Professional Documents
Culture Documents
Cabel Stayed
Cabel Stayed
Cabel Stayed
A typical cable stayed bridge is a continuous girder with one or more towers
erected above piers in the middle of the span. From these towers, cables stretch down
diagonally (usually to both sides) and support the girder
•This list of the largest cable-stayed bridges ranks the world's cable-stayed bridges by
the length of main span (distance between the suspension towers). The length of the
main span is the most common way to rank cable-stayed bridges.
•However, the size of the main span does often correlate with the eight of the towers
and the engineering complexity involved in designing and constructing the bridge
•Cable-stayed bridges with more than three spans are generally more complex, and
bridges of this type generally represent a more notable engineering achievement even
where their spans are shorter.
Rank Name Country Longest span Comp. year Paylons
1 Sutong Bridge Republic of China 1,088 m 2008 2
Yamuna Bridge at
Allahabad India 260m 2000 3
Case study
Yamuna Bridge at Allahabad
SITE DATA
Location: latitude 25˚77’N longitude 81˚44’N
Catchment area: 368302 km²
Highest flood level:88.000m
Lowest bed level:66.139m
Low water level:71.119m
MODULE 1
Foundation
Pylon and pier
Cable stayed
Deck
Foundation
Foundation
Six well foundation in reinforce concrete (P15-P20) are provided for this module, with
depth of about 40m in general.
All this foundation are located in deep channel of river with maximum depth of about
22m at HFL.
The foundation level is kept same for all 6 wells, at a depth of 59.0m below
HFL,37.1m below lowest bed level.
Pylon Well
dsf
15.0m
30.0m
13m
Pylon Dimensions & Reinforcement
Fig. 4a 4b
Pier:
Reinforced concrete twin pier columns each with independent foundation are provided
under each deck beam.
Height of pier: 23.4 – 25.9m
Hexagonal section 3.5m wide and 3.0m thick.
FIG. 5
Pier Section
Cable stays
1 Stay arrangement
A fan arrangement was selected for cabel
2 Anchorage
Stays are carried inside the girder through a steel
pipe which project 1.8 m above deck and is closed
by a neoprene sleeve fixed with stainless steel
clamping bands. Neoprene dampers are also housed
in the pipe.
At upper anchorage at pylon top the stays
are anchored into steel plates protruding from pylon
by fork socket.
DECK
1 Section
The stayed deck has a simple familiar pre stressed concrete π beam section with low
depth. The main span was 260m.
2 Dimension
• The stayed part of the deck module 1 extending from P16 to P19 has a uniform
Longitudinal Girder with tendon position Cross Girder with tendon position
Fig 13
Fig 14
MODULE 2
(SHALLOW CHANNEL BRIDGE)
A post-tensioned π beam deck continuous over 9 simple supports spaced deck
continuous over 9 simple supports.
Supports are spaced at 60.0 m.
The deck configuration is retained same as for module 1.
Reinforced concrete twin hexagonal piers are provided with independent well
foundation of 7.5m dia.
Fig 15
FIG 16
CONCLUSION
The design of bridge project has realized the prime objective of promoting
appropriate technology and environment compatibility.
The 600 m deep channel crossing of the project applies to many large river
crossing in India.
A large span of 250 meter could act as an alternative solution to protect our
scared river
THANK YOU