OFFICE TOWER
Office Tower TALAN TOWERS PROJECT
Technical areas
Office Tower BOH
Tenant areas
Verny Offices 28th & 29th floor
Office Tower TALAN TOWERS PROJECT
Progress:
Civil works completed 95% - Remaining
Technical areas works due to MEP requirements
Design completed 100%
Office Tower BOH Final fit out finishing works ongoing 85%
Tenant areas Risk Items:
Verny Offices 28th & 29th floor MEP and fit out works overlapping
MEP equipment testing and
commissioning putting into operations
Area critical for operation of Client
premises and Tower usage
Office Tower TALAN TOWERS PROJECT
Progress:
Civil works completed 90% - Screed and
Technical areas minor revisions due to design changes
Design completed 100%
Office Tower BOH Final fit out finishing works ongoing 85%
Tenant areas - tiling, suspended ceiling, painting, etc.
Verny Offices 28th & 29th floor Risk Items:
Evacuation staircases completion by
October 15th due to lack of workforce
Fitting smoke exhaust grill into
suspended ceiling
Office Tower TALAN TOWERS PROJECT
Progress:
Civil works completed 95% - Partition
Technical areas works due design changes
Design completed 100%
Office Tower BOH Final fit out and remedial works ongoing
Tenant areas 75%.
Verny Offices 28th & 29th floor LVL 10, 13, 15, 26, JLL Office handed
over to future tenants
Tenant contractor finishing works
ongoing
Risk Items:
Material delivery for public toilets, lift
lobbies and corridors
Office Tower TALAN TOWERS PROJECT
Progress:
Civil works completed 100%
Technical areas Design completed 100%
Risk Items:
Office Tower BOH High percentage of remedial works due
Tenant areas damages
Verny Offices 28th & 29th floor Final fit out commencement
Material delivery and installation
Proper quality control from contractors
side
Office Tower TALAN TOWERS PROJECT
VERNY OFFICE
AKFA
TOTAL
33.39%
100%
100.00%
100.00%
51.14%
35.10%
48.86%
64.90%
30-Jun-16
30-Jun-16
15-Oct-16
15-Oct-16
107
CONTRACTORS
OFFICE TOWER
PERFOMANCE
Contractor
Weighta
ge
Planned
%COMP
Actual
%COMP
Slippage
Planned
Finish
Expected
Finish
Delay For August 2016
Renaissance 54.67% 86.91% 84.44% 2.47% 30-Nov-16 30-Nov-16 0
PODIUM
Podium TALAN TOWERS PROJECT
Retail Area
Kitchen and Laundry Area
Underground levels
Landscaping
Podium TALAN TOWERS PROJECT
Progress:
Retail Area Civil works completed 98% - minor
revisions due design changes
Kitchen and Laundry Area Design completed 100%
Underground levels Final fit out and remedial works ongoing
65%.
