Download as pptx, pdf, or txt
Download as pptx, pdf, or txt
You are on page 1of 21

Copyright © 2014 by McGraw Hill Education (India) Private Limited. All rights reserved.

A project is made up of a sequence of activities that


form a network representing a project.

The path taking longest time through this network of


activities is called the “critical path.”

The critical path provides a wide range of scheduling


information useful in managing a project.

Critical path method (CPM) helps to identify the


critical path(s) in the project networks.

4–1
Copyright © 2014 by McGraw Hill Education (India) Private Limited. All rights reserved.
Identify each activity to be done
and estimate how long it will take.

Determine the required sequence


and construct a network diagram.

Determine the critical path.

Determine the early start/finish


and late start/finish schedule.

4–2
A(21)
C(7)

B(5)
D(2)
F(8)

E(5)
G(2)

4–3

Copyright © 2014 by McGraw Hill Education (India) Private Limited. All rights reserved.
Copyright © 2014 by McGraw Hill Education (India) Private Limited. All rights reserved.
Critical 21 28 28 36
Path 1:
ACFG C(7) F(8)

21 28 28 36
0 21 36 38

A(21) G(2)
0 21 36 38
21 26 26 28 28 33

Critical B(5) D(2) E(5)


Path 2:
ABDFG 21 26 26 28 31 36

Excel: Critical
For the Excel template visit Paths
www.mhhe.com/sie-chase14e
4–4
Copyright © 2014 by McGraw Hill Education (India) Private Limited. All rights reserved.
• When activity times vary, a single time
estimate may not be reliable.
– Instead, estimate three values
 Minimum
 Maximum
 Most likely
• This allows calculation of a probability
estimate of completion time.
• This is the distinguishing characteristic of the
PERT method.
4–5
Copyright © 2014 by McGraw Hill Education (India) Private Limited. All rights reserved.
𝑎 = 𝑚𝑖𝑛𝑖𝑚𝑢𝑚
𝐸𝑇
𝑏 = 𝑚𝑎𝑥𝑖𝑚𝑢𝑚
𝑚 = 𝑚𝑜𝑠𝑡 𝑙𝑖𝑘𝑒𝑙𝑦 𝑎 + 4𝑚 + 𝑏
=
𝐸𝑇 = 𝑒𝑥𝑝𝑒𝑐𝑡𝑒𝑑 𝑡𝑖𝑚𝑒 6
𝜎 2 = 𝑣𝑎𝑟𝑖𝑎𝑛𝑐𝑒 𝑏 −𝑎 2
𝜎2 =
6

Excel: PERT
Calculations
For the Excel template visit
www.mhhe.com/sie-chase14e
4–6
4–7

Copyright © 2014 by McGraw Hill Education (India) Private Limited. All rights reserved.
0
0

A(21)

21
21

21
21
21

21

B(5)
C(7)

26
26
28
28

26
26

D(2)

28
28

31
28
28
28

E(5)
F(8)

36
36
36

33
36
36

G(2)

38
38

4–8

Copyright © 2014 by McGraw Hill Education (India) Private Limited. All rights reserved.
• Probability of finishing in 35 weeks (or less)

4–9

Copyright © 2014 by McGraw Hill Education (India) Private Limited. All rights reserved.
in 35

less) is
weeks (or

about 19%
• Probability
of finishing

Copyright © 2014 by McGraw Hill Education (India) Private Limited. All rights reserved.
4–10
F
E
C
B
A

G
D

H
Activity
a

1
3
1
2
4
1
2

2
8
2
2
6
5
5

4
m

3
9
2
9
9
8

5
b

10
-
-

B
A
A

F,G
C, E
C, D
Immediate predecessor

Copyright © 2014 by McGraw Hill Education (India) Private Limited. All rights reserved.
4–11
Copyright © 2014 by McGraw Hill Education (India) Private Limited. All rights reserved.
• Calculate the expected time and
variance for each activity.
• Draw the critical path diagram. Show
the early start, early finish times and
late start, late finish times
• Show the critical path.
• What is the probability that the project
can be completed in 19 weeks?

4–12
Copyright © 2014 by McGraw Hill Education (India) Private Limited. All rights reserved.
Activity Expected Time Activity Variance

• A 5.00 1
• B 5.00 1 7/9
• C 6.17 25/36
• D 2.00 0
• E 3.00 1 7/9
• F 3.83 1/4
• G 7.50 1 1/3
• H 2.00 1/9

4–13
Copyright © 2014 by McGraw Hill Education (India) Private Limited. All rights reserved.
4–14
Using tables: there is 17 percent chance of completing the project by that date

Copyright © 2014 by McGraw Hill Education (India) Private Limited. All rights reserved.
4–15
Copyright © 2014 by McGraw Hill Education (India) Private Limited. All rights reserved.
• A time-cost model extends the CPM
model to consider the trade-off between
time required to complete an activity
and total project cost.
– Considers direct activity costs, indirect costs
of project, and activity completion times

• It is often referred to as “crashing” the


project to reduce overall duration.

4–16
Copyright © 2014 by McGraw Hill Education (India) Private Limited. All rights reserved.
Prepare a CPM-type network diagram.

Determine the cost per unit of time to


expedite each activity.

Compute the critical path.

Shorten the critical path at the point where


costs are lowest.

Plot project, indirect, and total cost curves


to find the minimum-cost schedule.

4–17
For the Excel template visit
www.mhhe.com/sie-chase14e
Crashing
Excel: Project

Copyright © 2014 by McGraw Hill Education (India) Private Limited. All rights reserved.
4–18
Copyright © 2014 by McGraw Hill Education (India) Private Limited. All rights reserved.
Project has reached
minimum duration

Activity D cannot be
reduced any further
at this point
Activity A cannot be
reduced any further
at this point

4–19
4–20
4–21

You might also like