Kick Off Meeting - Ipm Plug & Abandon
Kick Off Meeting - Ipm Plug & Abandon
18/07/17_bp
Service Company Introduction
01 Company Profile, experience, equipment
Organisasi IPM
02 Proses, Struktur, Alur Koordinasi
Rencana Kerja
03 Tentative Timeline
Diskusi
04 Question & Answer
18/07/17_bp
Organisasi Integrated Project Management
Proses, Struktur dan Alur Koordinasi
02
PEP - ADARO
IPM PROJECT
LEADER
JAKARTA OFFICE
SECURITY
18/07/17_bp
Organisasi Integrated Project Management
Proses, Struktur dan Alur Koordinasi
WELL SITE
COORDINATOR/
SUPERVISOR COMPANY MAN
SERVICE COMPANY
(DAY/NIGHT)
MULAI
TIDAK
TIDAK
PERBAIKAN SETUJU SETUJU
PERSETUJUAN PERSETUJUAN
18/07/17_bp
Organisasi Integrated Project Management
Fungsi, Proses, Struktur dan Alur Koordinasi
18/07/17_bp
Daftar Service Company Pendukung IPM
List, PIC, Company Profile
04
EQUIPMENT
NO SERVICES SERVICES COMPANY PERSON IN CHARGE PHONE
UNIT/MATERIAL LOCATION
01 SITE PREPARATION PT. LUBRISINDO JAYA GEMILANG BALIKPAPAN, KALTIM RICHARD 081254600022
02 DRILLING RIG 450 HP PT. NANA YAMANO TECHNIK SANGA-SANGA, KALTIM SUSANTO MICHAEL 08126003960
03 VSAT & TELECOMUNICATION PT. PATRA TELEKOMUNIKASI INDONESIA JAKARTA M. RIDWAN 081382354328
07 GENERAL SERVICES PT. TIGA MAS MUSIM JAYA BALIKPAPAN EKO SUTRISNA 081932527324
18/07/17_bp
Rencana Kerja IPM Site Preparation dan Plug & Abandon
General Tentative Timeline
05
Technical M eeting HSE Plan & JM M 1 Mon 24/ Jul/ 17 Mon 24/ Jul/ 17
Pemasukan & Review Dokumen SIKA 4 Tue 25/ Jul/ 17 Fri 28/ Jul/ 17
M obilisasi Peralatan/M aterial/Personil (Umum) 90 Tue 01/ Aug/ 17 Sun 29/ Oct / 17
Technical M eeting Operasi P & A 1 Wed 04/ Oct / 17 Wed 04/ Oct / 17
Tajak P & A (Sumur TT-01 & TT-02) 1 Fri 20/ Oct / 17 Fri 20/ Oct / 17
18/07/17_bp
Rencana Kerja IPM Site Preparation dan Plug & Abandon
Rencana Mobilisasi Unit / Personil Service Company
SITE PREPARATION
Target Waktu
Jul Aug Sep Oct Nov
PROJECT/TASK
Hari Start Finish
Pengukuran Lokasi Dan Finalisasi Lay Out 3 Tue 25/ Jul/ 17 Thu 27/ Jul/ 17
Sosialisasi dengan UPIKA dan Warga Desa 4 Fri 28/ Jul/ 17 Mon 31/ Jul/ 17
M obilisasi Peralatan ke Sumur Pertama 7 Tue 01/ Aug/ 17 Mon 07/ Aug/ 17
RIG 450 HP
Target Waktu
Jul Aug Sep Oct Nov
PROJECT/TASK
Hari Start Finish
Set & Rig Up Rig 5 Tue 10/ Oct / 17 Sat 14/ Oct / 17
Closing Finding Inspeksi M igas 2 Wed 18/ Oct / 17 Thu 19/ Oct / 17
Plug & Abandon Sumur TT-01 7 Sat 21/ Oct / 17 Fri 27/ Oct / 17
18/07/17_bp
Rencana Kerja IPM Drilling dan Plug & Abandon
Rencana Mobilisasi Unit / Personil Service Company
05
M obilisasi Electric Wireline Logging 20 Wed 13/ Sep/ 17 Sun 01/ Oct / 17
Call out Cementing Engineer to Rig Up 7 Wed 13/ Sep/ 17 Sun 01/ Oct / 17
Call out M ud Engineer to Rig Up 7 Wed 13/ Sep/ 17 Sun 01/ Oct / 17
18/07/17_bp
Diskusi
Question & Answer
06
18/07/17_bp
Terima Kasih
18/07/17_bp