RETICULATION AND

STORAGE PROJECT
GUIDELINES

AP IR DR ZAINAL ZAKARIA
SECTION DESCRIPTION JUSTIFICATION GUIDELINE
1 Approval Requirements The necessary requirements for LPG Legislation:
for LPG and NG and NG systems as set by the Energy
- Gas Act 1993, Gas Regulation
reticulation system Commission, The Department of
1997, FMD Act 19967, Bomba,
2
Occupational Safety and Health
Local Authority etc
(DOSH), Jabatan Bomba dan
Penyelamat and other appropriate Certificate:
authority body. This shall include brief - PMT , ATI, ATO, PTI, PTO, etc
procedures to obtain approval for the
piping materials (external and internal Form:
pipes), equipments, fittings and -JKKP(BP)1 (Welding of pipe)
pressure vessel
- JKJ 127 (pressure test)

- JG8 (ATI)

- JG9 (ATO), Etc

2 Code of Practices List out the necessary code of Malaysia Standard &
practices involve in the project which International Standard
respect the scope of works.
-Pipeline

- Storage

- Pipe jointing

- Corrosion control, Etc


3 Demand Calculation Calculate the demand requirement to be - Type and number of customer
supplied to the project based on the overall
- Type and number of gas appliances
consumption of the appliances and
equipment installed. Justify your assumption - Identify appliances rating
on appliances and equipment to be used
3 and the rating selected. Specify the - Determine or assume a gas coincident
minimum inlet pressure of the appliances factor
and equipment
4 Route of Pipe Provide a detaild plan layout showing the - Identify the best place for the bulk
piping route within the area and the location tank and perhaps the NG service
of the LPG storage tank or NG service station as well
station. In the route selection, please
- The selection must be considered on
consider the existence of a proposal natural
on safety, easy to excess and nearest
gas lateral line, if applicable
to NG lateral pipeline

- The best route is the shortest in


distance. The final route must be able
to provide safe supply and the most
economic
5 Tank Capacity Determine the required capacity of the LPG - Type of installation : Bulk tank or
storage tanks based on the total demand. manifold
The capacity and number of tanks required
- List out related assumption: LPG
should be determined based on natural
composition, overall coefficient,
evaporation method. The tank should
refilling percentage, peak usage, tank
equipment should equipped with proper
minimum pressure, number of tank,
piping system for remote filling and vapor
etc
withdrawal. All assumptions and references
made must be clearly explained. - Determine capacity in volume and
refilling period
6 Layout Plan of LPG Storage Show on bigger scale layout plan for the - Should include safety distance
Tank or Natural Gas Service tank and bulkhead location, piping layout, (deplection wall, if required), fencing,
Station tank area security protection, tanker sinage, access road, safety
process road and safety distances as equipments, etc
required by MS830. All assumptions and
references make must be clearly explained.
4
7 Technical Specifications of Prepare a technical specification of the - Tank
Storage and piping storage systems and its piping system for
- Tank accessories
from filling point to the first stage regulator.
The specification shall specify the design - Pipe
conditions of the tanks and the piping
system and identify the type, material, - Equipments
manufacturer and rating of the valves and
the gauges to be installed

8 Network Analysis for Pipe Determine the appropriate gas distribution - At least one loop should be
Design pipe size based on the demand and the considered
length of the piping to be installed. You are
- Only one supply source
free to apply the gas flow equation, which
you thing appropriate. Clearly state your - Identify the right equation which
assumption and carryout the network based on the supply pressure
analysis for the distribution system to check
for a balance system. Draw the balance - Determine the flow of every pipe and
network which must indicate the final flow node
direction. The flow rate and the pressure - Determine the pressure level of every
drop each section of the piping system node

- The flow and pressure will be used in


determining the downstream pipe
size
9 Selection of Pipe System Select the pipe material to be used for the - Carbon steel
Materials reticulation system (external and internal
- Polyethylene
piping) and give reasons for your selection..
Name the necessary equipments and fittings, - Copper
which are required to be installed on the
reticulation piping. Describe the jointing - Should clearly stateted the correct
5 requirements and necessary qualification of spesifications of the selected materials
jointers and welders.
- Welding, threading, fusion etc
10 Internal Piping Installation Briefly describe the method of installation for - Conceal
internal piping
- Open

- Above ceiling

- Emergency

- Inspection

11 External Piping Installation Describe the method of installation for external - Trenching
piping with emphasis on pipe trenching, road
- Road crossing
crossing, corrosion protection, pipe route
marker and trace wires. Please consider, for - Utility crossing
both the LPG and NG systems. Explain the sort
of inspection and quality control scheme - Marker
required to ensure pipeline integrity during the
- Trace wire
construction
- Emergency

- Inspection

- Buoyancy control (method and type of


anchor used)

- Corrosion control method (determine the


required anode and types of installation
12 Design and selection of Gas Select the correct size of pressure - Sizing of regulator
Pressure Regulator and regulators and meter to be installed.
- Sizing of meter
Meter as well its installation Describe the method of installation.
methods - Joule Thompson effect

- Calibration of meter
6

13 Tank and Pipeline Integrity Describe the method of pressure test - Hydrostatic test
method need to be carried out for tank
- Pneumatic test
and piping. You may required to show
the calculation related to the test. - Purging
Prepare the stress analysis on the tank
- Perform stress analysis as
and pipeline
suggested by the code

14 Project Schedule Plan for the schedule for the project to - List out the detail schedule of the
be undertaken project on Gantt Chart
15 Operation, Maintenance Prepare a brief write up on operation, - Leak survey schedule
and Emergency Procedures maintenance and emergency procedures
- Emergency procedure
which give emphasis on smooth running
of the system, at the same time provide - Leak
adequate safety customer and public at
- Fire
large
- Method of Statement

- Job Safety Analysis