Fondasi
Struktur
Finish
-ing
Zak
M3
M3
M3
bh
bh
M3
M3
Jumlah
Jumlah
Harga
( Rp )
1.
2.
3.
4.
5.
6.
Jam Harga
oper Sewa
asi
Alat Sendiri
BBM
Oli
Perba
ikan
Mob/
De- Jumlah
mob
Buldozer
Excavator
T. Crane
D. Truck
Pompa
Dst
Jumlah biaya Alat
Jenis
Pekerjaan
1.
2.
3.
4.
5.
6.
7.
8
9.
Galian
Timbunan
Pas. Batu kali
Pas. Batu
bata
Beton
bertulang
Lantai
Kuda-Kuda
Penutup Atap
Dst
Jumlah
Vol.
Pek
.
Budget
Pek (Rp)
Subkon A
Vol.
pek
Harga
Subkon
Sbkon B
Vol.
pek
Harga
Subkon
Kel.
Sub.Kel
Rp.
Keterangan
II.
1.
BAHAN / MATERIAL
2.
UPAH
3.
ALAT
4.
SUBKONTRAK
5.
PERSIAPAN / PENYELESAIAN
6.
OVERHEAD LAPANGAN
SUB TOTAL
KEWAJIBAN PAJAK
III
1.
PPN ( 10% )
2.
PPH
SUB TOTAL
IV
1.
2.
IV
Kode Subkelompok
II . 1
II . 2
II . 3
II . 4
II . 5
II . 6
: II . 1 . 1
- Pasir
: II . 1 . 2
- Batu pecah
: II . 1 . 3
- Besi beton
: II . 1 . 4
- Dan seterusnya
: II . 1 . n
INPUT
TOOLS &
TECHNIQUES
OUTPUT
39
40
41
42
43
Definition
Cost Performance
Index (CPI) = EV/AC
Schedule Performance
Index (SPI) = EV/PV
Performance Measure
45
Forecasting
Term
Definition
Budget At Completion
(BAC)
Estimate At Completion
(EAC)
EAC = BAC/CPI
EAC = AC + BAC EV
EAC = AC + Bottom-up
ETC
EAC = AC + [(BAC
EV)/(CPI x SPI)]
EAC Alt 4, If both the CPI and SPI influence the remaining work
46
47
Anggaran
Biaya
Realisasi
Biaya
4000
5000
3000
3000
6000
4000
5000
2500
8000
1000
Value
14.000
15.500
11.000
-4.500
-3.000
0,709 < 1
0,786 < 1
26.000
Forecasting
Term
Definition
Value
EAC = BAC/CPI
36.671
EAC = AC + BAC EV
30.500
EAC = AC + Bottom-up
ETC
15.500 +
20.000 (est) =
35.500
42.417
6,82 months
Projected
Slippage
31200
28600
Projected
Overrun
26000
23400
AC
20800
18200
PV
15600
13000
10400
7800
EV
5200
2600
0
6
6.82
51
PENGADAAN &
KONSTRUKSI
REALISASI
BIAYA
TINDAKAN
PERBAIKAN
ANALISIS
PENYIMPANGAN.
SESUAI
BUDGET
EVALUASI
BIAYA
DOKUMENTASI
OVER
BUDGET
Referensi:
1.Project Management Institute (PMI), A Guide to project
Management Body Of Knowledge, PMBOK Guide 5th Edition, 2013
2.Ikatan Ahli Manajemen Proyek Indonesia (IAMPI), Pelatihan
Sertifikasi Manajemen Proyek, Materi Project Cost Management,
2014
3.Asiyanto, MBA, IPM, Ir, Construction Project Cost Management",
PT. Pradnya Paramita Jakarta, 2005.
4.DellIsola, M.D., Architects Essentials of Cost Management,
John Wiley & Sons Inc, 2002
53
Terima Kasih
54