Professional Documents
Culture Documents
Bus Bar Schemes-New
Bus Bar Schemes-New
Bus Bar Schemes-New
06/04/17
The present electrical power system is a
complex interconnection of Generating
M L SHESHADRI
stations-Transmission systems-
Receiving stations- Distribution systems
and Load points.
In all the above phases of power flow, the
transfer of electrical energy takes place in
the electric sub stations.
2
2
THE ELECTRIC SUB STATION
INTRODUCTION
06/04/17
Basically an electrical sub station consists
M L SHESHADRI
of a number of incoming circuits and out
going circuits connected to common bus
bar systems.
3
THE ELECTRIC SUB STATION
INTRODUCTION
Each circuit connected to the bus bar will have
06/04/17
certain electrical component such as circuit
breakers, isolators, earth switches, current
M L SHESHADRI
transformers and voltage transformers.
4
THE ELECTRIC SUB STATION
INTRODUCTION
A sub station receives electrical power from
06/04/17
generating station through incoming
transmission lines and delivers electrical
M L SHESHADRI
power through the out going transmission
lines.
Sub station is an integral part of a power
system and is an important link between the
generating stations, transmission systems,
distribution systems and load points.
5
5
THE ELECTRIC SUB STATION
DESIGN CONSIDERATIONS
06/04/17
The sub station is designed with an
M L SHESHADRI
objective to provide maximum
reliability, flexibility, continuity of
service and to meet these objectives
with the lowest investment costs that
satisfy system requirement.
6
THE ELECTRIC SUB STATION
DESIGN CONSIDERATIONS
06/04/17
System requirements include the selection of
optimum voltage levels depending on the load
M L SHESHADRI
requirements and the transmission distances
involved. Generally, the generating source will be
far away from the load centers. The advantage of
capitalizing on low site costs, availability of ample
cooling water supply, economical fuel supply and
less stringent environmental considerations
compel construction of generating source far away
from load centers, there by, increasing
transmission distances.
7
7
THE ELECTRIC SUB STATION
DESIGN CONSIDERATIONS
06/04/17
Hence, to transmit power over long distances the
transmission voltage is to be increased and in our
M L SHESHADRI
country 400 kV is becoming common and higher
voltages for transmission is being explored. Many
factors such as voltage level, load capacity, site space
limitations, transmission line right of way requirement
and environmental considerations influence the design
of sub stations.
8
THE ELECTRIC SUB STATION
BUS LAYOUT AND SWITCHING ARRANGEMENT
06/04/17
power transformers, circuit breakers and disconnecting
switches, the bus layout and switching arrangement
M L SHESHADRI
selected will determine the number of switches and
power circuit breakers required.
9
THE ELECTRIC SUB STATION
SUB STATION LAYOUT AND BUS BAR SCHEMES
06/04/17
arrangement of various components in
M L SHESHADRI
the sub station relative to one another.
The layout is significant as it influences
the operation, maintenance, cost and
protection of the sub station. These
aspects are considered while designing
the sub station layout.
10
10
THE ELECTRIC SUB STATION
SUB STATION LAYOUT AND BUS BAR SCHEMES
06/04/17
lines, transformers, etc., the sub station can be
designed in several alternative ways.
M L SHESHADRI
The physical arrangement of the equipment is
called the layout of the sub station. The layout is
illustrated by means of single line diagrams.
11
THE ELECTRIC SUB STATION
SUB STATION LAYOUT AND BUS BAR SCHEMES
Switching requirement for normal operation.
06/04/17
Switching requirement during abnormal
conditions like short circuits and overloads.
M L SHESHADRI
Degree of flexibility in operations, simplicity.
Freedom from total shutdowns.
Maintenance requirements, space for
approaching various equipment for
maintenance.
Road/ rail for transporting main and auxiliary
equipment.
12
12
THE ELECTRIC SUB STATION
SUB STATION LAYOUT AND BUS BAR SCHEMES
06/04/17
Safety of personnel.
Protective zones for main and back up
M L SHESHADRI
protection.
Provision for bye pass facilities and for
extensions, space requirements.
Technical requirements such as ratings,
clearances, earth system, lightning protection.
Requirement for SCADA and communication.
Compatibility for local and ambient condition. 13
13
THE ELECTRIC SUB STATION
SUB STATION LAYOUT AND BUS BAR SCHEMES
06/04/17
The choice of bus bar schemes for ac yards
depend upon several factors mentioned above.
