RAILWAY WORK STATUS

ACTIVITIES DUE DATE

Step 1 Engagement of railway consultant NOV 2017


- Notice to Proceed
Step 2 Contract award DEC 2017

Step 3 Data collection and site survey DEC 2017

Step 4 Completion of all application documents DEC 2017

Step 5 Submission of permit application to railway DEC 2017


authority (DG of Railways)
Step 6 Tentative date to get approval from DG of JAN 2018
Railways
RAILWAY WORK STATUS

ACTIVITIES DUE DATE

Step 7.1 Start of Construction JAN 2018

Step 7.2 Piling Work Start FEB 2018

Step 7.3 Slab Structure Start FEB 2018

Step 8 Finish of Construction MAR 2018