Professional Documents
Culture Documents
KKMC WS4 Elec Presentation Rev 1
KKMC WS4 Elec Presentation Rev 1
KKMC WS4 Elec Presentation Rev 1
ELECTRICAL
SYSTEMS
LV Distribution
Power Systems Lighting Systems
and Sub Systems
Page 2
LV Distribution AGENDA
Page 3
General Overview Electrical Systems
Objectives of Schematic Design:-
Preliminary design criteria and goals for recommended electrical systems for all
buildings including power distribution system.
Utilities
Lighting system
(see separate presentation)
Drivers for
Hospital
Distribution
Design
Facilities must have the
Disaster recovery role capability of delivering on
delineation - advice a continuous basis for a
from MOH period exceeding several
weeks all critical health
services.
Agreed
Sustainability/efficiency
target
Authority Regulations/
Approvals
Page 5
Power Systems- Applicable Codes and Standards
The Client has requested that codes and standards for KKMC be those which would be
applicable if this project were to be constructed in the United States.
Compliance with local authorities codes and standards is also of great importance and Saudi
Building Codes are listed accordingly.
Page 6
Power Systems- Applicable Codes and Standards
Saudi Building Code
SB 401 Electrical
Electrical Codes
Americans with Disabilities Act (ADA)
Guidelines for Design and Construction of Health Care Facilities 2010 Edition
2012 International Building Code (IBC)
International Fire Code (IFC) 2012
Safety Code for Elevators and Escalators - ASME A17.1 2007
NFPA 110; Standard for Emergency and Standby Power Systems (2110)
NFPA 780; Standard for the Installation of Lightning Protection Systems (2011)
NFPA 70 - National Electrical Code (NEC) 2011 Edition
International Fire Code (IFC) 2009 Edition
International Mechanical Code (IMC) 2009 Edition
NFPA 99 - Standard for Health Care Facilities
NFPA 101 - Life Safety Code
Page 7
Power Systems- Applicable Standards
Codes and Standards (contd)
Standards:
Aecom have held a number of meetings with the Saudi Electrical Company (SEC) in
attempts to establish and identify any:-
Page 9
Power Systems- Applicable Standards
The developer will be responsible for the installation and maintenance of their MEP
infrastructure on the consumers side of the Network.
For projects requiring a load in excess of 16mVA, SEC do not give guidance on
requirements for installation and will not be approving the installation on the consumers
side.
(There are no guidelines for the service within the plot and there is no requirement for
SEC approval of the design).
The interface point will be at the HV switch within the grid station. The 13.8kV cables
will be coordinated up to this point only.
SEC have advised that they will not review the design and will not undertake any
inspections of the installed works. Page 10
Power Systems- Applicable Standards
(See RFA)
SEC advised that they would only be responsible for the design up to the grid station.
Once the grid station is energized that the ownership will pass to SEC and no access will
not be provided to KKMC.
The design on the consumer side should incorporate switchgear in order to isolate part of
the network for maintenance or emergency purposes
SEC advised that the cable distribution within the site will be owned and need to be
maintained by KKMC.
Page 11
HV/MV Schematic
Primary Sub-station
Generators
ATS
Page 12
Power Systems-
Distribution Strategy to meet NFPA
Requirements
NFPA/NEC requires that the emergency distribution be split into functional
branches.
Page 13
Power Systems-
Distribution Strategy to meet NFPA
Requirements
Critical Branch
The Critical branch of the emergency system shall supply power for the following lighting, power
outlets, and equipment:
Task illumination, selected power outlets, and fixed equipment in critical care areas that use
anesthetizing gases
IPS systems in special environments
Task illumination and selected power outlets in patient care areas
Additional specialized patient care task illumination and power where needed
Nurse call systems
Blood, bone, and tissue banks
Telephone equipment rooms and closets
Task illumination, selected power outlets, and selected power circuits for general care beds
Page 14
Power Systems-
Distribution Strategy to meet NFPA
Requirements
Life Safety Branch
The life safety branch of the emergency system shall supply power for the following
lighting, power outlets, and equipment:
A. Illumination of means of egress
B. Exit sign
C. Alarm and Alerting Systems
Fire alarms
Medical gas alarms
Building automation systems where required for life safety
D. Communication Systems Where used for issuing instructions during emergency
conditions
E. Generator and transfer switch locations
F. Generator set accessories
G. Elevators Cab lights, control, communications and signal systems
H. Automatic Doors Used for building egress
(Everything that you need to allow safe evacuation of building if mains power is lost).
No function other than those above Page 15
Power Systems-
Distribution Strategy to meet NFPA
Requirements
Equipment System
The equipment branch shall be installed and connected to the alternate power source such that the
equipment can be automatically restored to operation at appropriate time-lag intervals following the
energizing of the emergency system or manually restored to operation.
