Presentation On Step by Step Procedure For CSS Sites RFR ASSAM Circle
Presentation On Step by Step Procedure For CSS Sites RFR ASSAM Circle
ASR 920 o
Confidential Reliance Jio Infocomm Limited 4
CISCO ROUTER USED AT CSS(Cell Site Switch) SITES – 920(I)
Feed A Feed B
DC Power interfaces(Dual)
5
CISCO ROUTER USED AT CSS(Cell Site Switch) SITES – 920(O)
• ASR 920-O (Outdoor) [ASR-920-10SZ-PD]—This sub-family is designed for deployment outdoors in an environment protected from
rain and direct sunlight and provides cost optimized, and extended temperature range for business, residential, and mobile access
services
Feed A
Feed B
DC Power interfaces(Dual)
PORT NO 0,1 & 2, RESERVED FOR SMPS 10G PORTS(PORT 10 & 11)
1G PORTS(10 NOS PORTS , 0 -9) FOR 1G FOR 1 G CONNECTIVITY(use this ports
& ACCESS CONTROL CONNECTIVITY CONNECTIVITY USB PORT FOR PEN DRIVE are for uplink & down link connectivity)
CONNECTIVITY
Feed A
Feed B
1) Cage Nuts.
2) Heat Sleeves
3) Heat Gun
4) Lugs
Ring Lug Bottle Lug Pin Lug Fork Lug
5) Cable Ties
Reliance Jio Infocomm Limited 10
Material Required for RFR :
8) Multi Meter
9) Crimping Tool.
Confidential Reliance Jio Infocomm Limited 11
INSTALLATION PROCEDURE :
Router should be installed below 1U(3 holes) gap from E-node B and also there should be 1U gap between the router and
the equipment below the router (Please follow NDD)
ROUTER END :
1) Putty
4) Team Viewer
920 o router
12) Copy the IOS file from pen drive using the following command.
i) COPY USB0:asr920-universalk9_npe.V155_1_s2_SR635680903_6.bin FLASH:
ii) Press enter. The printout will appear as per the below snap.
The following printout will appear as the NIP gets copied and the hostname will appear instead of “router#”