Paper IV : Part 2

Oral Presentation
Report of Hazards
In the construction site of
Nestle Manufacturing (M)
Sdn Bhd
PREPARED BY:
INDEX NO: NS13202
IC NO: 860902-26-5017
Introduction
WM Link Construction Sdn Bhd

Located at Puchong and operates more than 14 years


G7 category construction company
Involves in civil engineering and building construction
Involves in construction works at Nestle, Toyota, Pure Circle & etc

Workplace: Nestle Manufacturing (M) Sdn Bhd

Work activity: New sewer line and manhole construction


(Focus on excavation activity)
Objective
•Identify at least 4 safety and 2 health hazards that occur at
workplace during the excavation work
•Explain in detail about hazard identification method and risk
assessment
•To carry out risk assessment on the hazards that have been
identified, prioritize these hazards based on risk rating and
determine the most critical safety and health hazards in the
construction work
•To suggest and discuss the control measures to eliminate or
reduce the risk of both critical hazards.
•To review the effectiveness of the recommended control
measures
Methodology

Hazard Identification

•Observation and inspection


•Document review
•Discussion or interview with workers and staff
Risk = Likelihood x Severity

LIKELIHOOD (L) EXAMPLE RATING

Most likely The most likely result of the hazard / event being 5
realized
Possible Has a good chance of occurring and is not unusual 4

Conceivable Might be occur at sometime in future 3

Remote Has not been known to occur after many years 2

Inconceivable Is practically impossible and has never occurred 1

(Cited from Guidelines for HIRARC, DOSH)


SEVERITY (S) EXAMPLE RATING
Catastrophic Numerous fatalities, irrecoverable property damage 5
and productivity
Fatal Approximately one single fatality major property 4
damage if hazard is realized
Serious Non-fatal injury, permanent disability 3
Minor Disabling but not permanent injury 2
Negligible Minor abrasions, bruises, cuts, first aid type injury 1

(Cited from Guidelines for HIRARC, DOSH)


RISK MATRIX – RISK ASSESSMENT

Severity (S)
gertrtergtrrtertsgf
Likelihood (L) 1 2 3 4 5
5 5 10 15 20 25
4 4 8 12 16 20
3 3 6 9 12 15
2 2 4 6 8 10
1 1 2 3 4 5

High Need immediate action to control the hazard

A planned approach to control the hazard and temporary measure


Medium if required

Low Low may considered as acceptable and future reduction may not
necessary
FINDINGS AND DISCUSSION
Safety Hazard
No Work Activity Hazard Which Existing Risk Likeli Seve Risk
can Control (if any) hood rity
cause /
effect
1 Excavate in Workers Serious / - Cordon off 4 3 12
depth falling into minor - Well trained &
between excavation injury experienced
900mm to worker
1100mm - SOP
- PPE
No Work Activity Hazard Which Existing Risk Likeli Seve Risk
can Control (if any) hood rity
cause /
effect
2 Dispose away Struck by Serious / - Place choke 2 3 6
the waste falling / minor for lorry
concrete and flying object injury - Removal of
extra soil off materials
site using from edge
backhoe and of
lorry excavated
area
3 Excavate in Trapped by Minor - PPE 2 2 4
depth collapse of injury - Close
between earth / supervision
900mm to materials
1100mm
No Work Activity Hazard Which Existing Risk Likelih Seve Risk
can Control (if any) ood rity
cause /
effect
4. Cut using Struck by Serious / - Appoint a traffic 2 4 8
road cuter construct minor controller
and hack off ion injury - No workers
the existing vehicle allowed to work
concrete road or plant surrounding
using backhoe areas
breaker - Close
supervision at all
times
Health Hazard
No Work Hazard Which can Existing Risk Likeli Seve Risk
Activity cause / Control (if any) hood rity
effect

1 Excavate in Heat stress Heat - Rotation of 3 2 6


depth stroke, workers
between exhaustion
900mm to , heat
1100mm rashes

2 Cutting of Dust Coughing, - Provision of dust 2 2 4


existing RC sneezing, mask for
slab irritation to workers
eyes
No Work Activity Hazard Which Existing Risk Likeli Seve Risk
can Control (if any) hood rity
cause /
effect

3 Excavate in Ingress Insect, - Suspension of 1 4 4


depth of water snake work during
between causing bite raining
900mm to flooding
1100mm
RECOMMENDATION ON CRITICAL SAFETY
HAZARD
Hazard Recommendation

Workers falling Engineering Control


into excavation
•Suitably designed and construct physical barriers (safety fences /
covers)
•Benching or shoring the sides of the excavation to reduce the risk of
ground collapse
RECOMMENDATION ON CRITICAL SAFETY HAZARD

Hazard Recommendation

Workers falling into Administrative Control


excavation
•Manage traffic while the work takes place with a temporary
traffic management plan
•Educate workers by providing training on safe work procedures
•Workers can be required to use standardized safety practices
•Adequate signage to warn of hazards
•Provide safe access and egress into the pit
•Construction work only allowed during day time

PPE

•Provision and implementation of compulsory PPE such as hard


hat, safety shoes, goggles, hearing protections and high visibility
vests
RECOMMENDATION ON CRITICAL HEALTH HAZARD

Hazard Recommendation

Heat stress Engineering Control

•Reduce manual handling by providing mechanical aids for


workers to minimize physical demand on them.
RECOMMENDATION ON CRITICAL HEALTH HAZARD
Hazard Recommendation

Heat stress Administrative Control

•Implement buddy system and avoid working alone


•Allowing time for acclimatization starting with a lower workload / shorter
working duration and gradually increases the workload or duration of work
•Advise workers to drink more water and eat more rich fiber fruits like
watermelon
•Setup shelter or sunshade over the working place where applicable
•Inform workers about the symptoms of heat related illnesses and advise to
inform to supervisor if they have any symptoms or inform to supervisor if they
notice any symptoms in another worker

PPE

•Recommend use of light-colored safety helmet, wear wide-brimmed hat to block


away sunlight on the face and neck
Review Program
Control measure can be reviewed periodically including the activities arising from:

Workplace inspection
Routine maintenance
Safety and health committee meeting
Safety and health campaign
Employee feedback through interviews, and suggestion box
Analysis of accident record

Benefit to the company:

Reduction in loss time injury


Increase of health and safety awareness among employees
Reduce property damage cost
Reduce risk at work place
Reduce accident cost
THANK YOU