CASE STUDY
2 delivery agents; 2 service personnel
Time taken to complete processes-
Booking a slot= 2 minutes
Max time to pick up= 15 hours
Suitable entry time= 5 minutes
Washing time= 20 minutes
Capacity= 15 big, 5 small
Mechanical Stages-
1. 15 minutes rinsing for 20 clothes
2. Stain removal of minimum 5 clothes
Stain removal- demanded by 5% customers
Time for dryer= 10 minutes
Dryer details-
20 large clothes at a time; 3 small clothes= 1 large cloth = 60 small clothes
Drying on a sunny day= 10 minutes
Drying on humid day= 23 minutes
Ironing details
6 minutes- 1 large cloth
5 minutes- 1 small cloth
Delivery process= pick up pick up
10% customers need no pick up
70% customers need only pick up
1 set is 15 big and 5
small clothes
a)Maximum capacity of clothes processed in a day, working for 10 hours=
20(washing)+15(rinsing)+(4*0.05)(stain removal)+10(drying)+10(sunny
day)+{[(6*15)+(5*5)]/2}(ironing)
[ it is divided by 2 because 2 service professional are available]
since to process a set of clothes it takes maximum time for ironing, so one set
can be processed in 57.5 minutes
=151.5 minutes
10000 per month for 260.8 sets so per set it will cost 38.34 rupees.