Pre-requisite and restriction

1. DB2 LUW version 9.7 FP5 or higher, if target SAP_BASIS release is 740 SP8 or higher and lower than 751.
2. For upgrades to EHP8 for SAP ERP 6.0 the usage of the Maintenance Planner is mandatory.
3. Staging server is required with source system OS, to import source system.
4. Target system will comprise of two tiers Application and Database. Application tier will be on source system OS
whereas SAP HANA DB on Linux Suse.

Source system Target system


SAP ECC 6.0 EHP3 SAP ECC 6.0 EHP8
DB2 database SAP HANA database
AIX OS Linux Suse OS

AIX OS Linux Suse OS


EHP8 upgrade with DMO process at glance

Postprocessing 4 hrs Target system

Downtime 8 hrs Start SAP system based on target DB


Uptime 3 days
Finalize upgrade

Migrate Application data incl. data conversion

Switch database connection

Setup target SAP HANA database

Upgrade Prepare

Source system