Definition of a project • A project is a statement or proposal of something to be done. • It may also be defined as is a series of related jobs usually directed toward some major output and requiring a significant period of time to perform.
6/18/2018 Dr. Paul Netalisile Malunda 2
Some examples of projects • Some examples of project include: • building projects, • water projects • and staff-training projects. • Projects are often very large and rely on detailed planning
6/18/2018 Dr. Paul Netalisile Malunda 3
Definition of a program • A program may be made up of interrelated projects completed by several organizations.
6/18/2018 Dr. Paul Netalisile Malunda 4
PERT/CPM • The acronyms PERT stands for Program Evaluation and Review Technique (PERT) • CPM stands for Critical Path Method • These are controlling tools based on dividing a project into separate operations and then charting the order in which the operations should be carried out in a way to save time and optimize the use of resources 6/18/2018 Dr. Paul Netalisile Malunda 5 Difference between PERT and CPM • The primary difference between these two techniques is that PERT is probabilistic where CPM is deterministic. • PERT used three estimates: optimistic, pessimistic, and best of an activity’s required, whereas CPM used just the best estimate. • PERT used an arrow to represent an activity and CPM used a node.
6/18/2018 Dr. Paul Netalisile Malunda 6
Critical path scheduling techniques may be applied to a project with the following characteristics • It must have well-defined tasks whose completion marks the end of the project. • The tasks are independent; they may be started, stopped, and conducted separately within a given sequence. • The tasks are ordered; they must follow each other in a given sequence. 6/18/2018 Dr. Paul Netalisile Malunda 7 The Gantt chart • The Gantt chart is a graphical presentation of a planned course of action and provides a means for comparing actual performance with planned performance.
6/18/2018 Dr. Paul Netalisile Malunda 8
PERT/CPM • Project Evaluation Review Technique (PERT) and Critical Path Method (CPM) are scheduling techniques used to plan, schedule, budget and control the many activities associated with projects.
6/18/2018 Dr. Paul Netalisile Malunda 9
Utilizing PERT/CPM involves breaking the total project down into many different individual activities with identifiable time requirements. Each activity must be accomplished as part of the total work to be done.
6/18/2018 Dr. Paul Netalisile Malunda 10
Net work analysis may be applied to projects with the following characteristics • The project can be split into a number of separate tasks. • The time (duration) required of each task can be estimated. • Certain tasks must precede other while some may carried out simultaneously (in parallel).
6/18/2018 Dr. Paul Netalisile Malunda 11
Steps involved in PERT/CPM project planning • Identify activities required by the project. • Identify the precedence relationships among the activities. • Determine the expected time requirements for each activity.
6/18/2018 Dr. Paul Netalisile Malunda 12
Steps involved in PERT/CPM project planning • Develop a network diagram of activities • Determine the earliest and latest feasible event times. • Identify the critical path
6/18/2018 Dr. Paul Netalisile Malunda 13
Project schedule Activity Time Depend on A-waking up 10 minutes - B-Bathing 30 minutes A C-Praying 10 minutes B D-Making tea 10 minutes A E-Dressing 20 minutes B F-Taking tea 10 minutes D, E, C G-Transport 30 minutes F to office 6/18/2018 Dr. Paul Netalisile Malunda 14 Steps involved in PERT/CPM project planning • Dummy activities are not real activities and thus will not actually be performed during the project. A dummy activity has a time of zero. They are used primarily to maintain the precedence relationships required in the network.
6/18/2018 Dr. Paul Netalisile Malunda 15
Benefits of PERT/ CPM • Provides a graphical view of the project. • Predicts the time required to complete the project. • Shows which activities are critical to maintaining the schedule and which are not. • It is a tool for decision-making meaning it can tell us what to do and activities that we are likely to phase out.
6/18/2018 Dr. Paul Netalisile Malunda 16
Benefits of PERT/ CPM • It tells us what we can do to speed up project or save on cost and time. • It is a very important tool for monitoring, evaluation and supervision. • It tells us the activities that are important and critical.
6/18/2018 Dr. Paul Netalisile Malunda 17
Assumptions • It assumes that we know the logic. • It assumes that we know the time(sometimes your time can be pessimistic, optimistic, and average). • It assumes that the activities can be drawn graphically.
6/18/2018 Dr. Paul Netalisile Malunda 18
Limitations • Data is sometimes not available. • Lack of expertise. • The determination of the project schedule is at most an academic guess work. • Resources may be scarce. The path assumes all resources are there. • There’s a tendency of rounding up especially on time (ignoring the seconds etc on the time) 6/18/2018 Dr. Paul Netalisile Malunda 19 Limitations • It assumes no external interference (market, available, technology same, no inflation etc) • It assumes available resources.
6/18/2018 Dr. Paul Netalisile Malunda 20
Why projects fail • Projects fail for a number of reasons. • The most important reason is that those involved do not take project scheduling seriously. • Usually the inexperienced personnel who may be involved do not comply with procedure
6/18/2018 Dr. Paul Netalisile Malunda 21
Exercise Activity Preceding Duration Activity J: negotiating - 6 distribution K: arrange publicity J 5 L: write screen play - 3 M: Hire Cast and Crew L 5 N: Shoot and edit M, Q 4 P: Design Sets L 2 Q: Build Sets P 1 6/18/2018 Dr. Paul Netalisile Malunda 22 Exercise • Required: • (a)Draw the network diagram for the above- mentioned project • (b) Determine the critical path and its duration.