KICK OFF MEETING

IPM SITE PREPARATION DAN


PLUG & ABANDON

18/07/17_bp
Service Company Introduction
01 Company Profile, experience, equipment

Organisasi IPM
02 Proses, Struktur, Alur Koordinasi

Rencana Kerja
03 Tentative Timeline

Diskusi
04 Question & Answer

18/07/17_bp
Organisasi Integrated Project Management
Proses, Struktur dan Alur Koordinasi
02
PEP - ADARO

IPM PROJECT
LEADER
JAKARTA OFFICE

24 HOURS SUPPORT HSE MANAGER


SR. DRILLING
ENGINEER
PROJECT
SUPPORT
CIVIL ENGINEER

WELLSITE WELLSITE WELLSITE


CIVIL FIELD
COMPANY MAN SUPERVISOR SUPERVISOR GEOLOGIST
WELL SITE (DAY) (DAY)
SUPERVISOR

LOGISTIC DRILLING RIG CEMENTING CONTRUCTION


HSE COORDINATOR VSAT & TEL
COORDINATOR SERVICES

LOGISTIC MEDICAL PERSONEL ELECTRIC WIRELINE


DRILLING FLUID DRILL BIT
ASSISTANT LOGGING

CLERK GENERAL SERVICES


/DISPATCHER

SECURITY

18/07/17_bp
Organisasi Integrated Project Management
Proses, Struktur dan Alur Koordinasi

WELL SITE
COORDINATOR/
SUPERVISOR COMPANY MAN
SERVICE COMPANY
(DAY/NIGHT)

MULAI

LAPORAN VERIFIKASI VERIFIKASI

TIDAK
TIDAK
PERBAIKAN SETUJU SETUJU

PERSETUJUAN PERSETUJUAN

18/07/17_bp
Organisasi Integrated Project Management
Fungsi, Proses, Struktur dan Alur Koordinasi

IPM Project Leader


Commercial
Responsibility
Process Management
Managing Interfaces Sr. Drilling Engineer
Technical Integrity
Architect :
Conceptional Well
Design
Detail Well Design Wellsite Supervisor
Well Program Service Provider :
Implements Well Program.
Responsible for planning,
coordinating, supervising,
evaluating all rig-site activities

18/07/17_bp
Daftar Service Company Pendukung IPM
List, PIC, Company Profile
04

EQUIPMENT
NO SERVICES SERVICES COMPANY PERSON IN CHARGE PHONE
UNIT/MATERIAL LOCATION

01 SITE PREPARATION PT. LUBRISINDO JAYA GEMILANG BALIKPAPAN, KALTIM RICHARD 081254600022

02 DRILLING RIG 450 HP PT. NANA YAMANO TECHNIK SANGA-SANGA, KALTIM SUSANTO MICHAEL 08126003960

03 VSAT & TELECOMUNICATION PT. PATRA TELEKOMUNIKASI INDONESIA JAKARTA M. RIDWAN 081382354328

04 DRILL BIT PT. MEGA POWERINDO JAKARTA ISKANDAR 08128110706

05 ELECTRIC WIRELINE LOGGING PT. ELNUSA TBK JAMBI FUAD 081380905999

06 DRILLING FLUID PT. HUILE INDONESIA JAKARTA SAID ISKANDAR 0811144137

07 GENERAL SERVICES PT. TIGA MAS MUSIM JAYA BALIKPAPAN EKO SUTRISNA 081932527324

18/07/17_bp
Rencana Kerja IPM Site Preparation dan Plug & Abandon
General Tentative Timeline
05

GENERAL IPM ACTIVITIES


Target Waktu
Jul Aug Sep Oct Nov
PROJECT/TASK
Hari Start Finish
Kick Off M eeting 2 Tue 18/ Jul/ 17 Wed 19/ Jul/ 17

Technical M eeting HSE Plan & JM M 1 Mon 24/ Jul/ 17 Mon 24/ Jul/ 17

Pemasukan & Review Dokumen SIKA 4 Tue 25/ Jul/ 17 Fri 28/ Jul/ 17

Penerbitan Dokumen SIKA 1 Mon 31/ Jul/ 17 Mon 31/ Jul/ 17

M obilisasi Peralatan/M aterial/Personil (Umum) 90 Tue 01/ Aug/ 17 Sun 29/ Oct / 17