M L SHESHADRI
The important bus bar schemes are:
Single bus bar
Double bus bar with one breaker per circuit
Double bus bar with two breaker per circuit
Main and transfer bus
Ring bus or Mesh scheme
Breaker and a half(1 1/2 breaker) arrangement 14
14
THE ELECTRIC SUB STATION
SUB STATION LAYOUT AND BUS BAR SCHEMES
06/04/17
The various schemes are generally compared to
emphasize their advantage and limitations.
M L SHESHADRI
The basis of comparison is generally the degree
of reliability & economic justification.
15
THE ELECTRIC SUB STATION
VARIOUS BUS BAR SCHEMES
06/04/17
SINGLE BUS BAR SCHEME
M L SHESHADRI
BUS
ISOLATO
R
BREAKE
R
CURRENT TRANSFORMER
POWER TRANSFORMER
16
16
THE ELECTRIC SUB STATION
SINGLE BUS BAR SCHEME
Advantage Lowest cost
06/04/17
Disadvantage:
M L SHESHADRI
Maintenance without interruption of supply is not possible.
17
THE ELECTRIC SUB STATION
VARIOUS BUS BAR SCHEMES
06/04/17
SECTIONALISER
M L SHESHADRI
BUS SECTION-1 BUS SECTION-2
SECTIONALISER ISOLATO
R
BREAKE
R
CURRENT
TRANSFORMER
POWER TRANSFORMER
18
18
THE ELECTRIC SUB STATION
SINGLE BUS BAR SCHEME WITH BUS SECTIONALISER
06/04/17
distributed evenly on both the sections.
M L SHESHADRI
Where double feed is provided for any single load it is
preferable to have one circuit from each section.
19
THE ELECTRIC SUB STATION
DOUBLE BUS BAR WITH ONE BREAKER PER CIRCUIT
BUS-1
06/04/17
BUS-2
M L SHESHADRI
BUS COUPLER
BREAKER
BREAKER
POWER TRANSFORMER
20
20
THE ELECTRIC SUB STATION
DOUBLE BUS BAR WITH ONE BREAKER PER
CIRCUIT
This arrangement has the following advantages:
06/04/17
Each load may be fed from either bus.
Operational flexibility may be increased by grouping the
M L SHESHADRI
incoming and out going feeders in separate groups.
Either bus bar can be taken out for maintenance.
Bus coupler helps in on load change over from one bus
to the other.
Adopted where load and continuity justify additional
cost.
A major disadvantage is that the breaker can not be
taken out for maintenance without interrupting supply to
the concerned circuit.
21
21
THE ELECTRIC SUB STATION
DOUBLE BUS BAR WITH ONE BREAKER PER
CIRCUIT
06/04/17
Bus protection scheme may cause loss of sub
station when it operates if all circuits are
M L SHESHADRI
connected to that bus.
High exposure to bus faults.
Line breaker failure takes all circuits connected
to that bus out of service.
Bus tie breaker failure takes the entire sub
station out of service.
22
22
DOUBLE MAIN BUS & CB BYPASS ISOLATOR SYSTEM
T/F-1 T/F-2
06/04/17
M L SHESHADRI
TIE BREAKER
BREAKER
TRANSFER BUS
LINE LINE
24
24
THE ELECTRIC SUB STATION
MAIN AND TRANSFER BUS
This is an alternative to double bus single
06/04/17
breaker arrangement which provided for change
over to either bus for carrying out maintenance
M L SHESHADRI
on other bus. But it provided no facility for
breaker maintenance without interrupting power
supply to the concerned circuit.
The main and transfer bus works the other way
round.
This arrangement provides facility for carrying
out breaker maintenance but does not permit
bus maintenance. 25
25
THE ELECTRIC SUB STATION
MAIN AND TRANSFER BUS
06/04/17
Wherever maintenance is required on any breaker, the circuit is changed
over to the transfer bus and controlled through the bus coupler breaker.
M L SHESHADRI
Potential devices may be used on the main bus for relaying.
The cost is increased due to use of an extra isolator for each circuit and
providing interlock for bus coupler and circuit isolators.