Landscaping Risk Items:
Overlapping of MEP and fit out works
MEP fire and life safety systems
operation
Material delivery on site
Podium TALAN TOWERS PROJECT
CONTRACTORS
ge %COMP %COMP Finish Finish
CAR PARK
HOTEL TOWER
Hotel Tower TALAN TOWERS PROJECT
Progress:
Guest Room Areas Civil work completed 85%
Shop drawings completed 95%
Public Areas No major Design issues
F&B Areas Average daily Manpower 250 workers
Residential Apartments Risk Items:
Quality control from Contractor side on
low level
Supervision of Site activities and
Subcontractors
Procurement of Material
Delivery of Materials and equipment to
Site
Quality of work force
Not completed position regarding Civil
works
Hotel Tower TALAN TOWERS PROJECT
Progress:
Guest Room Areas Civil work completed 85%
Shop drawings completed 95%
Public Areas No major Design issues
F&B Areas Average daily Manpower 250 workers
Residential Apartments
Hotel Tower TALAN TOWERS PROJECT
Progress:
Guest Room Areas Civil work completed 55%
Shop drawings completed 50%
Public Areas
F&B Areas Risk Items:
Quality control from Contractor side on
Residential Apartments low level
Supervision of Site activities and
Subcontractors
Procurement of Material
Delivery of Materials and equipment to
Site
Long lead Items
Special finishes and Lighting fixtures
Ongoing Shop drawings approval
Coordination of Shop drawings
Hotel Tower TALAN TOWERS PROJECT
Progress:
Guest Room Areas Civil work completed 55%
Shop drawings completed 50%
Public Areas
F&B Areas
Residential Apartments
Hotel Tower TALAN TOWERS PROJECT
Progress:
Guest Room Areas Civil work started in September
Shop drawings completed 25%
Public Areas Shop drawings to be submitted by 1st
F&B Areas October
Residential Apartments Risk Items:
Ongoing Submittal process
18th floor Shop drawings only 10%
submitted
Low progress on Site
Special finishes Materials and Lighting
fixtures
Hotel Tower TALAN TOWERS PROJECT
Progress:
Guest Room Areas Civil work started in September
Shop drawings completed 25%
Public Areas Shop drawings to be submitted by
F&B Areas 1st October
Residential Apartments
Hotel Tower TALAN TOWERS PROJECT
Progress:
Guest Room Areas Civil work started in September
Design completed 38%
Public Areas 20 floor has chosen as Mock-up floor
F&B Areas
Risk Items:
Residential Apartments Design not completed
MEP Design not finalized
Potential Coordination clashing's
between MEP and Architecture
Ongoing Submittal approval process
Potential claims for delays caused by
other contractors work and not finalized
Design
Hotel Tower TALAN TOWERS PROJECT
Progress:
Guest Room Areas Civil work started in September
Design completed 38%
Public Areas 20 floor has chosen as Mock-up floor
F&B Areas
Residential Apartments
Hotel Tower TALAN TOWERS PROJECT
RESIDENTIAL APARTMENTS
Contractor
Weighta
ge
Planned
%COMP
Actual
%COMP
Slippage
Planned
Finish
Expected
Finish
Delay CONTRACTORS
Renaissance
KUKBO
15.01%
2.58%
38.93%
72.53%
19.74%
53.25%
19.19%
19.28%
31-Jan-17
30-Sep-16
31-Jan-17
30-Sep-16
0
0
PERFOMANCE
Energoproj 82.41% 2.47% 6.5% 0.00% 31-Jan-17 28-Feb-17 28
SPA
RITZ CARLTON
HANDOVER SCHEDULE
TALAN TOWERS PROJECT
VERTICAL
TRANSPORTATION
VERTICAL TRANSPORTATION
TALAN TOWERS PROJECT
Brand : KONE
OFFICE TOWER
ELEVATORS
Turnstile
TALAN TOWERS PROJECT
HOTEL TOWER
ELEVATORS
MEP
UPDATE
Mechanical TALAN TOWERS PROJECT
Fire Alarm
Public Address
ICT
Earthling & Lightning protection
Hotel guestroom works
GSM antennas
Power Cables
Security
Electrical TALAN TOWERS PROJECT
Progress
Systems 3 months ago Today
Fire Alarm 50% 70%
Public Address 40% 55%
ICT 30% 60%
Earthing & Lightning 80% 100%
protection
Hotel guestroom works 10% 40%
GSM antennas 0% 10%
Power Cables 60% 90%
Security 30% 60%
In last 3 months:
90% of ELV equipment is delivered to the site.
GSM design issue has been solved with interior designers in order to location of access panels.
Telecommunication lines are activated in Office Tower Server room.
AV design issues are solved for Hotel.
Electrical TALAN TOWERS PROJECT
LIGHTING - 20% COMPLETED ELECTRICAL POWER AND ELV ROOMS - %80 COMPLETED
TALAN TOWERS PROJECT
TALAN TOWERS
MILESTONE DATES
Hotel Tower PM
Mehmet Kilic