Major Projects Commissioned in 2012-13
3
Major Projects of Phase-I Expansion
To be commissioned in 2013-14
Comm. Date
Sl Major Facilities Likely Comm. Date
As per contract
New Cold Rolling Mill-III
1 Dec’10 Dec’13
(Integrated Commissioning)
SMS II Modernisation
2 Apr’10 Dec’13
Hot Metal Desulphurisation unit
CH-3 : Jul’13
CH -5 : Nov’13
Cast House Slag Granulation
3 Oct’12 CH -4 : Dec’13
System for BF-1,2&3
CH -2 & CH -1 linked
with BF-1 C/R
4
Major Projects of Phase-I Expansion
To be commissioned in 2013-14
Comm. Date
Sl Major Facilities Likely Comm. Date
As per contract
Dec’13
(Subject to
4 Revamping of Sinter Band No.-1 Dec’12
availability of S/D of
Band-1)
Jan’14
Up gradation of existing HSM
5 Jan’14 (Subject to availability
roughing group
of shutdown)
5
Summary of Phase-I Expansion of BSL
Rs in Crs.
6
CRM-III
7
NEW CRM-III
Specific Area Time Frame
8
8
PL-Laser welding
9
PL- Bridle roll no-5
10
TCM-Pulpit with roll changing car
11
SPM- Stand mill housing with walking beam no-2
12
BAF-Furnace with base
13
NEW CRM-III
Ordered Cost/ Scheduled Likely Completion
Sl Pkgs Expend. Comm.
(Rs. Cr)
CPL-2: Mar’12
Coil Packaging
1 18.98/ 18.62 Jan’10 CPL-1: Jun’12
Lines
(Commissioned)
Acid Regeneration 60.03/ 57.29 Dec’09 To be commissioned with
2 PLTCM
Plant
3 Skin Pass Mill 107.23/ 95.17 Jul’10 Jul’13
Initial Delay:
Delay in ordering of civil & structural packages.
Segregation of civil and structural packages has caused delay due to
lack of co-ordination.
Delay in ordering of utility Pkgs like water supply, effluent treatment,
Compressed air (re-tendered) & Hydrogen generation and related
technological packages like HRCC, tension levelling & RGBS. There
was no order placement between 2008 to 2010.
Non sequential ordering of Pkgs i.e, ARP, CPL were ordered in the
beginning, whereas Tension levelling and RGBS & Utilities were
ordered late. Due to the absence of the load data progress of Civil & Strl
job got delayed related to cranes & other technological pkgs.
Civil work was further delayed on account of delayed design & engg. of
sublevel jobs related to transfer car, connectivity of HT/LT cable to
MSDS-9, foundation of coil conveyor.
16
Major Hurdles & Reasons for delay- CRM III
17
Major Hurdles & Reasons for delay- CRM III
18
Preparations for Integrated Trial of CRM III
20
CRM-I
Specific Area Time Frame
Conversion of Sulphuric Acid Jan’14
Pickling to HCL PL-1 of CRM-I
21
Hot Rolling Mill
22
HSM K-Bldg
23
HSM-E Bldg
24
HSM- Extractor Bldg of RHF
25
Hot Strip Mill
Specific Area Time Frame
Roughing Mill Upgradation Jan’14
27
Blast Furnace
28
CHSGP of CH-6, BF-3
29
CHSGP of CH-6, BF-3
31
CH3 Pump cellar
32
CHSGP for BF-1,2&3
Specific Area Time Frame
33
CHSGP for BF-1,2&3
Ordered Scheduled Likely Status
Cost/ Comm. Completion
Sl Pkgs
Expend. , Date
Rs. Crs.
1 Cast House 207.78/ Oct’12 CH-3 : Jul’13 CH-6 –Production started
Slag 128.17 CH -5 : Nov’13 from 15.10.12.
Granulation CH -4 : Dec’13 CH-3 – T/run of individual
System for BF- eqpt. in progress. Conv.
1,2&3 (6 units) CH-1&2: gallery eqpt. under erection.
(Dependent on CH-5 and CH-2: Erection of
BF-1 C/R) utility pipe line completed.
Modified drg. of Conv. Gallery
Disposal System under approval by CET.
