Professional Documents
Culture Documents
Topic6 Time Cost Trade Off
Topic6 Time Cost Trade Off
Topic6 Time Cost Trade Off
6/23/2017 8:42 AM 1
Reasons to Reduce Project Durations:
1. To realize incentive pay
2. To fit within the contractually required time (influences
Bid price).
3. To avoid paying Liquated Damages/Damage for delay
causes (or avoid damaging the companys
relationship).
4. To complete a project early & move on to another
project (Although the Job-specify profit may reduce,
company profile may increase).
5. To complete a project when weather conditions make
it less expensive (Avoid temporary Heating, avoid
completing site work during raining season).
Normal Crash
Activity Preceded by Duration Cost Duration Cost
(weeks) (SR) (weeks) (SR)
A 12 7000 10 7200
B A 8 5000 6 5300
C A 15 4000 12 4600
D B 23 5000 23 5000
E B 5 1000 4 1050
F C 5 3000 4 3300
G E,C 20 6000 15 6300
H F 13 2500 11 2580
I D, G, H 12 3000 10 3140
36,500 38470
0 12 12 12 8 20 20 5 25 27 20 47 47 12 59
A B E G I
0 0 12 14 2 22 22 2 27 27 0 47 47 0 59
2@100 2@150 1@50 5@60 2@70
2
12 15 27 27 5 32 32 13 45
F H ES D EF
C
29 2 34 34 2 47 Activity
12 0 27
3@200 1@300 2@40 LS F LF
Crash limit
Cycle Activity Can Be Days Cost per Cost for Total Project
Nil
# to Shorten Shortened Shortened Week Cycle Cost Duration
0 36,500 59
1 G 5 2 2 60 120 36,620 57
0 12 12 12 8 20 20 5 25 27 18 45 45 12 57
A B E G I
0 0 12 14 2 22 22 2 27 27 0 45 45 0 55
2@100 2@150 1@50 3@60 2@70
12 15 27 27 5 32 32 13 45
ES D EF
C F H
Activity
12 0 27 27 0 32 32 0 45
3@200 1@300 2@40 LS F LF
Crash limit
Cycle Activity Can Be Days Cost per Cost for Total Project
Nil
# to Shorten Shortened Shortened Week Cycle Cost Duration
0 36,500 59
1 G 5 2 2 60 120 36,620 57
2 I 2 - 2 70 140 36,760 55
0 12 12 12 8 20 20 5 25 27 18 45 45 10 55
A 0 B E G I
0 0 12 14 2 22 22 2 27 27 0 45 45 0 55
2@100 2@150 1@50 3@60 0
12 15 27 27 5 32 32 13 45
ES D EF
C F H
Activity
12 0 27 27 0 32 32 0 45
3@200 1@300 2@40 LS F LF
Crash limit
Cycle Activity Can Be Days Cost per Cost for Total Project
Nil
# to Shorten Shortened Shortened Week Cycle Cost Duration
0 36,500 59
1 G 5 2 2 60 120 36,620 57
2 I 2 2 70 140 36,760 55
3 A 2 2 100 200 36,960 53
Spring 2008, Time-Cost-Trade-off 17
King Saud University Dr. Khalid Al-Gahtani
18 23 41
D 2
20 2 43
0
0 10 10 10 8 18 20 5 25 25 18 43 43 10 53
A B E G I
0 0 10 12 2 20 22 2 27 25 0 43 43 0 53
0 2@150 1@50 3@60 0
10 15 25 25 5 30 30 13 43
ES D EF
C F H
Activity
10 0 25 25 0 30 30 0 43
3@200 1@300 2@40 LS F LF
Crash limit
Cycle Activity Can Be Days Cost per Cost for Total Project
Nil
# to Shorten Shortened Shortened Week Cycle Cost Duration
0 36,500 59
1 G 5 2 2 60 120 36,620 57
2 I 2 2 70 140 36,760 55
3 A 2 2 100 200 36,960 53
4 H, G 2 2 2 60+40 200 37,160 51
Spring 2008, Time-Cost-Trade-off 18
King Saud University Dr. Khalid Al-Gahtani
18 23 41
D
18 0 41
0
0 10 10 10 8 18 18 5 23 25 16 41 41 10 51
A B 0 E G I
0 0 10 10 0 18 20 2 25 25 0 41 41 0 51
0 2@150 1@50 1@60 0
10 15 25 25 5 30 30 11 41
ES D EF
C F H
Activity
10 0 25 25 0 30 30 0 41
3@200 1@300 0 LS F LF
Crash limit
Cycle Activity Can Be Days Cost per Cost for Total Project
Nil
# to Shorten Shortened Shortened Week Cycle Cost Duration
0 36,500 59
1 G 5 2 2 60 120 36,620 57
2 I 2 2 70 140 36,760 55
3 A 2 2 100 200 36,960 53
4 G, H 2 2 2 60+40 200 37,160 51
Spring 2008, Time-Cost-Trade-off 19
5 B, C
King Saud University 2 2 Al-Gahtani
Dr. Khalid 150+200 700 37,860 49
16 23 39
D
16 0 39
0
0 10 10 10 6 16 16 5 21 23 16 39 39 10 49
A B E G I
0 0 10 10 0 16 18 2 23 23 0 39 39 0 49
0 0 1@50 1@60 0
10 13 23 23 5 28 28 11 39
ES D EF
C F H
Activity
10 0 23 23 0 28 28 0 39
1@200 1@300 0 LS F LF
Crash limit
30000
Indirect
25000
cost
20000 Total
15000 Cost
10000
5000
0
48 49 50 51 52 53 54 55 56 57 58 59 60
Project Duration (Week)
On completion, the project will give a return of $110/day. Using time-cost trade-off method,
how much would you like to compress the project for maximizing the return? Show all
calculations.