Failure of bus or any circuit breaker results in shut down of entire sub
station. 26
26
DOUBLE MAIN BUS & TRANSFER BUS SYSTEM
T/F-1 T/F-2
BUS-1
BUS COUPLER
BUS-2
TRANSFER BUS
COUPLER
BAY3 BAY4 BAY5
BAY1 BAY2 TRANSFER BUS BAY6 BAY7 BAY8
27
BUS BAR ARRANGEMENTS
Double Bus Bar Arrangement with Transfer
Bus.
This arrangement provides more additional
flexibility, continuity of Power Supply,
permits periodic maintenance without total
shut down as the two main buses can be
operated independently with the same
redundancy.
28
THE ELECTRIC SUB STATION
DOUBLE BUS BAR WITH TWO BREAKER
PER CIRCUIT
06/04/17
M L SHESHADRI
BUS-1
BREAKER
BUS-2
29
LINE LINE 29
THE ELECTRIC SUB STATION
DOUBLE BUS BAR WITH TWO BREAKER PER
CIRCUIT
06/04/17
Each circuit has two dedicated breakers.
M L SHESHADRI
Has flexibility in permitting feeder circuits to be
connected to either bus.
Any breaker can be taken out of service for
maintenance.
High reliability.
Most expensive. Used only in large generating
stations where security of connection is paramount.
30
30
THE ELECTRIC SUB STATION
RING BUS OR MESH SCHEME
06/04/17
ISOLATOR
M L SHESHADRI
BREAKER
LINE
POWER TRANSFORMER
LINE
31
31
THE ELECTRIC SUB STATION
RING BUS OR MESH SCHEME
In this scheme the breakers are arranged in a ring with
circuits connected between breakers.
06/04/17
There are the same number of circuits as there are breakers.
M L SHESHADRI
During normal operation, all breakers are closed. For a circuit
fault, two breakers are tripped, and in the event one of the
breaker fails to operate to clear the fault, an additional circuit
will be tripped by operation of breaker- failure back up relays.
32
32
THE ELECTRIC SUB STATION
RING BUS OR MESH SCHEME
The circuits connected to the ring are arranged so that
sources are alternated with loads.
06/04/17
For an extended circuit outage, the line isolator may be opened
and the ring can be closed.
M L SHESHADRI
No changes to protective relays are required for any of the
various operating conditions or during maintenance.
33
THE ELECTRIC SUB STATION
One and a Half Breaker Arrangement.
34
THE ELECTRIC SUB STATION
BREAKER -AND -A -HALF SCHEME
06/04/17
BUS-1
ISOLATOR
M L SHESHADRI
BREAKER
LINE
TIE BREAKER
35
BUS-2 35
I-CONFIGUARATION
FEEDER1 FEEDER3 FEEDER5 FEEDER7 FEEDER9 FEEDER11
BAY10
BAY13
BAY16
BAY4
BAY7
BAY1
BAY11
BAY14
BAY17
BAY8
BAY2
BAY5
BAY12
BAY18
BAY15
BAY9
BAY3
BAY6
BUS-2
36
FEEDER2 FEEDER4 FEEDER6 FEEDER8 FEEDER10 FEEDER12
D-CONFIGUARATION
FEEDER1 FEEDER2 FEEDER5 FEEDER6 FEEDER9 FEEDER10
BAY15
BAY13
BAY3
BAY9
BAY1
BAY7
DIA1 DIA3 DIA5
BUS-1
BUS-2
BAY18
BAY12
BAY10
BAY6
BAY16
BAY4
06/04/17
The breaker and a half scheme, some times called
the three switch scheme, has three breakers in
M L SHESHADRI
series between the main buses.
38
THE ELECTRIC SUB STATION
BREAKER -AND -A -HALF SCHEME
06/04/17
closed and both buses are energized.
A circuit is tripped by opening the two associated circuit
M L SHESHADRI
breakers.
Tie breaker failure will trip one additional circuit, but no
additional circuit is lost if a line trip involves failure of a
bus breaker.
Either bus may be taken out of service at any time with
no loss of service.
With sources connected opposite loads, it is possible to
operate with both buses out of service.
Breaker maintenance can be done with no loss of
service, no relay changes, and simple operation of the
breaker isolators. 39
39
THE ELECTRIC SUB STATION
BREAKER -AND -A -HALF SCHEME
06/04/17
The breaker-and-a-half arrangement is more
expensive than other schemes, except the double-
M L SHESHADRI
breaker-double-bus scheme.
40
THANK YOU
06/04/17
ANY QUESTIONS ?
M L SHESHADRI
41
41