(Pkg-3)- Dec’14* CH-1: Ercn of RC conveyor &
Utility pipelines in progress.
CH-4: Ercn of Chimney
completed.
*Separate route from JH-25 to
JH-27 finalised with CET
Mecon & BF. Deviation
quantity being worked out by
34 the party & CET.
CHSGP for BF-1,2&3
35
SMS-II
36
SMS-II
Specific Area Time Frame
Integrated Commissioning of HMDS Unit Dec’13
37
HMDS Bldg
38
HMDS, combi car Fdn
39
HMDS, Pit 1 bolting
40
HMDS- ESP with ID Fan
41
SMS-II-HMDS Pkgs
Sl Pkgs Cost/ Completion Likely
No Expenditure schedule completion
1 Civil, Structural, piping, Rs. 173 crs 31.08.2010 Dec’13
Dismantling and Re- Rs. 110.93 Crs
Routing Works.
2 Power Distribution Rs 18.00 Crs 30.09.2009 May’13
Rs 15.92 Crs
3 Electrics for extension of Rs 0.26 Crs 15.12.2011 Dec’13
trolley line system in Nil
Desulphurisation building
4 4 nos. of Nitrogen Vessel Rs 5.03 Crs 22-02-09 Aug’13
Rs 3.75 Crs
5 Building extn of CCD Rs 5.53 Crs 14-04-13 Mar’14
Rs 0.553 Crs
6 Electrics For Augmentaion of Rs 2.7 Crs 05.05.2011 Aug’13
hot Metal Supply Rs 2.13 Crore
7 Ladle, ladle stand and Rs 27.84 Crs 30.11.2009 Jul’13
transfer car Rs. 21.60 Crs
8 Ladle Drier & Cooler for Rs 2.14 Crs 05.02.2011 Dec’13
42 SMS-II Rs 0.214 Crs
SMS-II-HMDS Pkgs
Sl Pkgs Cost/ Completion Likely
No Expenditure schedule completion
9 Hot Metal Desulphurization Euro 16,96,979 15.04.2010 Dec’13
+ Rs 51.20 Crs
Euro 13,13,212 +
Rs 45.53 Crs
10 08 nos. Torpedo ladle car for USD 47,04,800+ 31.08.2010 Sep’13
augmentation of hot metal Rs 21.27 Crs.
supply USD 36,05,987 +
Rs 4.26 Crs
(22.41 Crs)
11 Double Girder & Four Girder Rs 75.00 Crs 28.02.2010 Dec’13
EOT Cranes. Rs. 61.43 Crs
12 Double Girder and Under Slung Rs 25.00 Crs 02.02.2010 Dec’13
Cranes for SMS-II & CCS. Rs. 21.13 Crs
13 Slag Pot Car Rs 0.79 Crs 25-07-11 Sep’13
Nil
14 Torpedo ladle heating drying Rs 2.63 Crs 30.06.2009 Aug’13
and cooling system Rs 2.04 Crs
43
Major Hurdles & Reasons for delay- SMS II
Total failure of consultant causing increase in Civil & Strl work by 75%.
Unexpected diversion of railway tracks- 4 times for site clearance.
Strengthening of Rly track going to SSD for site clearance of new
Torpedo bay.
Diversion of 8 nos. HT cables which were fauling with the foundation of
new torpedo bay.
Non- availability of CR-140 Rail (for 450MT Crane) in India.
Diversion of Underground drainage pipeline
Diversion of gas pipeline
Construction of -18M pits at a distance of only 3M from the Rly track
carrying hot metal ladle.
Construction of another pits -18M at a distance of only 5M from existing
SMS-II auxiliaries bldg.
Shifting of 4 nos. of Nitrogen vessels.
Dismantling & reconstruction of Faecal pump house.
An existing cable tunnel passing through HMDS area was encountered at
shallow depth which necessitated the use of pile foundations. 44
44
Raw Material Handling
System in RMHP
45
RMHS & Sinter Plant
Ordered Schedl./ Status
Cost/ Likely
Sl Pkgs
Expend. Comm.
