Professional Documents
Culture Documents
Execution Phase Reviews
Execution Phase Reviews
Purpose
Background
EPR Scope
Responsibilities
Way Forward
EPR’s relate only to major projects (i.e. where BHPB’s share of the
investment exceeds the Group Approval Threshold which is currently
US$250 million)
EPR’s are conducted for major projects in execution phase generally
where BHPB is the operator. However there could be exceptions
where non-BHPB operated projects are also subject to EPR’s e.g.
Alumar & Samarco
EPR’s are conducted regularly at 3 to 4 month time intervals in
association with technical experts from RBO.
PMS undertakes the following EPR’s:
• Baseline Review – to ensure that the project is set-up properly and
within 3 months of project approval
• Intermediate Reviews - to assess, among other things, the health
of the project (Healthy, Observation or Critical) and alignment with
the project KPI’s. Generally, these reviews are held once every 4
months
• Pre-operations Review – no later than 3 months prior to start-up.
Background (cont.)
GAS’s audit of the Execution Phase for projects examines:
Area Details GAS PMS
1 Vendors appropriately approved
2 Procurement in a Competitive Environment
3 Payments to suppliers
5 Purchase Orders
6 Masterfile information
8 Continued Supply
10 Supply Liabilities
13 Monthly Report
14 Risk Management
19 Progress calculation
22 Execution Approvals
Safety:
• Confirm project execution is as per the Project HSEC Plan Yes
• Review major safety issues & how they are addressed Yes
•Confirm site safety by undertaking site visits & walkthroughs
Project Scope:
• Confirm project scope being executed is as per the Project Scope of Yes
Work document approved at the end of the definition phase
• Review variations, if any, to both project scope and internal scope Yes
and confirm proper authorisation thereof.
• Verify all scope changes (project & internal) are authorised as per Yes
approved project authority limits.
Execution:
• Confirm the execution strategy & plan adopted to execute the project Yes
is as per the Project Execution Strategy & Project Execution Plan
documents approved at the end of the definition phase.
• Ensure that all the key procedures are in place as identified at the Yes
end of the definition phase.
EPR Scope & Responsibility (cont.)
Engineering (cont.):
• Review actual engineering progress vs. plan vs. forecast. Yes
• Review the status of formal execution of documents for contracts & Yes
entered into CCR.
EPR Scope & Responsibility (cont.)
EPR Scope PMS GAS
Construction (cont.):
• Confirm that the Project Master Schedule and other associated Yes
schedules including contractors’ schedules are an accurate reflection
of the project status (current) from a schedule perspective.
• Confirm that the project completion milestone and other key Yes
intermediate milestone dates are a true & fair representation of
reality.
• Review Schedule Contingency to ensure that it accurately Yes
represents the outstanding risks & uncertainties.
• Review the status of critical & near critical activities & actions Yes
Project Controls – Cost Control
• Confirm that the forecast final cost (FFC) at the overall project level Yes
and at the individual WBS & Package levels are a true & fair
representation of reality.
• Confirm that Project Contingency accurately reflects the outstanding Yes
risks & uncertainties
• Confirm cost control including budgetary control & commitments are Yes Yes
as per the Project Cost Control Plan approved at the end of
definition phase.
EPR Scope & Responsibility (cont.)
EPR Scope PMS GAS
Quality:
• Confirm that quality management as per the Project Quality Yes
Management Plan approved at the end of definition phase.
• Verify major defects & non-conformances & actions for rectification
including inspection, supervision & training etc.
Project Accounting
• Verify and confirm payments to suppliers and contractors have been Yes
authorised as per the approved project authority limits.
• Confirm that a commitment (P.O. or Contract) exists prior to making Yes
a payment.
• Verify and confirm that back-charges from suppliers & contractors Yes
are correctly recovered in a timely fashion.
• Confirm development of the Fixed Assets Register as per the Yes
required standard / procedure.
Project Controls - Reporting
• Assess the health of the project from a cost & schedule perspective Yes
& assign watchlist status as Healthy, Observation or Critical