SYNDICATE 5 & 6

CASE : THE CAMPUS


WEDDING
Rifqi Nur Rivai Fajar Wahyudi
29117182 29117186

SYNDICATE
David Grandisa Nanda Rasera
29117147 MEMBER 29117084

Monique Prillagia Edlyn Valmai Devina Ian Danarko


29117024 29117056 29117125
PROJECT MANAGEMENT

 Management of Projects
1. Planning = Goal setting
2. Scheduling = Relates resources to activities
3. Controlling = Monitoring Resources
PROJECT MANAGEMENT

PLANNING SCHEDULING CONTROLLING

Ojectives Project activities Monitor

Resources Start & End Times Compare

Work- break down structure Network Revise

Organization Action
QUESTIONS

 Given the activities and predence relationships


described in the (A) case, develop a network
diagram for the wedding plans.
Identify the paths, Which are critical?
What is the minimum- cost plan that meets the
April 22 date?
Normal Time Crush Time
Activity Code Predecessor Successor Crush Time
(day) Cost
Activity
Reserve church & reception hall A 1

Church notice B A 17 10 $100

Church decoration C B 3

Jane trip D 10 2 $500

Choose cake & table decoration E 2

Catering notice F E 10

Choose dress pattern G 3

Order & receive dress material H G 8 5 $25

Sewing dress I H 11 5 $600

Final fitting dress J I 2

Clean & press dress K J 2 1 $30

Making guest list L 4

Choose invitation Style M 3

Order Invitation N L,M 12 5 $35

Adressing invitation O N 4 2 $50

Mailing invitation P O 1

Sending invitation Q P 10 8

Gift for bridesmaids R 1

Reherseal S All Activity 1

The Wedding T S 1
 Minimum Cost based on mainly critical path tahat has slack value = 0
 Critical Path : L-N-O-P-Q-S-T
 Cost Of Crashing : 0 + 35 + 50 + 0 + 0 + 0 + 0 = $ 85
 Chruch notice : $ 100 , because if we don’t crash this activity , it will be incrase time
to 21 days.
 Activity D , even use normal time , the time value of activity D is lower than activity I.
So we don’t use crash time for this activity.
Order and Recerve materrial = $25
 Sewing dress = $600
Clean and Press = $ 30
 Gift from Aunt Ethel = $ 200
 Minimum cost plan = 85 + 100 + 25 + 600 + 30 -200 = $640
ASSUMPTION (1)

 When Jane was arrived , Jane must join fitting dress with
Marry because Jane is Marry’s maid of honor
 Making guest list and choose invitation style can be doing
together, and this two activities is input for order the invitation
but this two activities is not related
 Based on father statement , that Everything should be
completed by rehearseal night and that only 21 days from
now.that mean the rehearseal held on day 21 after all activities
was completed. And the wedding held on tomorrow on day 22
or 22nd April
ASSUMPTION (2)

 Activity start on 1st April


 People work for 1 days a week
 Invitations delivery on time
 Max lead time for sending invitation is 8 days
CONCLUSION

 Married marriage can be done in 22 days but by using a minimum cost $


640 dollars