Technical Report and Estimate

You might also like

Download as pptx, pdf, or txt
Download as pptx, pdf, or txt
You are on page 1of 7

Presented by:

1. Adduchan Thorik Mahmudi


2. Akhmad Misbakhudin
3. Febby Riantasari Safitri
4. Kinantan Hardi
First Floor Second Floor Basement
 Wall -> Totally unplastered.
Plaster with mortar at ratio
1 cement : 5 sand.
Clading, primary coat, sand/glass
paper.
 Floor slab -> There’s no floor slab yet.
Place the formwork
then put the steel bar and pour
the concrete at ratio 1
cement : 2 sand : 3 gravel.
 Door and window-frames ->
Incompleted. Bunch the wooden frame
of the door and the window.
 Ceiling -> No ceiling yet. Do the
roofing. Set plywood
for ceiling. Install the electricity.
Texture with
emultion paint.