Download as pptx, pdf, or txt
Download as pptx, pdf, or txt
You are on page 1of 10

Progress Update

KEC INTERNATIONAL LIMITED


220/66/11 KV GIS ITI PROJECT
BESCOM, ITI GATE , DOORVANI NAGAR
KR PURAM , BANGALLORE.
KARNATAKA -560016.
220 /66/11 KV ITI GIS PROJECT

220 KV GIS HALL

Brick work and plastering Completed Expect Parapet wall, EOT Crane ,HVAC Erection Under progress,
windows frame fixing completed.
220 /66/11 KV ITI GIS PROJECT

Control room Building

Control room Building :Three floors Roof Slab Completed, Ground floor Brickwork and Internal plastering
completed,
220 /66/11 KV ITI GIS PROJECT

66 KV GIS HALL

Brick work and plastering Under Progress.


220 /66/11 KV ITI GIS PROJECT

Transformer

2 Nos 150 MVA POWER TRANSFORMER ERECTION COMPLETED


220 /66/11 KV ITI GIS PROJECT

Cable Trench

Out door Cable Trenches


7

220/66/11 KV GIS ITI PROJECT

Project Current
Description
Milestone Target Date
Milestone 1 10th OCT, 2018
66 kV GIS Erection
Milestone 2 25th OCT, 2018
66 kV GIS Commissioning
Milestone 3 15th Sep, 2018
220 kV GIS Erection
Milestone 6 20th Oct, 2018
220 KV GIS Commissioning
Milestone 7 150 MVA Transformer Commissioning
25th Oct, 2018
Milestone 8 66 kV GIS commissioning by 150 MVA
26th Oct, 2018
S.No Description 220 KV GIS 66 KV GIS Control Room Building

1 Brickwork + plastering Completed 20.08.2018 Ground floor -18.08.2018

First Floor -24.08.2018

Second Floor-30.08.2018

2 Putty + Painting 11.08.2018 25.08.2018 ground Floor -25.08.2018

First Floor-30.08.2018

Second Floor-30.08.2018

3 EOT Crane 17.08.2018 29.08.2018 Not Applicable

4 HVAC Erection 20.08.2018 1.09.2018

4 Illumination Completed Completed ground Floor -25.08.2018

First Floor-30.08.2018

Second Floor-03.09.2018

5 Doors Windows fixing 23.08.2018 10.09.2018 GF- 27.08.2018

FF-02.09.2018

SF-13.09.2018
S.No Description 220 KV GIS 66 KV GIS Control Room Building

6 RCC Flooring Completed 25.08.2018 20.08.2018

7 IPS Flooring 21.08.2018 08.09.2018 ground floor- 25.08.2018

` NA NA First Floor-30.08.2018

Flooring works NA NA second floor-10.09.2018

8 Internal cable Ducts Fabrication works 25.08.2018 05.09.2018 Ground floor 25.08.2018

First floor 30.08.2018

Second Floor -05.09.2018

9 Panel Erection

CRP 30.08.2018 05.09.2018

LCC 26.08.2018 05.09.2018

LT Switch Gear 10.09.2018

10 GIS Erection 15.09.2018 15.10.2018 Not Applicable

Battery/battery charger Installation &


11 Comissioning 10.09.2018
S.No Description 220 KV GIS 66 KV GIS Control Room Building

12 Control cable laying & Termnation. 30.09.2018

13 Testing and comissioning activites 30.10.2018

14 Out door Cable Trench 12.08.2018 20.08.2018 30.08.2018(11 Kv)

15 Road 3.5 Meter 30.08.2018

Road 5 meter 18.08.2018

Road 7.5 meter 30.08.2018

16 Drains 25.09.2018

17 L M TOWER Foundation 30.09.2018

18 220 KV CTT Tower 29.08.2018

19 66 KV CTT Tower Not Applicable Completed Not Applicable

20 Fire wall 12.08.2018

You might also like