Equipment that must be arranged for delayed automatic connection to the alternate power source
includes the following:
Central suction systems
Sump pumps and other equipment required to operate for the safety of a major apparatus,
Compressed air systems for medical and surgical functions
Stair pressurization and smoke control systems
Kitchen hood supply and exhaust systems if required to operate during a fire in or under the hood
Page 16
Power Systems-
Distribution Strategy to meet NFPA
Requirements
Dedicated Branch
Transformers
Page 17
Power Systems- Building MV Distribution
Building
Distribution
Option 2
Location of Transformer
and LV Rooms Tx. Rooms and LV Rooms
are located on different
levels.
Cable Trays
Maintenance
Page 19
Power Systems- Building MV Distribution
Strategy
Considerations: Option 2 19th Floor
Tx.
Tx. Rooms
Rooms and
and LV
LV Rooms
Rooms are
are located
located on
on
Cable costs different levels.
different levels.
Cable sizes
Ease of
maintenance 12th Floor
Access for
maintenance
Access for
replacement
Vertical
transportation
4th Floor
Page 20
Power Systems- Transformer movement
strategy
19th Floor
12th Floor
4th Floor
Page 21
Power Systems Transformer movement
strategy
Service Corridor
To Loading Dock
12th Floor
4th Floor
MV supply from
MV supply from
service tunnel
service tunnel
Page 23
Power Systems- Distribution Strategy Vertical
Risers
M
MV
VCCa
abble
les
s
Vertical Risers MV to
transformers
Page 24
Power Systems Distribution Strategy Vertical
Risers
Vertical Risers MV to
transformers
Page 25
Power Systems Distribution 4th Floor
MV Risers
Page 26
Power Systems Distribution
Transformers
MV Switchpanels
LV Switchpanels
Page 28
Power Systems- Building LV Distribution Design
progress
Building Option 1
Distribution
Location of Transformer
Option 2
and LV Rooms
Cable Trays
Maintenance
Page 29
HV/MV Schematic
Primary Sub-station
Generators
ATS
To Transformers
Page 30
X
Page 31
Power Systems LV Distribution
Sub-Main LV Panel
Page 32
Power Systems LV Distribution
Point of use
Page 33
Power Systems LV Distribution
IPS
Panel
(Dual supply)
Page 34
Power Systems - LV Distribution
MV Risers
Page 35
Power Systems Distribution
- Critical DBs
- Normal (Non-Essential) DBs
- UPS DBs
Page 36
Power Systems Distribution Strategy Horizontal
Distribution
Page 38
Power Systems Horizontal Distribution
Page 39
Thank you Any questions?
KKMC Workshop
No. of 500KVA
Transformers
Required = .95 Nos
Page 42
Power Systems Non Health Load Schedules
NON HEALTH CARE BUILDINGS - TOTAL LOAD BUILD UP
Area NO OF TRANSFORMERS
PROPOSED/ BLDG FED FROM Typ Total
S.NO BUILDING NAME REMARKS
CONNECTED DEMAND
sqm LOAD/BLDG DEMAND LOAD/BLDG PROPOSED POCKET
(kW) FACTOR (kW) Qty (No) Rating (MVA) SUBSTATION SUBSTATION blgs TX
Phase 1
Non Healhcare
OFFICE, RESEARCH
3 5262.89 0.80 4210.31 3 2 Yes Yes FOR 1 BUILDING (G+1+R)
AND CONFERENCE
CENTRAL UTILITY
5 1 0
PLANT
7 HOSPICE BUILDING 5233.61 534.89 0.80 427.91 1 1 Yes 1 1 FOR 1 BUILDING (G+1+R)
FOR 1 BUILDING
8 FAMILY HOUSING 33,185 5415.97 0.50 2707.99 2 2 Yes 1 2
(G+25+R)
9 HOTEL (OTHERS)
10 COMMUNITY CENTRE 11,946 1041.20 0.80 832.96 1 1.5 Yes 1 1 FOR 1 BUILDING (G+1+R)
FOR 1 BUILDING
11 MALE HOUSING 34,329 3845.98 0.50 1922.99 2 2 Yes 1 2
(B+G+19+R)
FOR 1 BUILDING
12 FEMALE HOUSING 59,440 9266.64 0.50 4633.32 4 2 Yes 2 8
(G+28+R)
14 VILLA HOUSING 2,480 565.20 0.50 282.60 1 0.5 Yes 1 1 FOR 8 VILLA (G+1)
36679.21 20523.35
Page 43
Power Systems Non Health Distribution
Page 44
Power Systems Non Health Distribution
Page 45
Power Systems Non Health Distribution
Emergency (standby) generation for Non Health Buildings.
(See RFA)
Page 46
Power Systems Non Health 1 Bed Apartment
(See RFA)
Page 47
Power Systems Non Health 2 Bed Apartment
Page 48
Power Systems Non Health 3 Bed Apartment
Page 49
Power Systems Non Health - Villa
Page 50
Power Systems Non Health Tower Apartments
Page 51
Power Systems Non Health Tower Apartments
Page 52
Power Systems Horizontal Distribution Tower Apartments
Page 53
Power Systems Horizontal Distribution Tower Apartments
Page 54
Power Systems Horizontal Distribution - Apartments
Page 55
Thank you Any questions?
KKMC Workshop