(Rs. Cr)
75.16/ Dec’12/ • Dismantling of duct and
7.88 Dec’13 Strs of partial cooling
(dependent zone completed.
on the • Fabn Drgs for wind box
availability released. Material
Revamping of Sinter of S/D) procured & Fabn work in
1
Band No.-1 progress.
• 1st lot of Imported eqpt.
expected to reach Kolkata
by 30-04-13.
• 2nd lot of Imported eqpt.
dispatch from Russia.
46
RMHS & Sinter Plant
Ordered Cost/ Schedl./ Status
Sl Pkgs Expend. Likely
(Rs. Cr) Comm.
Raw Material 107.85/ Jan’14/ • Civil & Strl work in Area
Handling system 28.58 Jan’14 Repair Shop & electrical sub-
store completed.
• Controlled blasting in
Wagon tippler-5 area (new)
in progress. Rock breaking
upto -14M out of -18M level
completed.
2
• One side RCC wall
completed from -12M to
-6M level.
• Strl Ercn in JNA1 in
progress.
• Civil work for Trestle of
conveyor P1C1 & JNA8A
under progress.
47
CO&BPP
48
CO&BPP
Specific Area Time Frame
Ammonium Sulphate Plant Jul’14
49
Pkgs Under Tendering
50
Upcoming Projects
SN Pkg. Name Budget NIT TOD Status
& Pkg No. Cr.
1. Recovery BOO 15-09-12 30-10-12 Against EOI, response of 14 bidders
type stamp 30-11-12 received on 24-04-12.
charged 01-02-13 Pre Bid meeting held on
08&09.11.12. 8 bidders participated.
battery 12-02-13
Single offer recieved upto 14-03-13.
22-02-13 ILFS New Delhi sought extension by
14-03-13 6 weeks.
Case referred to high level
committee for appropriate decision.
High level committee recommended
for dropping the idea of getting the
stamp charge battery on BOO basis
due to single offer from bidder.
However CET has been asked to
compare the Stamp charge battery
Vs 7MT Tall conventional battery
option so that BSL can move forward
for own battery.
51
51
Upcoming Projects
52
52
Upcoming Projects
53
53
Upcoming Projects
S Pkg. Name & Proposal Status
N Pkg No.
5 Modn & FR for Stage-I submitted by PAG meeting held on 20-
03-13. Reply to the PAG
Upgradation CET. Under study. queries sent to CO on 05-
of SMS-I Stage I: 1.306 MT (1*130 BOF, 1 04-13.
slab caster, 1 LF & Gas holder) Additional PAG queries
Est. LCNC Rs 1365 Crs received from Corporate
Benefit: Ingot casting will be Project and were replied.
stopped. Waiting for Board Sub
Net increase in crude steel Committee meeting.
production by 4 lakhs per ton.
Stage-II: 1.85 MT, (2*130T DS, 2*
130 BOF , 1 Thin slab caster, 2 LF
& 1 RHOB (Overall Crude Steel
capacity of BSL will be 6.5 MT by
2017-18)
54
54
Upcoming Projects
55
55
SMS-II-HMDS Pkgs
HMDS- Present Status
Fabrication & Erection of Building Strs of HMDS & Silos (490/519 MT) Completed.
Erection of Technological Structurs of ESP (819/1370 MT) Completed.
Erection of Equipment (250/796 MT) Completed.
Erecn of plate work in HMDS bldg (Environmental enclosure & Hood) in progress.
Front Not available: a) Old Steel Ladles for Lip modification work, b) Combi Car
Tracks, c) Duct supporting trestle foundations, d) Dust Conveying System, e)
Hydraulic, PLC and Computer rooms etc.
BALANCE WORK: Equipment erection of HMDS Stations, 2 nos. of Combi Car,
duct and duct supporting trestle, Dust Conveying System, laying of LT and Control
cables, erection of instmn and automation eqpts etc, PRS for Nitrogen, Insulation
of ESP.
HELP REQUIRED: 4 nos. of HM Ladles are to be handed over to M/s TPL for Lip-
Modification work, 4 nos. of Take-Over Points (TOP) are to handed over to M/s
TPL for tapping of Utility.
Services from existing network of BSL, which are dependent of Shutdowns.
a) Compressed air, b) Nitrogen, c) Oxygen and d) Industrial cooling water