HCA Tools For Regeneration
HCA Tools For Regeneration
New Players
Procurement Cost/Timescales
One stop shop
– Development
– Construction
– Dev Management and other Services
Contra
Thriving communities, affordable homes
Appointment Process
1-2 days
17
Stage 1
Phone/Email
1-3 weeks
Stage 2
Sifting Brief
SELECTED PANEL
3-8 MEMBERS TO TENDER
6-8 weeks
Stage 3
Tender
SINGLE APPOINTED
1 DPP MEMBER
Key Principles
Deferral of land receipt
Fair balance of risk and reward
Risk sharing linked to scheme revenues and site
super-abnormals
Maintaining the principle of value capture
(overage mechanism)
Retention of construction costs risk by PSP
Flexibility to negotiate key terms
Pre-development Appraisal
– Post planning – pre-start on site
– Fix on build cost ceiling (apart from super abnormals)
– Estimated revenues
– Fix on gap funding requirement
Completion Appraisal
– Re-measure revenues – HCA will share in 50% of the shortfall in scheme revenues up to the
max public sector risk share sum (base case assumption)
– Cost savings to be shared 50:50 (base case assumption)
Heads of Terms
Site Development Agreement
Building Lease
Financial schedule
Housing Gap Funding Agreement
Equity Loan Agreement
State Aid Note