Impounding Simulation chart of Jatigede Reservoir – 12 Jan 2017

Explanation : RESV WATER


1. Achieving intake level of +221.00 : 10-December– 2015 DAY DATE INFORMATION
LEVEL
2. First release of irrigation intake : 11 – December – 2015 1 164.000 AGT-31-2015 River bed elevation +164.00
3. Full opening release from irrigation intake : until 30–Mar–2016
4. Half day operation of irrigation intake gate : 1 April – 25 May 2016 102 221.000 DES-10-2015 Intake and PWW level +221,00
5. Spillway gate operation test : 26 May 2016, 07:00 – 08:00
6. Half day operation of spillway gate : 26 May – 3 June 2016 133 230.000 JAN-10-2016 Minimum Operation Level +230.00
7. Half day operation of irrigation intake gate : 4 June – 26 July 2016
222 247.000 APR-8-2016 Achieving spillway crest
8. 14 hours opr of spillway gate for decreasing to +250 : 27 July – 15 Aug 2016
9. 14 hours operation to maintain reservoir water level at elevation +250,00 , Maximum achievement during
275 252.569 MEI-31-2016
16 Aug – 14 Sept 2016 impounding
10. 15-Sept-2016 spillway gate released discharge start from 07:00 - 17:00, 547 259.985 FEB-27-2017 Full Supply Level +260.00
11. 5-8 Okt-2016 spillway gate released discharge start from 12:00 - 17:00, 12-Jan-17
12. 10-Okt-2016 spillway gate released discharge start from 07:00 - 17:00,
13. 27–Feb–2017 achieving full reservoir
Impounding Stage I IRR Full Open Open close Irr gate /Spill until Dec 2016 Full Resv+260
264 El. +260.00 FSL - 0
25
El.+247.00 Elevasi spillway
50
244 75
100
El. +230.00 MOL 125

Debit Outflow (m3/det)


150
Elevasi MAW

224 El +221.00 IRR


175
200
225
204 250
275
Outflow IRR (m3/sec) 300
Simulasi 1 - Qin last 25
184 325
Simulasi 2 - Qin1997 - ELNino sd akhir 2015
Realisasi sd 12-1-2017 350
Qo Pelimpah 375
164 400
JULI-11-2016
SEP-9-2015

MAR-16-2016
MAR-25-2016

SEP-3-2016
OKT-15-2015

NOV-11-2015
NOV-20-2015
NOV-29-2015

JULI-20-2016
JULI-29-2016

NOV-14-2016
NOV-23-2016
NOV-2-2015

JAN-13-2016
JAN-22-2016
JAN-31-2016

MAR-7-2016

NOV-5-2016

JAN-16-2017
JAN-25-2017

MAR-2-2017
AGT-31-2015

OKT-24-2015

DES-17-2015
DES-26-2015
JAN-4-2016

FEB-27-2016

JUN-14-2016
JUN-23-2016
JULI-2-2016

AGT-16-2016
AGT-25-2016

OKT-18-2016
OKT-27-2016

DES-11-2016
DES-20-2016
DES-29-2016
JAN-7-2017
APR-12-2016
APR-21-2016
APR-30-2016
OKT-6-2015

FEB-3-2017
DES-8-2015

MEI-18-2016
MEI-27-2016
JUN-5-2016

AGT-7-2016

OKT-9-2016

DES-2-2016
SEP-18-2015
SEP-27-2015

FEB-18-2016
FEB-9-2016

APR-3-2016

MEI-9-2016

SEP-12-2016
SEP-21-2016
SEP-30-2016

FEB-12-2017
FEB-21-2017
Periode harian
Skenario Pengaturan MAW Waduk Jatigede
Periode 13 Januari 2017 sd 20 Januari 2017
Skenario Pengaturan MAW Jatigede 13-Januari-2017 sd 20-Januari-2017
Qoutflow rata2 Qoutflow
Tanggal Elv MAW INTAKE IRIGASI SPILLWAY Tinggi Bukaan pintu Jam
(m3/det) (m3/det)

