CONSTRUCTION PROGRESS SNAPSHOTS

Project: 1x12 MW CDQ Power Plant, TATA Steel, Kalinganagar

April, 11, 2016


1
1x12 MW CDQ Power Plant, TATA Steel, Kalinganagar (BU: PG)

Overview CDQ Power Plant

2
1x12 MW CDQ Power Plant, TATA Steel, Kalinganagar (BU: PG)

TG Deck Slab
BHEL inspection completed on 09.04.2016. Ready for Concreting

3
1x12 MW CDQ Power Plant, TATA Steel, Kalinganagar (BU: PG)

TG Building B-C bay Structural works

4
1x12 MW CDQ Power Plant, TATA Steel, Kalinganagar (BU: PG)

TG Building B-C bay Switchgear Room (El. +3.5 m)


Deck Sheet Laying & Fixing nearing completion

5
1x12 MW CDQ Power Plant, TATA Steel, Kalinganagar (BU: PG)

TG Building B-C bay Control Room (El. +8.5 m)


Floor Beam erection completed. Final welding in progress.
Structural Fabrication drawings for Floor Beams above El. +8.5 not available

6
1x12 MW CDQ Power Plant, TATA Steel, Kalinganagar (BU: PG)

Generator Transformer Foundation


Rubble Soling work in progress

7
1x12 MW CDQ Power Plant, TATA Steel, Kalinganagar (BU: PG)

Air Washer Room Foundations


*On Hold from 18.02.2016. Re-approved drawings awaited

8
1x12 MW CDQ Power Plant, TATA Steel, Kalinganagar (BU: PG)

33 KV Breaker Room Foundation


Missing details in Breaker Room RC detail drawing awaited

9
CDQ Power Plant, TATA Steel, Kalinganagar

5S PRACTICES
Proper storage of IBR pipes Proper storage of equipments

10
1x12 MW CDQ Power Plant, TATA Steel, Kalinganagar (BU: PG)

5S PRACTICES
Scaffolding Material Storage Yard TMT Bar Storage yard

Scrap Yard (Steel)

11
1x12 MW CDQ Power Plant, TATA Steel, Kalinganagar (BU: PG)

Thank you

12