SUB SYSTEMS OF CIRCULATING FLUIDIZED BED BOILER

Instrument DCS Control Power


Air (2) (3) (4)

Water Fire Safety


(17) System
(5)

LP Steam Slag
(16) (6)

Coal
(15) BOILER Ash
(7)

Diesel De-sox
(14) (8)

Cooling
Lime Stone
Water (9)
& Ash (13)

Drainage Blow down


(12) Flash Vessel
(10)
HP Steam
(11)
BOILER

Mechanical Completion
Hydro test of the Boiler carried out.
Steam drum level glass gauges are installed
Boil out Process completed
PSV Testing done
Registration / legislation process completed.
Refractory dry out /Baking process completed
Primary, secondary & ID fan testing done
Power for Fans available
Interlocking, loop testing and trip testing checked.
Chemical dosing system complete.
Analyzers are in working condition
Fire suppression system on coal bunker is installed operative.
Screw feeders are ok, and power supply is available
Air supply to loop seals is available
Back filters are installed
Instrument air for all instruments available.
INSTRUMENT AIR

Power for IA Compressors is available


Instrument Air Compressors are tested by performance test.
All instrument air line are blown.
Instrument air Dryers are available
Desiccant available in air dryers
Air Receiver vessels are available and installed.
DCS / INSTRUMENT CONTROL

Control panels, Control room for HMI/DCS are available


HMI / DCS is available for Boiler
All loop testing of instrument & trips tested.
POWER

Transformer at CFB tested and ready to take in service


All electrical cables to drives connected
1500 KW load is available from works
All MCC panels are ready
FIRE SAFETY SYSTEM

Fire ring main installed as per drawing.


Fire extinguisher, fire hydrants and fire monitor installed.
Fire water pumps ( jockey, electric and diesel pump) tested and ready to operate.
Fire water pool constructed and clean.
Make up water available.
SLAG

Slag cooler installed


Power for slag cooler and conveyer is available
Slag conveyor and slag storage storage are available
Instrument air is available
Slag disposal system is available.
ASH

Bag filter fitted


Ash removal system is available
Ash silo, store house pump and ash hoppers are ready
Instrument air for ash conveying is available
Ash disposal system is identified.
HIGH PRESSURE STEAM

HP steam from boiler till boiler works is completed. (Isolation valves on steam trap lines
fitted)
HP steam line blowing is completed
Auto Vent valve fitted on HP steam Common Header at CFB area
LIME STONE STORAGE AND CONVEYING

Lime stone is available


Dust collecting unit are ready
Lime stone bin is installed
Lime stone Conveying system is installed
Store house pump are ok, and instrument air connected
Power supply for lime stone conveying system is available
Dust ID fan is ready
Power supply for Instrument operating valves is available
Interlock testing done.
DIESEL STORAGE AND CONVEYING

Diesel tank, diesel pump are ready and flushed


Diesel system till boiler is ready and flushed
Diesel decanting system is available
Power supply to diesel pump is available
Instrument air is available
Registration / Legislation process is completed
Interlock testing is completed
Burner (igniter, gun) is ready to install.
Cooling air for flame sensor is provided.
COAL CRUSHING,CONVEYING AND STORAGE SYSTEM

Coal is available
Coal yard / coal shed is available
Power supply to Grab crane is available, Grab crane is operative.
Coal feeder, conveyors and one coal crusher is available
Coal bunker is available. Fire suppression system installed on coal bunkers.
Coal conveyor to coal bunker & coal bunker to boiler are available
Power is available to conveyors, crusher, Grab crane
Loader is available
Instrument supply is available
Dust collecting unit are ready
Interlock testing carried out.
Coal feeders to conveyors installed and ready to use.
LOW PRESSURE STEAM

LP line from screw-8 to Deaerator is completed


All traps are in working condition and isolation valves installed.
Steam blowing is carried out as per standards.
PCV on de aerator is ready to take in service.
BOILER FEED WATER SYSTEM

Low lift pumps are ready to operate.


Boiler feed water line from low lift pumps to booster pumps flushed
Feed water line from booster to de aerator flushed
One de aerator ready and cutoff from other one
One boiler feed water pump / feed water line flushed.
Chemical dosing ready
Power supply available to booster pump and BFW pump
Instrument air is available
Cooling water to BFW pump is available
Inter lock testing complete.