12-Jan-17 251.97 0.00 341.83 2 x 2,2 m 07:00 - 17:00


13-Jan-17 251.92 0.00 341.83 2 x 2,2 m 07:00 - 17:00
14-Jan-17 251.87 0.00 341.83 2 x 2,2 m 07:00 - 17:00
15-Jan-17 251.81 0.00 341.83 2 x 2,2 m 07:00 - 17:00
16-Jan-17 251.72 0.00 341.83 2 x 2,2 m 07:00 - 17:00
17-Jan-17 251.67 0.00 341.83 2 x 2,2 m 07:00 - 17:00
18-Jan-17 251.58 0.00 341.83 2 x 2,2 m 07:00 - 17:00
19-Jan-17 251.54 0.00 341.83 2 x 2,2 m 07:00 - 17:00
20-Jan-17 251.47 0.00 341.83 2 x 2,2 m 07:00 - 17:00
Updated 12–Jan–2017
1. Tahapan Rencana Impounding Waduk Jatigede 2015-2016
1. Tahapan yang direncanakan dalam proses pengisian Waduk Jatigede

TAHAP KEGIATAN
Tahap I : Pelaksanaan Plugging
a) Sejak awal penggenangan, pintu pelimpah ditutup
b) Pintu intake irigasi pada elevasi +221 dibuka, sehingga pada saat muka air waduk
mencapai +222 maka akan terjadi aliran dari intake irigasi ke hilir bendungan.
c) Periode ini merupakan tahapan pelaksanaan pekerjaan penutupan pintu terowong
pengelak
Tahap II : Penurunan MAW pada elevasi +250, Pengamatan Instrumen
a) Muka air waduk diturunkan untuk monitoring kondisi perilaku bendungan
b) Debit outflow melalui intake irigasi maupun pelimpah dikeluarkan sesuai dengan
kebutuhan air irigasi maupun kondisi debit di hilir bendungan
Tahap III : Surveillance
a) Dilakukan surveillance, perbandingan terhadap hasil pembacaan instrumentasi dengan
angka desain
b) Dilakukan kajian terhadap stabilitas bendungan dari data instrument selama monitoring
bendungan
c) Hasil kesimpulan dari surveillance merupakan acuan untuk melaksanakan pengisian pada
tahap selanjutnya
Tahap IV : Pemantauan ke El +260
a) Dilaksanakan setelah surveillance
b) Pintu intake irigasi ditutup pada tanggal akhir Tahap III untuk menaikkan MAW ke FSL
c) Instalasi pendukung untuk pembukaan pintu telah dipersiapkan (CWL +258)
d) Muka air dijaga pada elevasi CWL +258, karena pada saat pelaksanaannya diperkirakan
terjadi pada musim hujan 2017.
e) Pintu pelimpah mulai dibuka setelah tercapai MAW +260. (3 Februari 2017).
f) Prakiraan bukaan pintu pelimpah adalah pintu 2 dan 3 dengan bukaan 25 cm, dipantau
setiap hari dan disesuaikan tiap 10 hari.
g) Dilakukan pencatatan terhadap seluruh kejadian pelaksanaan pengisian waduk untuk
digunakan segabai acuan operasi pada tahap selanjutnya.
2. Realisasi Pelaksanaan Impounding Waduk Jatigede 2015-2016

2. Catatan Realisasi Pelaksanaan Pengisian Waduk Jatigede 2015 – 2016

TAHAP DAN KEGIATAN JAM TANGGAL


Tahap I Menaikkan MAW
1. Mencapai elevasi intake +221.00 : 10-December– 2015
2. Mengalirkan debit intake yang pertama kali : 11 – December – 2015
3. Pintu irigasi dibuka penuh untuk irigasi sampai dengan : 30–Mar–2016
4. Operasi intake 17:00 – 06:00 : 1 April – 25 May 2016
5. Uji coba pintu pelimpah 07:00 – 08:00 : 26-May-16
6. Operasi pelimah 17:00 – 06:00 : 26 May – 3 June 2016
7. Operasi intake 17:00 – 06:00 : 4 June – 26 July 2016
Tahap II Penurunan MAW
8. Penuruan MAW ke elevasi +250 17:00 – 07:00, pelimpah dioperasikan 14 jam 17:00 – 07:00 : 27 July – 15 Aug 2016
9. Mempertahankan MAW pada elevasi +250, pelimpah dioperasikan 14 jam 17:00 – 07:00 : 16 Aug – 14 Sept 2016
10. Mempertahankan MAW pada elevasi +250, operasi melalui pintu radial
07:00 - 17:00 : 15-Sept-2016 sd 4-Okt-2016
pelimpah
Tahap III Surveillance dan Pemantauan
11. Operasi melalui pelimpah 12:00 – 17:00 : 5-Okt-2016 sd 10-Okt-2016
12. Operasi melalui pelimpah 07:00 - 17:00 : 10-Okt-2016 sd sekarang
Tahap IV Pengisian Penuh
13. Mencapai waduk penuh di elevasi +260 : FEB-12-2017

Updated 28–Nov–2016