Professional Documents
Culture Documents
Batchwise and Semibatch Processing: Sizing Plant Items
Batchwise and Semibatch Processing: Sizing Plant Items
Processing
Lecture 4
Sizing Plant Items
Principles of Sizing
Start with the recipe and the mass balance for the process
vessel 2
vessel 1 S
A
Reaction
A+B Separation
C
+C
B
vessel 1 vessel 2
A+B+
C+S
Taking a basis of 100kg of A
vessel 2
100 kg S
vessel 1
100 kg A
Reaction
60 kg A Separation
60 kg B 76 kg C
100 kg B 80 kg C
vessel 1 vessel 2
60 kg A
60 kg B
4 kg C
100 kg S
Solution - Occupancies
Vessel 1
200 kg 1 m3 kg
Occupancy 1000 2.924 m 3 /te
76 kg 900 kg te
Vessel 2
300 kg 1 m3 kg
Occupancy 1000 3.947 m 3 /te
76 kg 1000 kg te
Using one unit per stage and zero-wait transfer, the cycle time is max{8,2} = 8 hours
Solution vessel sizes
Using one unit per stage and zero-wait transfer, the cycle time is
max{8,2} = 8 hours
One way to achieve this is to duplicate the vessel with the longer
cycle time and operate the smaller vessels in a staggered manner
so that a smaller batch is passed forward more frequently.
Say we have two vessels for the reaction stage of our example
(vessels 1a and 1b). This means a batch will pass forward to the
separation stage every 4 hours. This gives a cycle time of 4 hours.
If we can apply the 2/3 power law to the cost of vessels and the
vessels are essentially the same type, the cost involved is
2 1.0 1.5
2 2
3 3
0.902 of the original design
2 2
3 3
2
3
Using this initial assumption of equal batch sizes we can determine the
number of campaigns of the different products and then the actual
batch sizes of each. Hence we can find the vessel sizes.
If the batch size for all three products is initially taken to be X tonnes,
regardless of product, then
Annual production of A = 50XnA = 650; similarly for B and C
50X nB = 450
50X nC = 200
Substituting for nC
The ratios of nA:nB:nC have not been maintained but we will allow for this by
changing the batch sizes of the three products.
Now we need to calculate the actual batch sizes required for each product in
order to meet the production requirement:
We can use these with the occupancies from before to calculate the vessel
sizes
So, for example for product A and vessel 1 the occupancy is
1.25 l/kg and the batch size is 2600kg
i.e. we must have 6, 7.5, 12.0 and 15.6 m3 for stages 1,2,3 and 4 respectively.
Do you know?
What is meant by occupancy?
How to calculate vessel size from occupancy and batch
size?
What initial assumptions are made when calculating
vessel sizes for a multiproduct plant from the annula
required productions, number of batches in a campaign,
recipe and occupancies?