Network analysis techniques like PERT and CPM are used to schedule complex projects. PERT is suitable for uncertain projects like R&D, using three time estimates per activity. CPM identifies the critical path of minimum time activities. Both techniques break projects into activities with dependencies, identify slack, and allow resource scheduling to minimize time/cost. Updating the critical path ensures projects meet completion goals.
Kdahfaiodhfoiahsdakjsiofadhi Ahdfuiadhf Huih Diuchau Iohaudgcoiua Dcgauiogdciuagdfu Agdfui Adguiofagiushello The No Manes. Matter What We Need What We Have Desired
Network analysis techniques like PERT and CPM are used to schedule complex projects. PERT is suitable for uncertain projects like R&D, using three time estimates per activity. CPM identifies the critical path of minimum time activities. Both techniques break projects into activities with dependencies, identify slack, and allow resource scheduling to minimize time/cost. Updating the critical path ensures projects meet completion goals.
Network analysis techniques like PERT and CPM are used to schedule complex projects. PERT is suitable for uncertain projects like R&D, using three time estimates per activity. CPM identifies the critical path of minimum time activities. Both techniques break projects into activities with dependencies, identify slack, and allow resource scheduling to minimize time/cost. Updating the critical path ensures projects meet completion goals.
Network analysis techniques like PERT and CPM are used to schedule complex projects. PERT is suitable for uncertain projects like R&D, using three time estimates per activity. CPM identifies the critical path of minimum time activities. Both techniques break projects into activities with dependencies, identify slack, and allow resource scheduling to minimize time/cost. Updating the critical path ensures projects meet completion goals.
of problem concerning of minimizing the total time to complete the project or total cost or something like that by enhancing the project’s efficiency. It is useful to analyses the complex situation, designing, planning, coordination, controlling, taking decision. • Networks are composed of events and activities. An event is defined as the starting or ending point for a group of activities and an activity is the work required to proceed from one event or point in time to another. Project implementation involves numerous activities (project components) by employing various resources such as men, materials, machine, money, and time. The activities of a project have inter-relationships arising from physical, technical and other considerations. Network: there are two basic network techniques: PERT and CPM. The common characteristics of these networks are • The project can be broken down into a well- defined set of jobs or activities. • The activities must be performed in a certain sequence which is technologically ordered. • Within a defined sequence, the activities may be started and stopped in an independent manner. • Activity: an activity is a definite task, job, or function to be performed in a project. An activity is represented by an arrow. The head of the arrow marks the completion of the activity and the tail of the arrow marks its beginning. • Event: an event is a specific point in time indicating the beginning or end of one or more activities. It represents a milestone and does not consume time or resources. Certain statistics must be known for PERT analysis. They are Schedule of each activities and also before starting of activities. Time span to complete the project’s activities. Program Evaluation and Review Technique (PERT) • PERT was originally developed to facilitate the planning and scheduling of the Polaris Fleet Ballistic Missile Project of the U.S. government. The project is designed to handle risk and uncertainties. It is suitable for research and development programmes, aerospace projects, and other projects involving new technology. In such project time required for completing various jobs or activities can be highly variable. Hence the orientation of PERT is ‘probabilistic’. • PERT was originally developed as a technique for evaluating established plans and schedules, but its utility is not limited to this. PERT can also be used as a planning and scheduling techniques. It is also called multiple time estimates. The PERT technique for estimating elapsed times provides a way of handling some of the uncertainties in estimating the time required to perform many types of activities. • PERT is; use statistical analysis, time span to complete project activities may not fixed. It is analyses by three ladder • Most optimistic time (to): the shortest time to complete the project in general time period or no obstacle to run the project. • Most pessimistic time (tp): long gestation time to complete the project due to the unusual activities. • Most likely time (tm): the appropriate time to complete the project in general condition. The expected time is calculated on the basis of above three points: te = (to+ tp + tm )/6 Critical Path Method (CPM) • CPM is a networking technique for planning and managing projects. It is the sequence of critical activities from project start to project finish that determine the shortest project duration. It is useful to identifies critical activities which require special attention from management, to assists in estimating the minimum total time needed to complete the project, • CPM is one method, which requires a database of cost time relationships to implement. Basically, such known relationship utilizes for individual activities as a basis for reallocating resources among activities. The known cost time relationship is an unrealistic requirement in the case of most complex projects. Since no such database usually exists. However, it is taken to assume simple linear cost time relationships. • The Critical Path is the shortest amount of time we can complete the project. • • We determine Critical Path by making a left- to-right pass across the network and finding the earliest start time each task can start. By the time we get to the end task, we know the earliest time the whole project can be finished. Critical Path: • The maximum time to complete the event and schedule of interrelated activities is called critical path. It takes long time so that it determines the project completion time. • since critical path is longest path through network diagram. Critical Activities or bottleneck activities: • All the activities of critical path are called critical activities. Disturbing on any one activities may affect to complete the project. Slack: • The time to complete the project and the difference between the lengths of activities is called slack. It indicates time day weeks, months, and something like that, which enable to complete the project in time even any one activities be late. This may be positive or negative. Positive slack shows the idle time and resources and negative slack shows the needs of additional time and resources. • Slack is the amount of time a task can be delayed without changing the Critical Path. • A task on the Critical Path has no (zero) slack. • We calculate Slack by making a right-to-left pass across the network and find the latest start date for each task. • Earlier Start Time (Est): The earliest time before initial start to particular activities of a project. • Earlier Finish Time (Eft): The time period of addition of Est and other particular activities. • Latest Finish Time ( Lft): The last time of timely completing project. • Latest Start Time (Lst): The difference between Lft and the time of concerned activities is called Lst. Latest Start Date - Earliest Start Date = Slack • The Critical Path are those tasks where the Early Finish of the Preceding Task is the Same as the Early Start of a Following Task. Importance of Updating Critical Path Data • • It is important to update project schedule information to meet time goals for a project • • The critical path may change as you enter actual start and finish dates • • If you know the project completion date will slip, negotiate with the project sponsor • It was develop to solve the scheduling problems in industrial settings. It is primarily concerned with the trade-off between cost and time. It has been applied mostly to projects that employ a fairly stable technology and are relatively risk free. Hence its orientation is ‘ deterministic’. Advantages • Using CPM for a project promotes advance planning • CPM provides a concise framework for an ongoing review of project progress. • The visual representation of the total project communicates effectively to line personnel, funding agencies, and other interest groups. Limitation of CPM • Project’s activities may not completed within stipulated or predetermine time. • The time is not analyzed according to statistical method. • This method is used to control project’s activities.
Kdahfaiodhfoiahsdakjsiofadhi Ahdfuiadhf Huih Diuchau Iohaudgcoiua Dcgauiogdciuagdfu Agdfui Adguiofagiushello The No Manes. Matter What We Need What We Have Desired