Professional Documents
Culture Documents
Esor Interim Results Presentation 25 Oct 2017 WVZ Comp (2) - MM
Esor Interim Results Presentation 25 Oct 2017 WVZ Comp (2) - MM
Esor Interim Results Presentation 25 Oct 2017 WVZ Comp (2) - MM
Welcome
Agenda
Financial
Overview Salient features
overview
Capex Conclusion
Khutala - Mpumalanga
Overview
Overview
Status of Northern
Profitability and Western Gearing
Aqueducts
Geographical
Unresolved claims Order book
diversification
Delayed awards
o 2D Steelpoort
o Clanwilliam dam
o Weza dam
o Diepsloot
o P700 road upgrade
o Fleurhof pipeline
Community impact
o Active on 102 sites
o RSA with 86 sites
• Community impacted on
6 sites
Vuwani
• Total of 198 employees
impacted and 4 500 hours
Revenue impact of R220 million
State of the nation
Salient features
Salient features
Financial overview
Statement of comprehensive income
2017 2016 %
R’000 R’000 Change
Revenue 553 075 666 286 (17,0)
Non-recurring items
5% 7%
95% 93%
Secured borrowings
Long-term 35 678 44 576
Short-term Reduced debt 45 255 57 508
by R21,2m
80 933 102 084
Cash flow graph
20,000
Total Increase Decrease
15,000
10,000
5,000
(2 212)
(2 799)
10 250
(6 261)
195
0
(22 127)
(229)
-5,000
-10,000
17 585
-15,000
-20,000
-25,000
Cash EBITDA Other Acquisition Working Tax paid Interest Cash
balance at cash items secured of fixed Capital balance at
1 March borrowings assets 31 August
2017 advanced / 2017
(repaid)
Northern
Black Mac-Aqueduct
Western -Cape
KZN
Operational overview
Group structure
• Body copy
Non-government 7% 14%
Contract award
Initial May 2011
Contractual completion December 2013
Value at award R311 million
Duration 31 months
Modification to December 2017
Contract award
Phase 1 November 2013
Phase 3 July 2014
Contractual completion September 2015
Value at award R240 million
Duration 22 / 48 months
Actual completion December 2017
• What happened now
– Completion a further 8 months late
– Quality issues related to welds
– Ovalities and bedding sand
– Repaired all weld deficiencies
– Client concessions on 800m not granted
• Where to now
– Programme to complete Dec 2017
– Testing in 3 sectors
Umgeni valley – Northern – Onerous contract
Aqueduct – Insurance claim progress
Western Aqueduct
Contract award
Phase 2 October 2013
Tshelimnyama July 2014
Contractual completion September 2016
Value at award R440 million
Duration 36 / 12 months
Actual completion December 2017/March
2018
• Status
– Completion delayed to March 2018,
17 months late
– Business Forum and community delays
– Violent environment
– Services relocation delays
– Testing 4 sectors
Western Aqueduct
West Coast
Contract award
CCTV inspection 2015
Lining November 2016
Contractual completion November 2017
Value at award R30 million
Duration 12 months
Contract award
Award date February 2017
Award value E554 million
Contractual completion December 2019
Duration 30 months
Joint Venture 50%
Lusip 2 – Canal
Developments
Diepsloot - Gauteng
Developments
2017 2016
R’000 R’000
Revenue 479 2 781
Number of employees 3 3
Government - -
Khayelitsha
• Land ownership
Phase 1 • Value chain opportunities
Private Sale or Subsidy Units –
ESOR/KHousing Joint Venture • CSI initiatives include:
(368 Units / SP = R450,000
• Local developer initiative
• Employment opportunities
• Social housing component
Stormwater - Orchards • Secured exit strategy
Reservoir - Jozini
Strategy
Strategy
• Body copy
Material issues
26% 31%
69%
74%
Conclusion
Summary
Done
o Secured order book and pending awards
in excess of R3,0 billion
o Reduced debt by a further R21 million to
14,5% debt/equity
o Continued progress on claims
settlements
o Operating model finalised
o Increased value chain
Strategy
o Focus on delivery
o Developments still focus area
o Geared for growth
o Targeting selected African countries
Forward-looking statements
Forward-looking statements
This presentation contains forward-looking statements that,
unless otherwise indicated, reflect the company’s
expectations as at 31 August 2017. Actual results may differ
materially from the company’s expectations if known and
unknown risks or uncertainties affect its business or if
estimates or assumptions prove inaccurate. The company
cannot guarantee that any forward-looking statement will
materialise and, accordingly, readers are cautioned not to
place undue reliance on these forward-looking statements.
The company disclaims any intention and assumes no
obligation to update or revise any forward-looking statement
even if new information becomes available as a result of
future events or for any other reason.
Contact details
Esor Limited
30 Activia Road PO Box 6478
Activia Park Dunswart
Germiston 1508
1401 South Africa