Technical M eeting Operasi P & A 1 Wed 04/ Oct / 17 Wed 04/ Oct / 17

Pre Spud M eeting 1 Wed 11/ Oct / 17 Wed 11/ Oct / 17

Tajak P & A (Sumur TT-01 & TT-02) 1 Fri 20/ Oct / 17 Fri 20/ Oct / 17

18/07/17_bp
Rencana Kerja IPM Site Preparation dan Plug & Abandon
Rencana Mobilisasi Unit / Personil Service Company

SITE PREPARATION
Target Waktu
Jul Aug Sep Oct Nov
PROJECT/TASK
Hari Start Finish

Pengukuran Lokasi Dan Finalisasi Lay Out 3 Tue 25/ Jul/ 17 Thu 27/ Jul/ 17

Sosialisasi dengan UPIKA dan Warga Desa 4 Fri 28/ Jul/ 17 Mon 31/ Jul/ 17

M obilisasi Peralatan ke Sumur Pertama 7 Tue 01/ Aug/ 17 Mon 07/ Aug/ 17

Clearing area 14 Tue 08/ Aug/ 17 Mon 21/ Aug/ 17

RIG 450 HP
Target Waktu
Jul Aug Sep Oct Nov
PROJECT/TASK
Hari Start Finish

M obilisasi Rig 450 HP 70 Tue 01/ Aug/ 17 Mon 09/ Oct / 17

Set & Rig Up Rig 5 Tue 10/ Oct / 17 Sat 14/ Oct / 17

Function Test 1 Sun 15/ Oct / 17 Sun 15/ Oct / 17

Inspeksi M igas 2 Mon 16/ Oct / 17 Tue 17/ Oct / 17

Closing Finding Inspeksi M igas 2 Wed 18/ Oct / 17 Thu 19/ Oct / 17

Tajak Sumur TT-01 1 Fri 20/ Oct / 17 Fri 20/ Oct / 17

Plug & Abandon Sumur TT-01 7 Sat 21/ Oct / 17 Fri 27/ Oct / 17

Release Sumur 1 Sat 30/ Dec/ 17 Sat 30/ Dec/ 17

18/07/17_bp
Rencana Kerja IPM Drilling dan Plug & Abandon
Rencana Mobilisasi Unit / Personil Service Company
05

SERVICES COM PANY


Target Waktu
Jul Aug Sep Oct Nov
PROJECT/TASK
Hari Start Finish
Inspeksi Peralatan/Lab/M aterial 1 Fri 21/ Jul/ 17 Mon 31/ Jul/ 17

Inspeksi HSE 1 Fri 21/ Jul/ 17 Mon 31/ Jul/ 17

M obilisasi General Services 7 Wed 04/ Oct / 17 Tue 10/ Oct / 17

M obilisasi VSAT 20 Thu 21/ Sep/ 17 Tue 10/ Oct / 17

M obilisasi Drilling Bit 20 Wed 13/ Sep/ 17 Sun 01/ Oct / 17

M obilisasi M an Power Services 20 Wed 13/ Sep/ 17 Sun 01/ Oct / 17

M obilisasi Cementing 20 Wed 13/ Sep/ 17 Sun 01/ Oct / 17

M obilisasi Drilling Fluid 20 Wed 13/ Sep/ 17 Sun 01/ Oct / 17

M obilisasi Electric Wireline Logging 20 Wed 13/ Sep/ 17 Sun 01/ Oct / 17

Call out Cementing Engineer to Rig Up 7 Wed 13/ Sep/ 17 Sun 01/ Oct / 17

Call out M ud Engineer to Rig Up 7 Wed 13/ Sep/ 17 Sun 01/ Oct / 17

Call out vsat 7 Wed 13/ Sep/ 17 Sun 01/ Oct / 17

18/07/17_bp
Diskusi
Question & Answer
06

18/07/17_bp
Terima Kasih

18/07/17_bp