YEARS
DESCRIPTION UNIT TOTAL
2010 2011 2012 2013 2014
COMMODITY ton 5.520.000 500.000 1.000.000 1.500.000 20.000 2.500.000
WASTE REMOVAL bcm 90.000.000 6.000.000 12.000.000 18.000.000 24.000.000 30.000.000
SR
A. STRIPPING
Land Clearing ha 840 144 174 174 174 174

Top Soil Removal bcm 8.400.000 1.440.000 1.740.000 1.740.000 1.740.000 1.740.000
Hauling Distance m 1.500 1.500 1.500 1.500 1.500 1.500

Overburden Removal 81.600.000 4.560.000 10.260.000 16.260.000 22.260.000 28.260.000


Rippable Material bcm 17% 13.872.000 775.200 1.744.200 2.764.200 3.784.200 4.804.200
UnRipable Material bcm 83% 67.728.000 3.784.800 8.515.800 13.495.800 18.475.800 23.455.800
Hauling distance m 2.000 2.000 2.000 2.000 2.000 2.000
B. WINNING
Pit To ROM ton 5.520.000 500.000 1.000.000 1.500.000 20.000 2.500.000
Haul Distance m 5.000 5.000 5.000 5.000 5.000 5.000

Hitung total cost OB ? Hitung Harga cost per Bcm OB ?


Hitung total cost Coal ? Hitung Harga cost per Ton Coal ?
Case study
Alat-alat yang dapat digunakan :
a. Land Clearing
- D85
b. Top Soil Removal
- D 85, PC 400, PC 750, BMA 40
c. OB Removal
- D 375, D 155, D 85; PC 2000, PC 1250, PC 750; HD 785, HD 465
d. Coal Winning
- PC 300 ( cleaning), PC 750, HD 465, Scania
Case study
Equipment Price
D 375 $ 620.000
PC 2000 $ 1.520.000
Capacity Untuk aktifitas
PC 1250 $ 765.000 peledakan dilakukan
PC 2000 13 m3
oleh subcontractor
PC 300 $ 200.000
PC 1250 6 m3 dengan cost = 0,2$/bcm
PC 400 $ 285.000
PC 300 1.19 m3
PC 750 $ 540.000
PC 400 1.62 m3 Productivity :
HD 465 $ 495.000
PC 750 4 m3 D375 = 550 bcm/hrs
BMA 40 $ 375.000
HD 785 95 ton D155 = 400 bcm/hrs
Scania $ 120.000
HD 465 52 ton D85 = 250 bcm/hrs
D 155 $ 410.000
BMA 40 40 ton
D 85 ESS $ 170.000
Scania 30 ton
HD 785 $776.000
Assumption : Case study
Fuel : Rp.6.000,-
US$ : Rp.9.000,- Assumption :

Usefull = 5 tahun Prodty DZ 85 = 0,2 Ha/hrs

Special Item DZ $1.5 / hrs; EX $2 / hrs Life time EQP = 4500 hrs/year

Operator : $1 / hrs ; Filter 0.5 x kons Oil


engine oil 15,500 (Rp/lt)
Repair Cost : $2 ; Tyre : Life time 4.000
transmission oil 15,500 (Rp/lt)
Tyre BMA 40 $7000;
final drive oil 15,500 (Rp/lt)
Tyre HD $15.000,-
hydraulic control 12,000 (Rp/lt)
Tyre Scania = $ 7000,-
grease 36,450 (Rp/kg)
Resale Value 10%, Annual Rates 14%

Note : DZ = Dozer
EX = Excavator
EQP = Equipment
Sasaran tugas ini adalah :
1. Mampu menentukan asumsi teknis yang tidak disebutkan dalam soal.
2. Mampu melakukan perhitungan produktifitas alat.
3. Mementukan fleet matching & syncronization alat untuk alat loading &
hauling.
4. Mampu Menentukan jam kerja alat dengan asumsi PA = 98% dan UA = 75%.
5. Mampu menentukan jumlah alat.
6. Mampu melakukan perhitungan owning & operating cost
7. Mampu melakukan perhitungan ABC (activity Base Costing)
8. Mampu menentukan hitungan harga aktifitas pengambilan OB dan aktifitas
pengambilan Coal
9. Mampu menentukan harga satuan untuk mengambil 1 ton batubara ($/ton)
dan mengambil 1 bcm overburden ($/bcm)

Untuk tugas ini tidak dilengkapi dengan :


1. Data bor
2. Data litologi batuan
3. Peta area penambangan
Sehingga untuk kondisi actual lokasi penambangan ditentukan sendiri
Dan tidak perlu menyajikan urutan penambangan.
MINE TERMINOLOGY
1. Stripping
2. Mine Rehabilitation :
1. Reclamation
2. Revegetation
3. Mining Mine Operating Cost
4. Mine road Maintenance
5. Coal Hauling
Hauling Cost
6. Hauling road Maintenance
7. Crushing & Washing Plant ---------- Processing Cost
8. Barging
Shipping Cost
9. Shipping
10. Infrastructure -------------------- Infra structure is a part of Capital Cost /
Overhead Cost (tergantung kesepakatan).
11. Administration, office, dan fasilitas pendukung lainnya ----- Overhead cost