BhoomiPark (SolarEdge)
BhoomiPark (SolarEdge)
for
Solar Inverters
• Safety IEC-62103 (EN50178), IEC-62109, AS3100
• Grid Connection Standards* VDE-AR-N-4105, G59/3, AS-4777,EN 50438 ,
CEI-021,VDE 0126-1-1
• Emissions IEC61000-6-2, IEC61000-6-3 , IEC61000-3-11,
IEC61000-3-12
• RoHS Yes
ABS Renew Power System Design
The Solar Edge advantage
In traditional systems all the panels in a string must have the same
azimuth to have optimum performance.
Generation reduction limited to panel level and the whole string is not
affected due to soiling, bird droppings or vegetation growing across
panels.
5000 kWh
4000 kWh
3000 kWh
2000 kWh
1000 kWh
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Estimated System Performance
• 40 kWp (First year results) Mean values:
• Annual production (DC) : 63,928 kWh Annual Production (DC) : 58,856 kWh
4. DCDB with String level DC Fuse, SPD & Disconnect ABS - SPD Type II Phoenix / Citel
5 ACDB with 3 Phase SPD & Disconnect ABS – 3 Phase SPD Type II Phoenix / Citel
7 AC Cables – 6SQMM 4 Core Armored Copper Cable AC Cables – Polycab / KEI / Munisu
1 2 x 20kW Solar Plant First Year Annual Generation 56,000 kWhr / Year +/- 10%
2 Application for Net Metering & Approvals 2nd Week – 4th Week
3 Supply & Fabrication of Elevated Mounting Structure 3rd Week – 6th Week
4 Supply & Installation of Earthing & Lightning Arrestors 4th Week – 6th Week
5 Supply & Installation Solar Inverters & BOS Items 4th Week – 6th Week
6 Supply & Installation of Solar PV Panels & DC Cabling 6th Week – 7th Week
Excluded