Nano City:

30°North, 77°East
216 km from Delhi (aerial distance)
4 hours drive from Delhi (Indian Drive)
25 km from Chandigarh
Nano-City – Topography:
Old Delhi Fabric
Chandigarh’s Urban Fabric
Initial Program:
Please develop in teams of two (as assigned) the master 5) Municipal buildings (police, town hall)
plan for the 11,000 acres, the Phase I Stage I design for
500+ acres, and identify the full Phase I of 3500 acres. For
all groups the following program applies for Phase I, Stage I: 6) Golf Course (18 holes, world class)

1) residential for a population of 20,000 residents 7) Parks, recreation, tennis courts


– 5,000 dwelling units: 1000 upper end detached
single family houses 8) Identified freeway connection to National Highway
– 2000 townhouses
– 1000 low-rise apartments (3 story) 9) An IT campus
– 1000 studio apartments for low-income
population • Note: Each group will start with one of the following
At 40 people per acre (reasonable assumption), this should programs as the investment and development driver for
cover roughly 500 acres. We should account for 10,000 cars the initial phase. All groups will eventually include in their
(Average of 2 per residential unit). development some areas of:
– Hospital and medical center
2) Nano City Builder’s City (housing and associated services – Retail, entertainment and convention center
for the construction workers) Initial population of 4,000 – – IT industry campuses with major R&D facilities
5,000 plus strategic plan for growth is needed. – Higher education
• Traffic planning: Sabeer notes that “traffic patterns and
3) An airport (type to be described by group: for the flows have to be carefully designed so that this self
international airport you can use SFO or Oakland or San contained mini-city can be replicated 10 times without
Diego as a model, for the corporate airport use the Hayward causing a "planning nightmare“ in the future.” Please
or Concord airport as a model) plan so that the traffic nightmare is not a future outcome
of the design. Light rail, trolleys, etc: 20,000 people
4) Schools: begin with numbers based on typical USA initially do not justify a light-rail system or a subway, but
standards space for a future over ground transportation system
should be planned from the very beginning.
– one primary school per 5,000 residents
• For groups I, II and III, only 1 village (in the south) will
– one middle school per 10,000 residents remain. Group IV can retain as many villages as they
– one high school per 12,000 residents determine is reasonable and good for the city.
3) Schools

Detailed Program
 we will begin with numbers based on typical USA standards modified
by the Indian standards
Two primary (that includes middle schools in the Indian context)
private schools, and one public School, 3 acres for a total of 9 acres.
All three must be well located with walking distances in the residential
neighborhoods.
One Private residential high school for a total of 10 acres.
Stage one must include the following: One Private or public high school for a total of 5 acres.
1) Residential One college with the capacity to expand to be a university in first stage
For a population of 15-16,000 residents in around 4,000 dwelling units: only 20 acres to become 100 in stage two of phase one.
100 one acre lots (60x60m) total of 100 acre Total Educational facilities are 45 acres for stage one, with an
additional 80 for stage two
200 1/2 acre lots (30x60m) total of 100 acres
200 1/4 acre lots (15x60m) total of 300 acres 4) Service Buildings
800 1/8 acre lots (20x30m) total of 100 acres One police station -1 acre
2400 1/16 acre lots (10x30) total of 150 acres One fire station -1 acre
500 luxury apartments -300 square meters- in residential towers 10-15 One post office - 1 acre
stories high at a density of 50 persons per acre for a total of 50 acres- One Municipal /government building 2 acres
including10 acres for services/parking One Administration building 2 acres
500 Attached townhouses on medium size lots 20x30 meters for up One Nano City Inc. Headquarters- 10 acres
middle income families at a total of 75 acres One Electric substation -2 acres
500 mid-rise apartments -150 square meters- for middle income families One electric grid station- 2 acres
(3-5 floor walk-ups) at a density of 60 person per acre for a total of 40 One water treatment plant 2-4 acres
acres including parking One sewage treatment facility 4-6 acres
500 small two bedroom apartments for low-income families at a density of Five religious centers each one acre- 5 acres
70 person per acre for a total of 30 acres including parking One Hospital on 10 acres with the capacity to expand to be an
500 studio apartments accommodating non family households -1000 International Medical Center in stage two of phase one to become a
square meters in 4 floor walkup apartment blocks at a density of 60 100 acres.
persons per acre for a total of 30 acres. Total services facilities are 45 acres for stage one, with an
500 small rental units acting as the initial core for Nano City Builder's City additional 90 for stage two
for the construction workers at a density of 80 persons per acre for a total
of 25 acres 5) Golf Course and Recreation Facilities
This comes to a total residential land of 1000 acres for Stage one, not 18 holes world class course - 150 acres
including any services (like schools, parks, or grocery stores) but Two Neighborhood clubs 5 acres each -10 acres
including open spaces between the units which can also function as One Banquet Hall with Parking - 5 acres
green space.  And additional 1000 acres of residential following the Total for Recreation is 165 acres
same formula will also happen in stage two of phase one.
6) An IT Park
2) Commercial and Business A small IT campus with 100 acres for one or two companies and their
-A commercial spine of mixed uses and multi-storey structures with retail R&D in stage one, and expanding in stage two to develop a special
shops and restaurants at the ground floor and businesses above in
structures of different heights 5-20 floors. campus for Samsung (400 acres)
Initially is should occupy 30 acres only (including 5 for a major super Total in Stage one for IT is 100 acres only, with an additional 400
market and the Nano Mall with one anchor store, and 5 acres for for stage two
parking).  The spine should have the capacity to expand in stage two to
be 60 acres. This is a very precise estimate of what is needed for stage one with a
-4 Neighborhood Grocery Stores of one acre each total of 1390-1400 acres for stage one with all the new functions
Total for Commercial is 34 acres for stage one, with an additional 30 now required. Stage two of phase one is an expansion from the
acres for stage two first core and should be another 1600 acres for a total of 3000.
Stage three of phase one will be another 2000 acres mainly
residential, IT, and commercial expansion following similar
proportions.